Overview
ADMIRE GREEN PHASE- 1
M/S ADMIRE INFRAZONE PVT.LTD · RAIPUR
Units108
Booked5 of 108As of 2026-06-30
Construction progress85%As of 2026-06-30
Completion2027-05-20Revised · Proposed 2024-02-20
Registered on2020-12-24
Approvals6
Cases5
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Disputes & cases | 5 cases |
| Contract & costs | 2 cost heads · 23 quarters |
| Technical report | |
| Site & area | 3 site details · 108 unit types |
| Construction & progress | 4 progress details · 23 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 133 documents · 16 source links |
Registration
Registration
| Promoter | M/S ADMIRE INFRAZONE PVT.LTD | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA241220001171 | |
| Registered on | 2020-12-24 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2024-02-20 | |
| Revised completion | 2027-05-20 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Nazul clearance in case of Nazul Area |
| Enviornment Clearance |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| M-PRO-2025-02988 | CG RERA | Complaint | Disposed | 2026-08-06 |
| SM-EXA-2026-03667 | CG RERA | Complaint | Disposed | 2026-07-02 |
| M-PRO-2025-03238 | CG RERA | Complaint | Disposed | 2026-03-23 |
| M-PRO-2024-02569 | CG RERA | Complaint | Disposed | 2024-10-07 |
| M-COM-2023-02073 | CG RERA | Complaint | Disposed | 2024-02-21 |
Complaints & cases
| Cases | 5 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,41,82,000 | |
|---|---|---|
| Construction | ₹3,47,77,000 |
Quarterly money flows
| 2020-Q4 | ₹0 |
| 2021-Q1 | ₹0 |
| 2021-Q2 | ₹0 |
| 2021-Q3 | ₹11,67,000 |
| 2021-Q4 | ₹25,14,000 |
| 2022-Q1 | ₹13,75,000 |
| 2022-Q2 | ₹0 |
| 2022-Q3 | ₹7,000 |
| 2022-Q4 | ₹23,000 |
| 2023-Q1 | ₹0 |
| 2023-Q2 | ₹0.6 |
| 2023-Q3 | ₹672.4 |
| 2023-Q4 | ₹672.4 |
| 2024-Q1 | ₹272 |
| 2024-Q2 | ₹472 |
| 2024-Q3 | ₹472 |
| 2024-Q4 | ₹8,172 |
| 2025-Q1 | ₹8,172 |
| 2025-Q2 | ₹8,172 |
| 2025-Q3 | ₹8,172 |
| 2025-Q4 | ₹172 |
| 2026-Q1 | ₹21,00,872 |
| 2026-Q2 | ₹172 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 108 | |
|---|---|---|
| Booked | 5 | |
| Booked as of | 2026-06-30 |
Unit types
| plot-1 | 1 | 0 |
| plot -2 | 1 | 0 |
| plot -plot | 1 | 0 |
| PLOT-4 | 1 | 0 |
| PLOT-5 | 1 | 0 |
| PLOT-6 | 1 | 0 |
| PLOT-7 | 1 | 0 |
| PLOT-8 | 1 | 0 |
| PLOT-9 | 1 | 0 |
| PLOT-10 | 1 | 0 |
| PLOT-11 | 1 | 0 |
| PLOT-12 | 1 | 0 |
| PLOT-13 | 1 | 0 |
| PLOT-14 | 1 | 0 |
| PLOT-15 | 1 | 0 |
| PLOT-16 | 1 | 0 |
| plot -17 | 1 | 0 |
| plot-18 | 1 | 0 |
| plot-19 | 1 | 0 |
| plot-20 | 1 | 0 |
| PLOT -21 | 1 | 0 |
| PLOT-22 | 1 | 0 |
| PLOT-23 | 1 | 0 |
| PLOT-24 | 1 | 0 |
| PLOT-25 | 1 | 0 |
| PLOT-26 | 1 | 0 |
| PLOT-27 | 1 | 0 |
| PLOT-28 | 1 | 0 |
| PLOT-29 | 1 | 0 |
| PLOT-30 | 1 | 0 |
| PLOT-31 | 1 | 0 |
| PLOT-32 | 1 | 0 |
| PLOT-33 | 1 | 0 |
| PLOT-34 | 1 | 0 |
| PLOT-35 | 1 | 0 |
| PLOT-36 | 1 | 0 |
