Overview
AGI BUSINESS CENTRE
AGI INFRA LIMITED · Jalandhar
Units69
Completion2018-12-31Proposed
Valid to2019-12-31
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 1 unit type |
| Construction & progress | 2 progress details · 28 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 15 documents · 35 source links |
Registration
Registration
| Promoter | AGI INFRA LIMITED | |
|---|---|---|
| District | Jalandhar | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-JAL33-PC0058 | |
| Valid to | 2019-12-31 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2018-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Application for Occupancy/ Completion/ Phase Completion Certificate | 2018-04-05 | |
| CLU Certificate | ||
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | Clearances (Received) | 2018-04-12 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹20,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,578 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 5 | |
| Units | 69 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| COMMERCIAL SHOP | 60 | 69 | BUSINESS CENTRE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2014-09-01 | |
|---|---|---|
| Proposed completion | 2018-12-31 |
Quarterly progress
| 2019-Q4 | 2021-01-02 |
| 2020-Q1 | 2021-01-15 |
| 2020-Q2 | 2021-01-15 |
| 2020-Q3 | 2021-01-22 |
| 2020-Q4 | 2022-03-21 |
| 2021-Q1 | 2022-03-21 |
| 2021-Q2 | 2022-03-21 |
| 2021-Q3 | 2022-03-21 |
| 2021-Q4 | 2022-03-21 |
| 2022-Q1 | 2022-05-16 |
| 2022-Q2 | 2022-08-05 |
| 2022-Q3 | 2022-11-03 |
| 2022-Q4 | 2023-01-24 |
| 2023-Q1 | 2023-05-01 |
| 2023-Q2 | 2023-07-06 |
| 2023-Q3 | 2023-10-04 |
| 2023-Q4 | 2024-01-05 |
| 2024-Q1 | 2024-04-10 |
| 2024-Q2 | 2024-07-08 |
| 2024-Q3 | 2024-10-07 |
| 2024-Q4 | 2025-01-06 |
| 2025-Q1 | 2025-04-09 |
| 2025-Q2 | 2025-07-04 |
| 2025-Q3 | 2025-10-03 |
| 2025-Q4 | 2026-01-14 |
| 2026-Q1 | 2026-04-11 |
| 2026-Q2 | 2026-07-13 |
| 2026-Q3 | 2026-10-12 |
Extensions
| Valid to |
|---|
| 2019-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AGI INFRA LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Punjab National Bank | |
| Other projects in this city pack | 16 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10470&inPromoter_ID=1099&inPromoterType=2
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- Application for Occupancy/ Completion/ Phase Completion Certificate · 2018-04-05
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-04-12
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- Application for Occupancy/ Completion/ Phase Completion Certificate · 2018-04-05
- CLU Certificate
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2018-04-12
- Extension order · Sign in to download
- 2019-Q4 · 2021-01-02
- 2020-Q1 · 2021-01-15
- 2020-Q2 · 2021-01-15
- 2020-Q3 · 2021-01-22
- 2020-Q4 · 2022-03-21
- 2021-Q1 · 2022-03-21
- 2021-Q2 · 2022-03-21
- 2021-Q3 · 2022-03-21
- 2021-Q4 · 2022-03-21
- 2022-Q1 · 2022-05-16
- 2022-Q2 · 2022-08-05
- 2022-Q3 · 2022-11-03
- 2022-Q4 · 2023-01-24
- 2023-Q1 · 2023-05-01
- 2023-Q2 · 2023-07-06
- 2023-Q3 · 2023-10-04
- 2023-Q4 · 2024-01-05
- 2024-Q1 · 2024-04-10
- 2024-Q2 · 2024-07-08
- 2024-Q3 · 2024-10-07
- 2024-Q4 · 2025-01-06
- 2025-Q1 · 2025-04-09
- 2025-Q2 · 2025-07-04
- 2025-Q3 · 2025-10-03
- 2025-Q4 · 2026-01-14
- 2026-Q1 · 2026-04-11
- 2026-Q2 · 2026-07-13
- 2026-Q3 · 2026-10-12