DOSLBihar Workspace

Overview

A.S TOWER

MITTAL INFRASPACES · Bhagalpur
Booked3As of 2026-09-30
Construction progress64%As of 2026-09-30
Completion2028-01-16Proposed
Registered on2023-06-13
Valid to2028-01-16
Approvals5

Sections

Property title & search report
Approvals5 approvals
Contract & costs1 cost head
Technical report
Site & area6 site details
Construction & progress4 progress details · 14 quarters
Developer & finance
Developer4 developer details
The evidence
Sources30 documents · 19 source links

Registration

Registration

PromoterMITTAL INFRASPACES
DistrictBhagalpur
RegulatorRERA Bihar
Registration numberBRERAP81137-002/61/R-1577/2023
Registered on2023-06-13
Valid to2028-01-16
Project typeCommercial
Status (as filed)RERA Registered Projects
Proposed completion2028-01-16