Overview
81 HIGH STREET
PURI CONSTRUCTION PVT LTD. · Faridabad
Units8,025
Completion2018-11-02Revised · Proposed 2018-11-02
Valid to2018-11-02
Approvals4
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Disputes & cases | 1 case · 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 8 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 11 documents · 3 source links |
Registration
Registration
| Promoter | PURI CONSTRUCTION PVT LTD. | |
|---|---|---|
| District | Faridabad | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-FBD-42-2018 | |
| Valid to | 2018-11-02 | |
| Status (as filed) | Lapsed Project | |
| Proposed completion | 2018-11-02 | |
| Revised completion | 2018-11-02 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 1069-1070 of 2006 Transferred on 11-02-2009 | Town & Country Planning Department | |
| Layout Plan | 2018-06-12 | ||
| Building Plan | 2018-06-12 | ||
| I. OCCUPATION CERTIFICATE RECEIVED | 2018-11-02 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Status |
|---|---|---|
| RERA-PKL-1783-2022 | HRERA Panchkula | Disposed |
Complaints & cases
| Cases | 1 |
|---|
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2018-11-02 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹24,98,60,000 | |
|---|---|---|
| Construction | ₹78,31,05,000 | |
| Total | ₹1,24,90,68,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 15,402.19 | |
|---|---|---|
| Units | 8,025 |
Unit types
| 1 | 265 |
| 2 | 465 |
| 3 | 500 |
| 4 | 530 |
| 5 | 600 |
| 6 | 785 |
| 7 | 880 |
| 8 | 4,000 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2018-11-02 | |
|---|---|---|
| Revised completion | 2018-11-02 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PURI CONSTRUCTION PVT LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | UCO BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/SFJFUkEtUEtMLUZCRC00Mi0yMDE4
- https://haryanarera.gov.in/view_project/project_preview_open/976
- Registration Certificate
- OCCUPATION CERTIFICATE · 2019-11-27 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-11-27 · Sign in to download
- DRAFT BBA · 2019-11-27 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2019-11-27
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-11-27
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-11-27
- RERA REGISTRATION CERTIFICATE · 2019-11-27 · Sign in to download
- SPECIFICATIONS · 2020-03-02 · Sign in to download