Overview
AARYAA ENCLAVE
AARYAA PROPERTIES BUILDTECH PRIVATE LIMITED
Completion2024-12-26Proposed
Registered on2020-05-08
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details |
| Construction & progress | 2 progress details · 13 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 20 documents · 18 source links |
Registration
Registration
| Promoter | AARYAA PROPERTIES BUILDTECH PRIVATE LIMITED | |
|---|---|---|
| Regulator | RERA Bihar | |
| Registration number | BRERAP0001341-1/1131/R-972/2020 | |
| Registered on | 2020-05-08 | |
| Project type | Plotted Development | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2024-12-26 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,90,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 6,615.42 | |
|---|---|---|
| FAR | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-12-25 | |
|---|---|---|
| Proposed completion | 2024-12-26 |
Quarterly progress
| 2023-Q2 | 2024-07-25 |
| 2023-Q1 | 2023-04-20 |
| 2022-Q4 | 2023-04-20 |
| 2022-Q3 | 2022-10-13 |
| 2022-Q2 | 2022-10-13 |
| 2022-Q1 | 2022-10-13 |
| 2021-Q4 | 2022-01-29 |
| 2021-Q3 | 2021-12-31 |
| 2021-Q2 | 2021-12-31 |
| 2021-Q1 | 2021-12-31 |
| 2020-Q4 | 2021-02-28 |
| 2020-Q3 | 2021-02-28 |
| 2020-Q2 | 2021-02-28 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AARYAA PROPERTIES BUILDTECH PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Axis Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP11182019221341-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP11182019221341-1
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Document
- Sanctioned Layout Plan
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-20
- Q3-Oct to Dec / 2022-2023 · 2023-04-20
- Q2-Jul to Sep / 2022-2023 · 2022-10-13
- Q1-Apr to Jun / 2022-2023 · 2022-10-13
- Q4-Jan to Mar / 2021-2022 · 2022-10-13
- Q3-Oct to Dec / 2021-2022 · 2022-01-29
- Q2-Jul to Sep / 2021-2022 · 2021-12-31
- Q1-Apr to Jun / 2021-2022 · 2021-12-31
- Q4-Jan to Mar / 2020-2021 · 2021-12-31
- Q3-Oct to Dec / 2020-2021 · 2021-02-28
- Q2-Jul to Sep / 2020-2021 · 2021-02-28
- Q1-Apr to Jun / 2020-2021 · 2021-02-28
- Notice of Commencement
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-20
- 2022-Q4 · 2023-04-20
- 2022-Q3 · 2022-10-13
- 2022-Q2 · 2022-10-13
- 2022-Q1 · 2022-10-13
- 2021-Q4 · 2022-01-29
- 2021-Q3 · 2021-12-31
- 2021-Q2 · 2021-12-31
- 2021-Q1 · 2021-12-31
- 2020-Q4 · 2021-02-28
- 2020-Q3 · 2021-02-28
- 2020-Q2 · 2021-02-28