| PLOT-37 | 1 | 0 |
| PLOT-38 | 1 | 0 |
| PLOT-39 | 1 | 0 |
| PLOT-40 | 1 | 0 |
| PLOT-41 | 1 | 0 |
| PLOT-42 | 1 | 0 |
| PLOT-43 | 1 | 0 |
| PLOT-44 | 1 | 0 |
| PLOT-45 | 1 | 0 |
| PLOT-46 | 1 | 0 |
| PLOT-47 | 1 | 0 |
| PLOT-48 | 1 | 0 |
| plot-49 | 1 | 0 |
| plot-50 | 1 | 0 |
| plot-51 | 1 | 0 |
| plot-52 | 1 | 0 |
| plot-53 | 1 | 0 |
| plot-54 | 1 | 0 |
| plot-55 | 1 | 0 |
| plot-56 | 1 | 0 |
| plot-57 | 1 | 0 |
| plot-58 | 1 | 0 |
| plot-59 | 1 | 0 |
| plot-60 | 1 | 0 |
| plot-61 | 1 | 0 |
| plot-62 | 1 | 0 |
| plot-63 | 1 | 0 |
| plot-64 | 1 | 0 |
| plot-65 | 1 | 0 |
| PLOT-66 | 1 | 0 |
| PLOT-67 | 1 | 0 |
| PLOT-68 | 1 | 0 |
| PLOT-69 | 1 | 0 |
| PLOT-70 | 1 | 0 |
| PLOT-71 | 1 | 0 |
| PLOT-72 | 1 | 0 |
| PLOT-73 | 1 | 0 |
| PLOT-74 | 1 | 0 |
| PLOT-75 | 1 | 0 |
| PLOT-76 | 1 | 0 |
| PLOT-77 | 1 | 0 |
| PLOT-78 | 1 | 0 |
| PLOT-79 | 1 | 0 |
| PLOT-80 | 1 | 0 |
| PLOT-81 | 1 | 0 |
| PLOT-82 | 1 | 0 |
| PLOT-83 | 1 | 0 |
| PLOT-84 | 1 | 0 |
| PLOT-85 | 1 | 0 |
| PLOT-86 | 1 | 1 |
| PLOT-87 | 1 | 0 |
| PLOT-88 | 1 | 0 |
| PLOT-89 | 1 | 1 |
| PLOT-90 | 1 | 0 |
| PLOT-91 | 1 | 1 |
| PLOT-92 | 1 | 0 |
| PLOT-93 | 1 | 0 |
| PLOT-94 | 1 | 0 |
| PLOT-95 | 1 | 0 |
| PLOT-96 | 1 | 0 |
| PLOT-97 | 1 | 0 |
| PLOT-98 | 1 | 0 |
| PLOT-99 | 1 | 0 |
| PLOT-100 | 1 | 0 |
| PLOT-101 | 1 | 0 |
| PLOT-102 | 1 | 0 |
| PLOT-103 | 1 | 0 |
| PLOT-104 | 1 | 1 |
| PLOT-105 | 1 | 0 |
| PLOT-106 | 1 | 1 |
| PLOT-107 | 1 | 0 |
| PLOT-108 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 85% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2024-02-20 | |
| Revised completion | 2027-05-20 |
Quarterly progress
| 2020-Q4 | 5% |
| 2021-Q1 | 5% |
| 2021-Q2 | 10% |
| 2021-Q3 | 12% |
| 2021-Q4 | 13% |
| 2022-Q1 | 15% |
| 2022-Q2 | 25% |
| 2022-Q3 | 30% |
| 2022-Q4 | 34% |
| 2023-Q1 | 40% |
| 2023-Q2 | 40% |
| 2023-Q3 | 40% |
| 2023-Q4 | 42% |
| 2024-Q1 | 43% |
| 2024-Q2 | 46% |
| 2024-Q3 | 51% |
| 2024-Q4 | 56% |
| 2025-Q1 | 60% |
| 2025-Q2 | 63% |
| 2025-Q3 | 63% |
| 2025-Q4 | 69% |
| 2026-Q1 | 80% |
| 2026-Q2 | 85% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/S ADMIRE INFRAZONE PVT.LTD | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTQ1OA==
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Enviornment Clearance
- Modified Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Final order · 2026-08-06 · Sign in to download
- Final order · 2026-07-02 · Sign in to download
- Final order · 2026-03-23 · Sign in to download
- Final order · 2024-10-07 · Sign in to download
- Final order · 2024-02-21 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Enviornment Clearance
- Development Permission from competent authorities
- M-PRO-2025-02988 · Sign in to download
- SM-EXA-2026-03667 · Sign in to download
- M-PRO-2025-03238 · Sign in to download
- M-PRO-2024-02569 · Sign in to download
- M-COM-2023-02073 · Sign in to download