Overview
ACHYUT CORNERSTONE
M/S TIRUPATI BUILDERS · TRIPURA ROAD JUNCTION
Units101
Completion2030-12-31Proposed
Registered on2026-08-11
Valid to2030-12-31
Approvals7
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 23 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 37 documents · 5 source links |
Registration
Registration
| Promoter | M/S TIRUPATI BUILDERS | |
|---|---|---|
| District | KAMRUP METRO | |
| Locality | TRIPURA ROAD JUNCTION | |
| Regulator | RERA Assam | |
| Registration number | RERAA KM 269 OF 2026-2027 | |
| Registered on | 2026-08-11 | |
| Valid to | 2030-12-31 | |
| Status (as filed) | Ongoing Projects | |
| Proposed completion | 2030-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Layout Plan | ||
| Building Plan | ||
| NOC/Building Permit | GMC/W45/0444/12032026 | |
| I. PLANNING PERMIT FROM THE GUWAHATI METROPOLITAN DEVELOPMENT AUTHORITY | 2026-03-11 | |
| II. NOC FOR GROUND WATER EXTRACTION FROM CENTRAL GROUND WATER AUTHORITY | 2026-04-22 | |
| III. NOC FOR HEIGHT CLEARANCE FROM AIRPORT AUTHORITY OF INDIA | 2025-03-28 | |
| IV. NOC/BUILDING PERMIT FROM GUWAHATI MUNICIPAL CORPORATION | 2026-04-18 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 | |
|---|---|---|
| Construction | ₹33,60,00,000 | |
| Total | ₹42,20,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 4,121.93 | |
|---|---|---|
| Units | 101 |
Unit types
| 4 | 178.63 | 1 |
| 4 | 186.34 | 1 |
| 4 | 240.09 | 2 |
| 0 | 29.25 | 1 |
| 0 | 30.25 | 1 |
| 0 | 30.97 | 1 |
| 0 | 34.87 | 1 |
| 0 | 38.64 | 1 |
| 0 | 44.07 | 1 |
| 0 | 54.11 | 1 |
| 0 | 138.03 | 1 |
| 0 | 146.01 | 1 |
| 0 | 685.74 | 1 |
| 3 | 98 | 10 |
| 3 | 90.64 | 10 |
| 3 | 96.56 | 10 |
| 3 | 94.66 | 9 |
| 3 | 92 | 8 |
| 3 | 96.26 | 9 |
| 3 | 96.3 | 10 |
| 3 | 101.92 | 10 |
| 4 | 146.98 | 10 |
| 4 | 170.05 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2026-05-15 | |
|---|---|---|
| Proposed completion | 2030-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/S TIRUPATI BUILDERS | |
|---|---|---|
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.assam.gov.in/admincontrol/custom_search
- https://rera.assam.gov.in/admincontrol/registered_projects/1
- https://rera.assam.gov.in/assistancecontrol/project_search_public/1
- https://rera.assam.gov.in/view_project/project_preview_open/2661
- https://rera.assam.gov.in/view_project/searchprojectDetail/2661
- Registration Certificate
- POWER OF ATTORNEY · 2026-04-25 · Sign in to download
- TRACE MAP SHOWING NEARBY BY STREAMS, PONDS ETC. · 2026-04-25 · Sign in to download
- LATEST NON ENCUMBRANCE CERTIFICATE · 2026-05-02 · Sign in to download
- PLANNING PERMIT FROM COMPETENT AUTHORITY · 2026-04-25
- HEIGHT CLEARANCE FROM AIRPORT AUTHORITY OF INDIA · 2026-04-25
- FIRE NOC · 2026-05-02
- APPROVED DRAWING FROM COMPETENT AUTHORITY · 2026-05-07 · Sign in to download
- ARCHITECT, STRUCTURAL ENGINEER AND CONTRACTOR DETAILS WITH NAME AND ADDRESS AS THE CASE MAY BE · 2026-05-07 · Sign in to download
- PLAN OF DEVELOPMENT WORKS · 2026-05-07
- LOCATIONAL MAP INCLUDING LATITUDE AND LONGITUDE · 2026-05-07 · Sign in to download
- CLEARANCE FROM ASSAM GROUND WATER CONTROL AND REGULATION AUTHORITY · 2026-05-08
- NO OBJECTION CERTIFICATE FROM THE COMPETENT AUTHORITY · 2026-05-12 · Sign in to download
- CARPET AREA AND PARKING AREA DETAILS · 2026-05-13 · Sign in to download
- PROJECT COST ESTIMATE · 2026-05-13 · Sign in to download
- COMMENCEMENT CERTIFICATE OF THE PROJECT · 2026-05-13 · Sign in to download
- PROOF CHECKING OF STRUCTURAL DESIGN / VETTING CERTIFICATE · 2026-05-14 · Sign in to download
- REGISTRATION CERTIFICATE OF THE ENTITY · 2026-04-25
- Other · 2026-04-25 · Sign in to download
- LETTER OF AUTHORIZATION FOR AUTHORIZED SIGNATORY · 2026-05-07 · Sign in to download
- Other · 2026-05-14 · Sign in to download
- BANK MANAGER'S LETTER MENTIONING THAT THE ACCOUNT HAS BEEN OPENED IN COMPLIANCE WITH THE SECTION 4(2)(L)(D) OF REAL ESTATE (REGULATION AND DEVELOPMENT) ACT, 2016 · 2026-05-02 · Sign in to download
- AUDITED BALANCE SHEET OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2026-05-07 · Sign in to download
- INCOME TAX RETURN OF THE PROMOTER FOR THE IMMEDIATELY PRECEDING THREE (3) FINANCIAL YEARS · 2026-05-07 · Sign in to download
- CASHFLOW STATEMENT · 2026-05-13 · Sign in to download
- PHOTOCOPY OF BANK DRAFT · 2026-05-13 · Sign in to download
- FORM B, DULY NOTARIZED · 2026-05-07 · Sign in to download
- SPECIFICATION OF CONSTRUCTION · 2026-05-13 · Sign in to download
- ESTIMATED COST OF PROJECT · 2026-05-13 · Sign in to download
- DETAILS OF AGENCY TAKING UP EXTERNAL DEVELOPMENT WORKS · 2026-05-13 · Sign in to download
- QUARTERLY ESTIMATED COST OF APARTMENTS · 2026-05-13
- QUARTERLY ESTIMATED COST OF FACILITIES & SERVICES · 2026-05-13
- EXTERNAL DEVELOPMENT WORKS · 2026-05-13 · Sign in to download
- Other · 2026-05-13 · Sign in to download
- Project application order/letter · 2026-08-06 · Sign in to download
- Project application order/letter · 2026-07-06 · Sign in to download
- Project application order/letter · 2026-05-30 · Sign in to download