Overview
Abdul Majeed Tower
HIGHWAY & HYDEL PROJECTS PRIVATE LIMITED · Bhagalpur
Units32
Booked20 of 32As of 2026-09-30
Construction progress74%As of 2026-09-30
Completion2027-08-10Proposed
Registered on2025-08-30
Valid to2027-08-10
Approvals9
Sections
| Property title & search report | |
|---|---|
| Approvals | 9 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 16 unit types |
| Construction & progress | 4 progress details · 4 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 27 documents · 12 source links |
Registration
Registration
| Promoter | HIGHWAY & HYDEL PROJECTS PRIVATE LIMITED | |
|---|---|---|
| District | Bhagalpur | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP190122060825100827E00 | |
| Registered on | 2025-08-30 | |
| Valid to | 2027-08-10 | |
| Project type | Mixed Development(residential and commercial) | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2027-08-10 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Environmental Clearance Certificate | |
| NOC From Airport Authority of India | |
| NOC from Fire Service Authority | |
| Notice of Commencement in form X | |
| Environment Clearance | 2026-01-01 |
| Fire NOC | 2026-01-01 |
| Airport NOC | 2026-01-01 |
| Water Supply Permission | 2026-01-01 |
| Other approval | 2026-01-01 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 505.67 | |
|---|---|---|
| Built-up (m²) | 1,138.94 | |
| FAR | 2.25 | |
| Towers | 1 | |
| Units | 32 | |
| Booked | 20 | |
| Booked as of | 2026-09-30 |
Unit types
| Shop | 1 | Abdul Majeed Tower |
| Shop | 1 | Abdul Majeed Tower |
| Shop | 1 | Abdul Majeed Tower |
| Shop | 1 | Abdul Majeed Tower |
| Shop | 1 | Abdul Majeed Tower |
| Shop | 1 | Abdul Majeed Tower |
| Shop | 1 | Abdul Majeed Tower |
| Shop | 1 | Abdul Majeed Tower |
| Shop | 1 | Abdul Majeed Tower |
| 2 BHK | 5 | Abdul Majeed Tower |
| 2 BHK | 5 | Abdul Majeed Tower |
| Shop | 1 | Abdul Majeed Tower |
| Shop | 1 | Abdul Majeed Tower |
| 2 BHK | 5 | Abdul Majeed Tower |
| Shop | 1 | Abdul Majeed Tower |
| 2 BHK | 5 | Abdul Majeed Tower |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 74% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2024-12-12 | |
| Proposed completion | 2027-08-10 |
Quarterly progress
| 2026-Q3 | 2026-10-25 | 74% | 20 |
| 2026-Q2 | 2026-08-20 | ||
| 2026-Q1 | 2026-07-20 | ||
| 2025-Q4 | 2026-07-20 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | HIGHWAY & HYDEL PROJECTS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Canara Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP179201800861-5
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP179201800861&ld=pan&pj=RERAP179201800861-5&f=2026-2027&q=2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP179201800861-5
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- A certificate from a Chartered accountant declaring that no advance booking amount has been taken from the customers against the current project duly signed by the promoter and countersigned by CA · Sign in to download
- Any other Project related documents · Sign in to download
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Environmental Clearance Certificate
- NOC From Airport Authority of India
- NOC from Fire Service Authority
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-25
- Quarterly Progress Image · 2026-10-25
- Quarterly Progress Image · 2026-10-25
- Q1 (Apr - Jun) / 2026-2027 · 2026-08-20
- Quarterly Progress Image · 2026-07-20
- Quarterly Progress Image · 2026-07-20
- Q4 (Jan - Mar) / 2025-2026 · 2026-07-20
- Quarterly Progress Image · 2026-07-20
- Quarterly Progress Image · 2026-07-20
- Q3 (Oct - Dec) / 2025-2026 · 2026-07-20
- Project Photogragh · Sign in to download
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Environmental Clearance Certificate
- NOC From Airport Authority of India
- NOC from Fire Service Authority
- Notice of Commencement in form X
- 2026-Q2 · 2026-08-20
- 2026-Q1 · 2026-07-20
- 2025-Q4 · 2026-07-20