AFFORDABLE GROUP HOUSING COLONY
M/S PIVOTALINFRASTRUCTURE PVT. LTD · Gurugram
Completion2021-07-27Revised · Proposed 2021-07-27
Registered on2017-09-01
Valid to2021-05-29
Approvals10
Sections
| Property title & search report | |
|---|---|
| Approvals | 10 approvals |
| Disputes & cases | 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 5 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 9 documents · 3 source links |
Registration
Registration
| Promoter | M/S PIVOTALINFRASTRUCTURE PVT. LTD | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 178 OF 2017 DATED 01.09.2017 | |
| Registered on | 2017-09-01 | |
| Valid to | 2021-05-29 | |
| Status (as filed) | Lapsed Project | |
| Proposed completion | 2021-07-27 | |
| Revised completion | 2021-07-27 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 5 of 2016 (30.05.2016) | Town & Country Planning Department | |
| Layout Plan | 2016-07-25 | ||
| Building Plan | 2016-07-25 | ||
| I. POLLUTION | 2017-09-14 | ||
| II. BUILDING PLAN APPROVAL | 2016-07-25 | ||
| III. ENVIRONMENT CLEARANCE | 2017-07-28 | ||
| IV. FIRE SCHEME APPROVAL | 2017-04-12 | ||
| V. POWER LOAD ASSURANCE | 2016-06-09 | ||
| VI. SEWRAGE TREATED WATER FOR CONSTRUCTION | 2016-05-27 | ||
| VII. WATER SUPPLY ASSURANCE | 2017-03-20 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2021-05-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹21,17,00,000 | |
|---|---|---|
| Construction | ₹84,91,00,000 | |
| Total | ₹1,59,47,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 225 |
|---|
Unit types
| Type |
|---|
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2021-07-27 | |
|---|---|---|
| Revised completion | 2021-07-27 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/S PIVOTALINFRASTRUCTURE PVT. LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1023
- https://nominatim.openstreetmap.org/search?q=sector+62%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2017-09-01
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-11-30
- A COPY OF THE DRAFT ALLOTMENT LETTER BY WHICH THE APARTMENT SHALL BE ALLOTTED/ BOOKED IN FAVOUR OF THE APARTMENT BUYERS · 2019-11-30 · Sign in to download
- A COPY OF THE DRAFT AGREEMENT WHICH SHALL BE MADE BEFORE SEEKING ANY DEPOSIT EXCEEDING 10% OF THE COST OF THE APARTMENT.(BASED ON THE MODEL AGREEMENT PRESCRIBED IN THE RULES) · 2019-11-30 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-11-30 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-11-30
- ZONING PLAN · 2019-11-30
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2019-11-30 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-11-30