Overview
ADVAITA HOMES
WILL ABODES PRIVATE LIMITED · Krishna
Units100
Completion2023-09-23Proposed
Registered on2021-09-23
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 4 site details · 100 unit types |
| Construction & progress | 2 progress details · 4 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 24 documents · 9 source links |
Registration
Registration
| Promoter | WILL ABODES PRIVATE LIMITED | |
|---|---|---|
| District | Krishna | |
| Regulator | AP RERA | |
| Registration number | P06160121897 | |
| Registered on | 2021-09-23 | |
| Project type | Residential | |
| Status (as filed) | New Project | |
| Proposed completion | 2023-09-23 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Authority |
|---|---|---|---|
| Building / layout plan | 1073/0001/B/VMC/KUN/2019 | 2019-09-23 | Director,Town and Country Planning |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,16,90,080 | |
|---|---|---|
| Construction | ₹17,38,00,000 | |
| Total | ₹24,54,90,080 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 5,191.37 | |
|---|---|---|
| Built-up (m²) | 12,923.66 | |
| Towers | 5 | |
| Units | 100 |
Unit types
| 2BHK | 69.52 | 1 | BLOCK A | First Floor |
| 2BHK | 70.87 | 1 | BLOCK A | First Floor |
| 2BHK | 70.53 | 1 | BLOCK A | First Floor |
| 2BHK | 68.72 | 1 | BLOCK A | First Floor |
| 2BHK | 69.52 | 1 | BLOCK A | Fourth Floor |
| 2BHK | 70.87 | 1 | BLOCK A | Fourth Floor |
| 2BHK | 70.53 | 1 | BLOCK A | Fourth Floor |
| 2BHK | 68.72 | 1 | BLOCK A | Fourth Floor |
| 2BHK | 76.11 | 1 | BLOCK A | Ground Floor |
| 2BHK | 76.11 | 1 | BLOCK A | Ground Floor |
| 2BHK | 76.11 | 1 | BLOCK A | Ground Floor |
| 2BHK | 76.11 | 1 | BLOCK A | Ground Floor |
| 2BHK | 69.52 | 1 | BLOCK A | Second Floor |
| 2BHK | 70.87 | 1 | BLOCK A | Second Floor |
| 2BHK | 70.53 | 1 | BLOCK A | Second Floor |
| 2BHK | 68.72 | 1 | BLOCK A | Second Floor |
| 2BHK | 69.52 | 1 | BLOCK A | Third Floor |
| 2BHK | 70.87 | 1 | BLOCK A | Third Floor |
| 2BHK | 70.53 | 1 | BLOCK A | Third Floor |
| 2BHK | 68.72 | 1 | BLOCK A | Third Floor |
| 2BHK | 68.72 | 1 | BLOCK B | First Floor |
| 2BHK | 69.52 | 1 | BLOCK B | First Floor |
| 2BHK | 70.87 | 1 | BLOCK B | First Floor |
| 2BHK | 70.53 | 1 | BLOCK B | First Floor |
| 2BHK | 68.72 | 1 | BLOCK B | Fourth Floor |
| 2BHK | 69.52 | 1 | BLOCK B | Fourth Floor |
| 2BHK | 70.87 | 1 | BLOCK B | Fourth Floor |
| 2BHK | 70.53 | 1 | BLOCK B | Fourth Floor |
| 2BHK | 68.72 | 1 | BLOCK B | Ground Floor |
| 2BHK | 69.52 | 1 | BLOCK B | Ground Floor |
| 2BHK | 70.87 | 1 | BLOCK B | Ground Floor |
| 2BHK | 70.53 | 1 | BLOCK B | Ground Floor |
| 2BHK | 68.72 | 1 | BLOCK B | Second Floor |
| 2BHK | 69.52 | 1 | BLOCK B | Second Floor |
| 2BHK | 70.87 | 1 | BLOCK B | Second Floor |
| 2BHK | 70.53 | 1 | BLOCK B | Second Floor |
| 2BHK | 68.72 | 1 | BLOCK B | Third Floor |
| 2BHK | 69.52 | 1 | BLOCK B | Third Floor |
| 2BHK | 70.87 | 1 | BLOCK B | Third Floor |
| 2BHK | 70.53 | 1 | BLOCK B | Third Floor |
| 2BHK | 68.72 | 1 | BLOCK C | First Floor |
| 2BHK | 68.73 | 1 | BLOCK C | First Floor |
| 2BHK | 70.65 | 1 | BLOCK C | First Floor |
| 2BHK | 71 | 1 | BLOCK C | First Floor |
| 2BHK | 68.72 | 1 | BLOCK C | Fourth Floor |
| 2BHK | 68.73 | 1 | BLOCK C | Fourth Floor |
| 2BHK | 70.65 | 1 | BLOCK C | Fourth Floor |
| 2BHK | 71 | 1 | BLOCK C | Fourth Floor |
| 2BHK | 68.72 | 1 | BLOCK C | Ground Floor |
| 2BHK | 68.73 | 1 | BLOCK C | Ground Floor |
| 2BHK | 70.65 | 1 | BLOCK C | Ground Floor |
| 2BHK | 71 | 1 | BLOCK C | Ground Floor |
| 2BHK | 68.72 | 1 | BLOCK C | Second Floor |
| 2BHK | 68.73 | 1 | BLOCK C | Second Floor |
| 2BHK | 70.65 | 1 | BLOCK C | Second Floor |
| 2BHK | 71 | 1 | BLOCK C | Second Floor |
| 2BHK | 68.72 | 1 | BLOCK C | Third Floor |
| 2BHK | 68.73 | 1 | BLOCK C | Third Floor |
| 2BHK | 70.65 | 1 | BLOCK C | Third Floor |
| 2BHK | 71 | 1 | BLOCK C | Third Floor |
| 2BHK | 68.72 | 1 | BLOCK D | First Floor |
| 2BHK | 68.73 | 1 | BLOCK D | First Floor |
| 2BHK | 70.65 | 1 | BLOCK D | First Floor |
| 2BHK | 71 | 1 | BLOCK D | First Floor |
| 2BHK | 68.72 | 1 | BLOCK D | Fourth Floor |
| 2BHK | 68.73 | 1 | BLOCK D | Fourth Floor |
| 2BHK | 70.65 | 1 | BLOCK D | Fourth Floor |
| 2BHK | 71 | 1 | BLOCK D | Fourth Floor |
