Overview
AGI PALACE
AGI INFRA LIMITED · Jalandhar
Units116
Completion2020-12-31Proposed
Valid to2022-06-30
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 5 unit types |
| Construction & progress | 2 progress details · 28 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 15 documents · 35 source links |
Registration
Registration
| Promoter | AGI INFRA LIMITED | |
|---|---|---|
| District | Jalandhar | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-JAL33-PR0360 | |
| Valid to | 2022-06-30 | |
| Project type | (1) Residential (Building/Tower Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2020-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Environment Clearance certificate/ NOC | Clearances (Received) | 2018-02-26 |
| License to develop colony or society from Competent Authority | ||
| NOC from NHAI/ PWD | Clearances (Received) | 2018-03-26 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹45,75,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 8,852.49 | |
|---|---|---|
| Towers | 5 | |
| Maximum floors | 13 | |
| Units | 116 |
Unit types
| APARTMENTS | 241.55 | 52 | BLOCK 1 |
| APARTMENTS | 241.55 | 52 | BLOCK 2 |
| APARTMENT | 517 | 1 | BLOCK 1 PENT HOUSE |
| APARTMENT | 517 | 1 | BLOCK 2 PENT HOUSE |
| SHOPS | 48.23 | 10 | COMMERCIAL SHOPS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-02-01 | |
|---|---|---|
| Proposed completion | 2020-12-31 |
Quarterly progress
| 2019-Q4 | 2021-01-02 |
| 2020-Q1 | 2021-01-11 |
| 2020-Q2 | 2021-01-12 |
| 2020-Q3 | 2021-01-22 |
| 2020-Q4 | 2021-09-01 |
| 2021-Q1 | 2021-09-01 |
| 2021-Q2 | 2021-09-01 |
| 2021-Q3 | 2021-11-13 |
| 2021-Q4 | 2022-03-21 |
| 2022-Q1 | 2022-05-18 |
| 2022-Q2 | 2022-08-06 |
| 2022-Q3 | 2022-11-03 |
| 2022-Q4 | 2023-01-10 |
| 2023-Q1 | 2023-05-04 |
| 2023-Q2 | 2023-07-10 |
| 2023-Q3 | 2023-10-13 |
| 2023-Q4 | 2024-01-06 |
| 2024-Q1 | 2024-04-10 |
| 2024-Q2 | 2024-07-13 |
| 2024-Q3 | 2024-10-08 |
| 2024-Q4 | 2025-01-06 |
| 2025-Q1 | 2025-04-09 |
| 2025-Q2 | 2025-07-08 |
| 2025-Q3 | 2025-10-04 |
| 2025-Q4 | 2026-01-12 |
| 2026-Q1 | 2026-04-11 |
| 2026-Q2 | 2026-07-15 |
| 2026-Q3 | 2026-10-14 |
Extensions
| Valid to |
|---|
| 2022-06-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AGI INFRA LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Punjab National Bank | |
| Other projects in this city pack | 16 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10381&inPromoter_ID=1099&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- Engineers Certificate (Form 2)
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Environment Clearance certificate/ NOC · 2018-02-26
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2018-03-26
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- Extension of Registration Certificate · Sign in to download
- CLU Certificate
- Environment Clearance certificate/ NOC · 2018-02-26
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2018-03-26
- Extension order · Sign in to download
- 2019-Q4 · 2021-01-02
- 2020-Q1 · 2021-01-11
- 2020-Q2 · 2021-01-12
- 2020-Q3 · 2021-01-22
- 2020-Q4 · 2021-09-01
- 2021-Q1 · 2021-09-01
- 2021-Q2 · 2021-09-01
- 2021-Q3 · 2021-11-13
- 2021-Q4 · 2022-03-21
- 2022-Q1 · 2022-05-18
- 2022-Q2 · 2022-08-06
- 2022-Q3 · 2022-11-03
- 2022-Q4 · 2023-01-10
- 2023-Q1 · 2023-05-04
- 2023-Q2 · 2023-07-10
- 2023-Q3 · 2023-10-13
- 2023-Q4 · 2024-01-06
- 2024-Q1 · 2024-04-10
- 2024-Q2 · 2024-07-13
- 2024-Q3 · 2024-10-08
- 2024-Q4 · 2025-01-06
- 2025-Q1 · 2025-04-09
- 2025-Q2 · 2025-07-08
- 2025-Q3 · 2025-10-04
- 2025-Q4 · 2026-01-12
- 2026-Q1 · 2026-04-11
- 2026-Q2 · 2026-07-15
- 2026-Q3 · 2026-10-14