Project · 2 RERA phases
The Icon North
Gcorp Homes Pvt Ltd · Thanisandra
- RERA phases
- 2
- Flats, all phases
- 117
- RERA completion
- May 2019 to Feb 2023
- Flat sizes
- Not quoted
each filed on its own
38 + 79
first to last phase
Phases
How do the phases compare, and which one should I look at? Each column is one registration with its own filings.
| Filed with K-RERA | Towers C, D And E Cluster IIIPR/171015/000326Open report | Tower FPR/171016/000420Open report |
|---|---|---|
| Flats | 38 | 79 |
| RERA completion | May 2019 | Feb 2023 |
| Read from each phase's own documents | ||
| Defect liability | 5 years | 5 years |
Towers C, D And E Cluster III
PR/171015/000326
- Flats
- 38
- RERA completion
- May 2019
- Defect liability
- 5 years
Read from each phase's own documents
Tower F
PR/171016/000420
- Flats
- 79
- RERA completion
- Feb 2023
- Defect liability
- 5 years
Read from each phase's own documents
Why these are one project
- Filed as 2 separate K-RERA registrations.
- The same project name and promoter, less than 500 metres apart.
In each phase’s own report
- Valuation: What is it worth?
- Title & ownership: Who owns it, and is the title clean?
The price paid, the title and the valuation are read from one phase’s filings at a time, so each phase has its own full report and its own unlock.
Everything here is as filed by the promoter with Karnataka RERA, one registration at a time, and can be stale or wrong at source. A total appears only when every phase reports the figure. Open The Icon North on the map