Project · 2 RERA phases
Subha Ecostone
Subha Luxury Projects LLP · Hennagara Main Road, Bommasandra, Electronic City Phase 2
- RERA phases
- 2
- Flats, all phases
- 203
- RERA completion
- Aug 2023 to May 2025
- Flat sizes
- Not quoted
each filed on its own
87 + 116
first to last phase
Phases
How do the phases compare, and which one should I look at? Each column is one registration with its own filings.
| Filed with K-RERA | Registered 2 Jun 2022PR/020622/004953Open report | Phase 2PR/110823/006150Open report |
|---|---|---|
| Flats | 87 | 116 |
| RERA completion | Aug 2023 | May 2025 |
| Read from each phase's own documents | ||
| Defect liability | 5 years | 5 years |
| Possession, agreement | 30 Nov 2022 | 31 May 2024 |
| Interest the buyer pays on late payment | Rate prescribed in the Rules | Rate prescribed in the Rules |
| Interest the builder pays on late possession | Rate prescribed in the Rules | Rate prescribed in the Rules |
| Forfeiture, agreement | The booking amount | The booking amount |
| Due on signing | 15% | 15% |
| Payment plan | 5 stages showhide
| 5 stages showhide
|
Registered 2 Jun 2022
PR/020622/004953
- Flats
- 87
- RERA completion
- Aug 2023
- Defect liability
- 5 years
- Possession, agreement
- 30 Nov 2022
- Interest the buyer pays on late payment
- Rate prescribed in the Rules
- Interest the builder pays on late possession
- Rate prescribed in the Rules
- Forfeiture, agreement
- The booking amount
- Due on signing
- 15%
- Payment plan
5 stages showhide
- 5% Booking advance
- 10% On agreement of sale
- 10% On completion of foundation
- 10% On completion of all amenities
- 65% At the time of execution of sale deed
Read from each phase's own documents
Phase 2
PR/110823/006150
- Flats
- 116
- RERA completion
- May 2025
- Defect liability
- 5 years
- Possession, agreement
- 31 May 2024
- Interest the buyer pays on late payment
- Rate prescribed in the Rules
- Interest the builder pays on late possession
- Rate prescribed in the Rules
- Forfeiture, agreement
- The booking amount
- Due on signing
- 15%
- Payment plan
5 stages showhide
- 5% Booking advance
- 10% On agreement of sale
- 40% On completion of foundation
- 25% On completion of all amenities
- 20% At the time of execution of sale deed
Read from each phase's own documents
Why these are one project
- Filed as 2 separate K-RERA registrations.
- The same project name and promoter, less than 500 metres apart.
In each phase’s own report
- Valuation: What is it worth?
- Title & ownership: Who owns it, and is the title clean?
The price paid, the title and the valuation are read from one phase’s filings at a time, so each phase has its own full report and its own unlock.
Everything here is as filed by the promoter with Karnataka RERA, one registration at a time, and can be stale or wrong at source. A total appears only when every phase reports the figure. Open Subha Ecostone on the map