Overview
10 ACRES (AFFORDABLE GROUP HOUSING PROJECT)
GLS INFRATECH PVT LTD · Gurugram
Completion2020-04-10Revised
Registered on2017-09-19
Valid to2020-04-12
Approvals13
Sections
| Property title & search report | |
|---|---|
| Approvals | 13 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 2 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 15 documents · 2 source links |
Registration
Registration
| Promoter | GLS INFRATECH PVT LTD | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 232 OF 2017 DATED 19.09.2017 | |
| Registered on | 2017-09-19 | |
| Valid to | 2020-04-12 | |
| Status (as filed) | Registered | |
| Revised completion | 2020-04-10 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 110 of 2014 (14-08-2014)) | Town & Country Planning Department | |
| Layout Plan | 2014-09-24 | ||
| Building Plan | 2014-09-24 | ||
| I. BUILDING PLAN APPROVAL | 2014-10-01 | ||
| II. ENVIRONMENT CLEARANCE | 2016-04-12 | ||
| III. FIRE SCHEME APPROVAL | 2015-11-24 | ||
| IV. FOREST | 2014-09-01 | ||
| V. WATER SUPPLY ASSURANCE | 2014-09-03 | ||
| VI. HEIGHT CLEARANCE | 2014-09-11 | ||
| VII. POLLUTION | 2016-06-16 | ||
| VIII. POWER LOAD ASSURANCE | 2014-09-29 | ||
| IX. ARAWALI NOC | 2014-12-01 | ||
| X. WATER NOC | 2015-12-07 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹38,79,00,000 | |
|---|---|---|
| Construction | ₹1,55,42,60,000 | |
| Total | ₹2,74,56,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 22.299 |
|---|
Unit types
| Type |
|---|
| 1 |
| 2 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2016-04-15 | |
|---|---|---|
| Revised completion | 2020-04-10 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GLS INFRATECH PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | YES BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1009
- Registration Certificate · 2017-09-19
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2019-11-30 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-11-29
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-11-29 · Sign in to download
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-11-30
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2019-11-30 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-11-30
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-11-30
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2019-11-30 · Sign in to download
- DRAFT ALLOTMENT LETTER · 2019-11-30 · Sign in to download
- DRAFT ALLOTMENT LETTER · 2019-11-30 · Sign in to download
- EXTENSION NO. HARERA/GGM/REP/RC/232/2O17/EXT/179/2019 DATED-30.12.2019 · 2020-05-30 · Sign in to download
- OC uploaded · 2023-08-04 · Sign in to download
- OC Uploaded · 2023-08-08 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download