Overview
AGARNI WOODS
DDL Infratech Private Limited
Units0
Completion2024-12-31Proposed
Registered on2023-04-24
Cases2
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 2 cases |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 3 site details · 1 unit type |
| Construction & progress | 2 progress details · 22 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 41 documents · 30 source links |
Registration
Registration
| Promoter | DDL Infratech Private Limited | |
|---|---|---|
| Regulator | RERA Bihar | |
| Registration number | BRERAP00496-4/676/R-369/2019 | |
| Registered on | 2023-04-24 | |
| Project type | Plotted Development | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2024-12-31 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status |
|---|---|---|---|
| RERA/CC-624/2019 | RERA Bihar | Pending | |
| Exe. Case No -496/2022 RERA/CC/578/2021 | RERA Bihar | Complaint | Pending |
Complaints & cases
| Cases | 2 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 7,52,715.3 | |
|---|---|---|
| FAR | 0 | |
| Units | 0 |
Unit types
| Type | Units | Tower |
|---|---|---|
| Plot | 0 | AGARNI WOODS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2010-11-05 | |
|---|---|---|
| Proposed completion | 2024-12-31 |
Quarterly progress
| 2025-Q1 | 2025-04-16 |
| 2024-Q4 | 2025-01-15 |
| 2024-Q3 | 2024-10-16 |
| 2024-Q2 | 2024-10-16 |
| 2024-Q1 | 2024-07-25 |
| 2023-Q4 | 2024-07-25 |
| 2023-Q3 | 2024-07-25 |
| 2023-Q2 | 2024-07-25 |
| 2022-Q4 | 2023-02-22 |
| 2022-Q3 | 2023-02-21 |
| 2022-Q2 | 2022-09-05 |
| 2022-Q1 | 2022-09-05 |
| 2021-Q4 | 2022-02-24 |
| 2021-Q3 | 2022-02-24 |
| 2021-Q1 | 2021-06-12 |
| 2020-Q4 | 2021-06-12 |
| 2020-Q3 | 2021-06-12 |
| 2020-Q2 | 2021-06-12 |
| 2020-Q1 | 2021-06-12 |
| 2019-Q4 | 2021-06-12 |
| 2019-Q3 | 2021-06-12 |
| 2019-Q2 | 2021-06-12 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | DDL Infratech Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP156201800496-4
- https://rera.bihar.gov.in/ProceedingOrder.aspx
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP156201800496-4
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- https://rera.bihar.gov.in/publicorder.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Q4-Jan to Mar / 2024-2025 · 2025-04-16
- Q3-Oct to Dec / 2024-2025 · 2025-01-15
- Q2-Jul to Sep / 2024-2025 · 2024-10-16
- Q1-Apr to Jun / 2024-2025 · 2024-10-16
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2022-2023 · 2023-02-22
- Q2-Jul to Sep / 2022-2023 · 2023-02-21
- Q1-Apr to Jun / 2022-2023 · 2022-09-05
- Q4-Jan to Mar / 2021-2022 · 2022-09-05
- Q3-Oct to Dec / 2021-2022 · 2022-02-24
- Q2-Jul to Sep / 2021-2022 · 2022-02-24
- Q4-Jan to Mar / 2020-2021 · 2021-06-12
- Q3-Oct to Dec / 2020-2021 · 2021-06-12
- Q2-Jul to Sep / 2020-2021 · 2021-06-12
- Q1-Apr to Jun / 2020-2021 · 2021-06-12
- Q4-Jan to Mar / 2019-2020 · 2021-06-12
- Q3-Oct to Dec / 2019-2020 · 2021-06-12
- Q2-Jul to Sep / 2019-2020 · 2021-06-12
- Q1-Apr to Jun / 2019-2020 · 2021-06-12
- View · 2022-12-05 · Sign in to download
- View · 2025-07-14 · Sign in to download
- View · 2025-10-13 · Sign in to download
- Other · 2026-09-11 · Sign in to download
- Other · 2026-07-24 · Sign in to download
- Other · 2026-02-17 · Sign in to download
- Other · 2025-12-23 · Sign in to download
- Other · 2025-07-29 · Sign in to download
- Other · 2025-06-02 · Sign in to download
- Other · 2021-06-03 · Sign in to download
- Other · 2022-12-05 · Sign in to download
- RERA/CC-624/2019 · Sign in to download
- Exe. Case No -496/2022 RERA/CC/578/2021 · Sign in to download
- 2025-Q1 · 2025-04-16
- 2024-Q4 · 2025-01-15
- 2024-Q3 · 2024-10-16
- 2024-Q2 · 2024-10-16
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2022-Q4 · 2023-02-22
- 2022-Q3 · 2023-02-21
- 2022-Q2 · 2022-09-05
- 2022-Q1 · 2022-09-05
- 2021-Q4 · 2022-02-24
- 2021-Q3 · 2022-02-24
- 2021-Q1 · 2021-06-12
- 2020-Q4 · 2021-06-12
- 2020-Q3 · 2021-06-12
- 2020-Q2 · 2021-06-12
- 2020-Q1 · 2021-06-12
- 2019-Q4 · 2021-06-12
- 2019-Q3 · 2021-06-12
- 2019-Q2 · 2021-06-12