Overview
Aaniket Pramila Palace
Aaniket Homes Private Limited · Patna
Units32
Completion2021-11-24Proposed
Registered on2018-11-01
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 8 unit types |
| Construction & progress | 2 progress details · 18 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 28 documents · 22 source links |
Registration
Registration
| Promoter | Aaniket Homes Private Limited | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00797-1/582/R-239/2018 | |
| Registered on | 2018-11-01 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2021-11-24 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,20,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,545.59 | |
|---|---|---|
| Built-up (m²) | 3,050.02 | |
| FAR | 1.96 | |
| Towers | 1 | |
| Units | 32 |
Unit types
| 3 BHK | 3 | Aaniket Pramila Palace |
| 3 BHK | 3 | Aaniket Pramila Palace |
| 2 BHK | 6 | Aaniket Pramila Palace |
| 3 BHK | 6 | Aaniket Pramila Palace |
| 3 BHK | 6 | Aaniket Pramila Palace |
| 3 BHK | 1 | Aaniket Pramila Palace |
| 3 BHK | 1 | Aaniket Pramila Palace |
| 3 BHK | 6 | Aaniket Pramila Palace |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-11-25 | |
|---|---|---|
| Proposed completion | 2021-11-24 |
Quarterly progress
| 2023-Q1 | 2023-04-14 |
| 2022-Q4 | 2023-02-10 |
| 2022-Q3 | 2023-02-10 |
| 2022-Q2 | 2022-07-18 |
| 2022-Q1 | 2022-04-24 |
| 2021-Q4 | 2022-01-27 |
| 2021-Q3 | 2021-10-11 |
| 2021-Q2 | 2021-07-27 |
| 2021-Q1 | 2021-04-20 |
| 2020-Q4 | 2021-02-02 |
| 2020-Q3 | 2020-11-05 |
| 2020-Q2 | 2020-10-02 |
| 2020-Q1 | 2020-10-02 |
| 2019-Q4 | 2020-01-13 |
| 2019-Q3 | 2019-10-22 |
| 2019-Q2 | 2019-07-24 |
| 2019-Q1 | 2019-01-31 |
| 2018-Q4 | 2019-01-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Aaniket Homes Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | FEDERAL BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP318201800797-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP318201800797-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q4-Jan to Mar / 2022-2023 · 2023-04-14
- Q3-Oct to Dec / 2022-2023 · 2023-02-10
- Q2-Jul to Sep / 2022-2023 · 2023-02-10
- Q1-Apr to Jun / 2022-2023 · 2022-07-18
- Q4-Jan to Mar / 2021-2022 · 2022-04-24
- Q3-Oct to Dec / 2021-2022 · 2022-01-27
- Q2-Jul to Sep / 2021-2022 · 2021-10-11
- Q1-Apr to Jun / 2021-2022 · 2021-07-27
- Q4-Jan to Mar / 2020-2021 · 2021-04-20
- Q3-Oct to Dec / 2020-2021 · 2021-02-02
- Q2-Jul to Sep / 2020-2021 · 2020-11-05
- Q1-Apr to Jun / 2020-2021 · 2020-10-02
- Q4-Jan to Mar / 2019-2020 · 2020-10-02
- Q3-Oct to Dec / 2019-2020 · 2020-01-13
- Q2-Jul to Sep / 2019-2020 · 2019-10-22
- Q1-Apr to Jun / 2019-2020 · 2019-07-24
- Q4-Jan to Mar / 2018-2019 · 2019-01-31
- Q3-Oct to Dec / 2018-2019 · 2019-01-31
- 2023-Q1 · 2023-04-14
- 2022-Q4 · 2023-02-10
- 2022-Q3 · 2023-02-10
- 2022-Q2 · 2022-07-18
- 2022-Q1 · 2022-04-24
- 2021-Q4 · 2022-01-27
- 2021-Q3 · 2021-10-11
- 2021-Q2 · 2021-07-27
- 2021-Q1 · 2021-04-20
- 2020-Q4 · 2021-02-02
- 2020-Q3 · 2020-11-05
- 2020-Q2 · 2020-10-02
- 2020-Q1 · 2020-10-02
- 2019-Q4 · 2020-01-13
- 2019-Q3 · 2019-10-22
- 2019-Q2 · 2019-07-24
- 2019-Q1 · 2019-01-31
- 2018-Q4 · 2019-01-31