Overview
2.425 ACRES COMMERCIAL COLONY
OJOS DEVELOPERS PVT. LTD. · Gurugram
Completion2020-12-31Revised · Proposed 2020-12-31
Registered on2017-08-10
Valid to2020-12-31
Approvals17
Sections
| Property title & search report | |
|---|---|
| Approvals | 17 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 2 unit types |
| Construction & progress | 3 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 55 documents · 3 source links |
Registration
Registration
| Promoter | OJOS DEVELOPERS PVT. LTD. | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 38 OF 2017 DATED 10.08.2017 | |
| Registered on | 2017-08-10 | |
| Valid to | 2020-12-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2020-12-31 | |
| Revised completion | 2020-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 131 of 2008 | Town & Country Planning Department | |
| Layout Plan | 2015-11-03 | ||
| Building Plan | 2015-11-03 | ||
| I. APPROVAL OF ZONING PLAN | 2014-12-09 | ||
| II. ENVIRONMENT CLEARANCE | 2016-03-15 | ||
| III. CONSENT TO ESTABLISH FROM ANGLE OF AIR & WATER POLLUTION FROM HARYANA STATE POLLUTION CONTROL BOARD. | 2016-03-29 | ||
| IV. NOC FROM AIRPORT AUTHORITY | 2016-02-01 | ||
| V. NOC FOREST CLARIFICATION REGARDING NON FOREST LAND | 2015-11-02 | ||
| VI. ARAVALI HILL CLEARANCE | 2016-01-13 | ||
| VII. NOC FROM HUDA FOR USE OF WATER FOR CONSTRUCTION OF THE PROJECT | 2016-08-30 | ||
| VIII. FIRE SCHEME | 2016-03-03 | ||
| IX. NOC APPLICABILILITY OF WILD LIFE LAWS | 2016-03-02 | ||
| X. SERVICE PLAN /ESTIMATE | 2016-10-03 | ||
| XI. PERMISSION /NOC FOR CONSTRUCTION OF RAIN WATER HARVESTING STRUCTURE. | 2018-05-09 | ||
| XII. FIRE NOC | 2019-05-01 | ||
| XIII. OCCUPATION CERTIFICATE | 2019-09-11 | ||
| XIV. CONSENT TO OPERATE | 2019-11-22 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,15,71,000 | |
|---|---|---|
| Construction | ₹1,17,05,88,000 | |
| Total | ₹1,64,87,90,000.0000002 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 9,813.62 | |
|---|---|---|
| FAR | 175 |
Unit types
| Type |
|---|
| 1 |
| 2 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2016-06-30 | |
|---|---|---|
| Proposed completion | 2020-12-31 | |
| Revised completion | 2020-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | OJOS DEVELOPERS PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK LTD | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/973
- https://nominatim.openstreetmap.org/search?q=sector+70%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2017-08-10
- APPROVED SERVICE ESTIMATE · 2019-11-28 · Sign in to download
- BALANCE SHEET OF LAST 3 YEARS · 2019-11-26 · Sign in to download
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2019-11-27 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-11-27
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-11-26 · Sign in to download
- APPROVAL OF FIRE SCHEME · 2019-11-28
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-11-27
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2019-11-27 · Sign in to download
- ROAD LAYOUT · 2019-11-28 · Sign in to download
- BASEMENT 2 PLAN · 2019-11-29
- ELEVATION- 2 · 2019-11-29 · Sign in to download
- SECOND FLOOR · 2019-11-29 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2019-11-26
- ARCHITECT'S CERTIFICATE · 2019-11-30 · Sign in to download
- OCCUPATION CERTIFICATE · 2019-11-26 · Sign in to download
- WATER SUPPLY APPROVAL · 2019-11-28
- 4TH, 5TH AND 8TH FLOOR PLAN · 2019-11-29
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-11-27
- WATER SUPPLY LAYOUT · 2019-11-28 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-11-27
- AGREEMENT FOR SALE DRAFT · 2019-11-27 · Sign in to download
- MAZZANINE FLOOR PLAN · 2019-11-29
- ZONING PLAN · 2019-11-27
- STORM WATER DRAINAGE LAYOUT · 2019-11-28 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2019-11-26 · Sign in to download
- SEWER LAYOUT · 2019-11-28 · Sign in to download
- SECTIONS · 2019-11-29 · Sign in to download
- THIRD FLOOR PLAN · 2019-11-29
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2019-11-26 · Sign in to download
- FIRST FLOOR PLAN · 2019-11-29
- 6TH, 7TH, 9TH, 10TH AND TERRACE FLOOR PLAN · 2019-11-29
- ELEVATION -1 · 2019-11-29 · Sign in to download
- TOILET PLAN · 2019-11-29
- BASEMENT 1 PLAN · 2019-11-29
- GROUND FLOOR PLAN · 2019-11-29
- ENGINEER'S CERTIFICATE · 2019-11-30 · Sign in to download
- CERTIFICATE OF INCORPORATION · 2019-11-30 · Sign in to download
- SATYENDER PARASH · 2019-11-30 · Sign in to download
- GROUND FLOOR AS BUILD PLAN · 2019-11-30
- 4TH, 5TH AND 8TH FLOOR AS BUILD PLAN · 2019-11-30
- FIRE NOC · 2020-01-31
- LC-IV · 2020-01-31 · Sign in to download
- CLARIFICATION OF APPLICABILITY OF FOREST LAWS - NOC · 2020-01-31
- NON ENCUMBRANCE CERTIFICATE · 2020-01-31 · Sign in to download
- FOREST AND ARAVALI NOC · 2020-01-31
- SITE PLAN · 2020-01-31
- DEMARCATION PLAN · 2020-01-31
- NOC FOR WILD LIFE DEPTT. REG. APPLICABILITY OF WILD LIFE LAW · 2020-01-31
- OCCUPATION CERTIFICATE · 2020-01-31 · Sign in to download
- ENVIRONMENT CLEARANCE · 2020-01-31
- NOC FROM AIRPORT AUTHORITY · 2020-01-31
- DEMAND DRAFT · 2020-02-06 · Sign in to download
- OC uploaded · 2023-09-12 · Sign in to download
- CC uploaded · 2023-09-12 · Sign in to download