AASMA CITY HOME PHASE - IV

AASMA BUILDERS & COLONISERS LTD. · BILASPUR
Units419
Booked340 of 419As of 2026-06-30
Construction progress82%As of 2026-06-30
Completion2027-04-30Revised · Proposed 2023-03-31
Registered on2020-05-21
Approvals4
Cases2

Sections

Property title & search report
Approvals4 approvals
Disputes & cases2 cases
Contract & costs2 cost heads · 25 quarters
Technical report
Site & area3 site details · 419 unit types
Construction & progress4 progress details · 25 quarters
Developer & finance
Developer3 developer details
The evidence
Sources166 documents · 12 source links

Registration

Registration

PromoterAASMA BUILDERS & COLONISERS LTD.
DistrictBILASPUR
RegulatorCG RERA
Registration numberPCGRERA210520001111
Registered on2020-05-21
Project typeResidential Plotted Development
Status (as filed)New
Proposed completion2023-03-31
Revised completion2027-04-30