| 2BHK | 68.72 | 1 | BLOCK D | Ground Floor |
| 2BHK | 68.73 | 1 | BLOCK D | Ground Floor |
| 2BHK | 70.65 | 1 | BLOCK D | Ground Floor |
| 2BHK | 71 | 1 | BLOCK D | Ground Floor |
| 2BHK | 68.72 | 1 | BLOCK D | Second Floor |
| 2BHK | 68.73 | 1 | BLOCK D | Second Floor |
| 2BHK | 70.65 | 1 | BLOCK D | Second Floor |
| 2BHK | 71 | 1 | BLOCK D | Second Floor |
| 2BHK | 68.72 | 1 | BLOCK D | Third Floor |
| 2BHK | 68.73 | 1 | BLOCK D | Third Floor |
| 2BHK | 70.65 | 1 | BLOCK D | Third Floor |
| 2BHK | 71 | 1 | BLOCK D | Third Floor |
| 3BHK | 104.63 | 1 | BLOCK E | First Floor |
| 3BHK | 105.76 | 1 | BLOCK E | First Floor |
| 3BHK | 107.21 | 1 | BLOCK E | First Floor |
| 3BHK | 106.37 | 1 | BLOCK E | First Floor |
| 3BHK | 104.63 | 1 | BLOCK E | Fourth Floor |
| 3BHK | 105.76 | 1 | BLOCK E | Fourth Floor |
| 3BHK | 107.21 | 1 | BLOCK E | Fourth Floor |
| 3BHK | 106.37 | 1 | BLOCK E | Fourth Floor |
| 3BHK | 104.63 | 1 | BLOCK E | Ground Floor |
| 3BHK | 105.76 | 1 | BLOCK E | Ground Floor |
| 3BHK | 107.21 | 1 | BLOCK E | Ground Floor |
| 3BHK | 106.37 | 1 | BLOCK E | Ground Floor |
| 3BHK | 104.63 | 1 | BLOCK E | Second Floor |
| 3BHK | 105.76 | 1 | BLOCK E | Second Floor |
| 3BHK | 107.21 | 1 | BLOCK E | Second Floor |
| 3BHK | 106.37 | 1 | BLOCK E | Second Floor |
| 3BHK | 104.63 | 1 | BLOCK E | Third Floor |
| 3BHK | 105.76 | 1 | BLOCK E | Third Floor |
| 3BHK | 107.21 | 1 | BLOCK E | Third Floor |
| 3BHK | 106.37 | 1 | BLOCK E | Third Floor |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-09-23 | |
|---|---|---|
| Proposed completion | 2023-09-23 |
Quarterly progress
| 2021-Q4 | 2022-01-22 |
| 2022-Q1 | 2022-04-21 |
| 2022-Q2 | 2022-07-21 |
| 2022-Q3 | 2022-10-22 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | WILL ABODES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.ap.gov.in/RERA/Views/GeoMap.aspx
- https://rera.ap.gov.in/RERA/Views/Project.aspx??enc=mUX5JvffTObOCE+6xFBEFdda9XZKYBRvLz6VZaBlV/nhQJXVVqmI6wXCZ9C5/rz+PnArQhlhTG9qj1zijipTydw8ue1VXygQb2J3gaMxDEeFf1jRTdKTVewqHKX9v/BB
- https://rera.ap.gov.in/RERA/Views/Reports/ApprovedProjects.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/DwellingUnitsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/ProjExpectedDateofCompletion.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QprProjectsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QuarterlyReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/SoldInformation.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/TotalBuildupArea.aspx
- Promoter registration certificate
- Promoter GST certificate
- Litigation details
- Modified plan
- Architect certificate
- Board resolution
- 1.Income Tax Return Acknowledgement of Preceding Year 1
- 2. Income Tax Return Acknowledgement of Preceding Year 2
- 3.Income Tax Return Acknowledgement of Preceding Year 3
- 4.Balance Sheet
- 10. Detailed site plan showing the measurements as on ground including diagonals, Latitude and Longitude at end points of the project site
- 15. Details of the cases pending before the Authorities or in Courts of Law and their current status along with the copies of the orders issued
- 16. Copy of the plan and proceedings issued by the competent Authority for approval of plans
- 17. Approved plan / list of amenities proposed in the site
- 18. NOC's issued by Authority
- 19. Detailed technical specifications of the construction if the buildings and facilities proposed in the project including brand specifications details of fixtures and fittings
- 20. Full address of the proposed development project along with the land mark nearby and a location plan/ Topo plan drawn to a scale
- 21. Licenses/Enrolment form of Civil Contractors, or turnkey contractor, or EPC Contractors.
- 25.Licenses/Enrolment form of Chartered Accountant or firm or company
- 26.Detailed estimate of the expenditure for construction of the building
- 27. Statement of source of funds for construction of project
- 29.Proforma of the Allotment Letter proposed to be signed with the Allottee
- 32.Structural Stability Certificate duly issued by Certified Structural Consultant/Engineer along with the details of parameters followed for verification of structural stability *
- APRERA CERTIFICATE