Project · 4 RERA phases

Sobha Sentosa

Sobha Limited · Panathur Main Road / Balagere, off Outer Ring Road, East Bengaluru

RERA phases
4

each filed on its own

Flats, all phases
533

71 + 142 + 178 + 142

RERA completion
Jun 2026 to Dec 2027

first to last phase

Flat sizes
Not quoted

Phases

How do the phases compare, and which one should I look at? Each column is one registration with its own filings.

Phase 1 Wing 7

PR/310322/004796

Open report
Flats
71
RERA completion
Jun 2026
Read from each phase's own documents
Defect liability
5 years
Possession, agreement
30 Jun 2026
Interest the buyer pays on late payment
Rate prescribed in the Rules
Interest the builder pays on late possession
Rate prescribed in the Rules
Forfeiture, agreement
The booking amount

Phase 2 Wing 5 And 6

PR/310322/004797

Open report
Flats
142
RERA completion
Dec 2026
Read from each phase's own documents
Defect liability
5 years
Possession, agreement
31 Dec 2026
Interest the buyer pays on late payment
Rate prescribed in the Rules
Interest the builder pays on late possession
Rate prescribed in the Rules
Forfeiture, agreement
The booking amount

Phase 3 Wing 3 And 4

PR/310322/004798

Open report
Flats
178
RERA completion
Jun 2027
Read from each phase's own documents
Defect liability
5 years
Possession, agreement
30 Jun 2027
Interest the buyer pays on late payment
Rate prescribed in the Rules
Interest the builder pays on late possession
Rate prescribed in the Rules
Forfeiture, agreement
The booking amount

Phase 4 Wing 1 And 2

PR/310322/004799

Open report
Flats
142
RERA completion
Dec 2027
Read from each phase's own documents
Defect liability
5 years
Possession, agreement
31 Dec 2027
Interest the buyer pays on late payment
Rate prescribed in the Rules
Interest the builder pays on late possession
Rate prescribed in the Rules
Forfeiture, agreement
The booking amount

Why these are one project

  • Filed as 4 separate K-RERA registrations.
  • The same building-plan number is on file for these registrations.
  • They are filed on overlapping survey numbers.
  • They cite the same sale deed.
  • They cite the same khata.

In each phase’s own report

  • Valuation: What is it worth?
  • Title & ownership: Who owns it, and is the title clean?

The price paid, the title and the valuation are read from one phase’s filings at a time, so each phase has its own full report and its own unlock.

Everything here is as filed by the promoter with Karnataka RERA, one registration at a time, and can be stale or wrong at source. A total appears only when every phase reports the figure. Open Sobha Sentosa on the map