AHAD HILLS

AHAD BUILDERS PRIVATE LIMITED · Mandya
Construction progress100%
Completion2025-03-31Proposed
Registered on2023-09-01
Valid to2025-03-31
Approvals17
Complaints0

Sections

Property title & search report
Approvals17 approvals
Disputes & cases0 project complaints · 6 promoter complaints
Contract & costs3 cost heads · 2 quarters
Technical report
Construction & progress3 progress details · 2 quarters
Developer & finance
Developer4 developer details
The evidence
Sources307 documents · 21 source links

Registration

Registration

PromoterAHAD BUILDERS PRIVATE LIMITED
DistrictMandya
RegulatorK-RERA
Registration numberPRM/KA/RERA/1267/374/PR/010923/006213
Registered on2023-09-01
Valid to2025-03-31
Project typePlotted Development
Status (as filed)APPROVED