Overview
AIPL Joy Street Jalandhar
Francolin Infrastructure Private Limited · Jalandhar
Units72
Completion2028-04-14Proposed
Valid to2028-04-14
Approvals11
Sections
| Property title & search report | |
|---|---|
| Approvals | 11 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 2 unit types |
| Construction & progress | 2 progress details · 12 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 30 documents · 25 source links |
Registration
Registration
| Promoter | Francolin Infrastructure Private Limited | |
|---|---|---|
| District | Jalandhar | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-JAL33-PC0191 | |
| Valid to | 2028-04-14 | |
| Project type | (1) Commercial (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2028-04-14 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| Electric Substation NOC | Permissions (Received) | 2023-07-18 |
| License as Promoter from competent Authority | 2021-11-26 | |
| License to develop colony or society from Competent Authority | ||
| NOC from NHAI/ PWD | 2022-05-01 | |
| Other Document (Access NOC NHAI attached.) | 2022-11-01 | |
| Other Document (Clarification regarding EC NOC and EIA Notf) | 2023-09-05 | |
| Other Document (Forest NOC attached) | 2022-12-16 | |
| Other Document (Licence) | 2023-05-29 | |
| Other Document (Pollution NOC CTE attached) | 2023-05-18 | |
| Pollution Clearance from Punjab Pollution Control Board | 2023-05-18 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,16,61,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 23,744.17 | |
|---|---|---|
| Units | 72 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| Type 1 | 143.67 | 68 | COMMERCIAL PLOTS |
| Type 2 | 223.79 | 4 | COMMERCIAL PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-08-14 | |
|---|---|---|
| Proposed completion | 2028-04-14 |
Quarterly progress
| 2023-Q4 | 2024-06-03 |
| 2024-Q1 | 2024-06-03 |
| 2024-Q2 | 2024-07-18 |
| 2024-Q3 | 2025-05-31 |
| 2024-Q4 | 2025-05-31 |
| 2025-Q1 | 2025-05-31 |
| 2025-Q2 | 2025-08-18 |
| 2025-Q3 | 2025-11-04 |
| 2025-Q4 | 2026-02-21 |
| 2026-Q1 | 2026-04-10 |
| 2026-Q2 | 2026-07-14 |
| 2026-Q3 | 2026-10-09 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Francolin Infrastructure Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | Others | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11619&inPromoter_ID=2495&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- Amendments or revisions in sanctioned Layout/ Sanction / Building Plan · 2023-05-29
- Borewell Registration certificate from Central Ground Water Authority · 2023-05-24
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2023-07-18
- License as Promoter from competent Authority · 2021-11-26
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2022-05-01
- Other Document (Access NOC NHAI attached.) · 2022-11-01
- Other Document (Clarification regarding EC NOC and EIA Notf) · 2023-09-05
- Other Document (Forest ) · 2022-12-16 · Sign in to download
- Other Document (Forest NOC attached) · 2022-12-16
- Other Document (Licence) · 2023-05-29
- Other Document (Pollution NOC CTE attached) · 2023-05-18
- Other Document (Reply to observation 24.08.2023) · 2023-08-24 · Sign in to download
- Other Document (RERA Observation reply submission. ) · 2023-07-28 · Sign in to download
- Other Document (Service Plans approved) · 2023-05-29
- Other Document (Solid Waste) · 2023-07-26 · Sign in to download
- Other Document (Zoning Control Sheet Application) · 2023-06-01 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2023-05-18
- Project Land Khasra Report or Plan
- CLU Certificate
- Electric Substation NOC · 2023-07-18
- License as Promoter from competent Authority · 2021-11-26
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2022-05-01
- Other Document (Access NOC NHAI attached.) · 2022-11-01
- Other Document (Clarification regarding EC NOC and EIA Notf) · 2023-09-05
- Other Document (Forest NOC attached) · 2022-12-16
- Other Document (Licence) · 2023-05-29
- Other Document (Pollution NOC CTE attached) · 2023-05-18
- Pollution Clearance from Punjab Pollution Control Board · 2023-05-18
- 2023-Q4 · 2024-06-03
- 2024-Q1 · 2024-06-03
- 2024-Q2 · 2024-07-18
- 2024-Q3 · 2025-05-31
- 2024-Q4 · 2025-05-31
- 2025-Q1 · 2025-05-31
- 2025-Q2 · 2025-08-18
- 2025-Q3 · 2025-11-04
- 2025-Q4 · 2026-02-21
- 2026-Q1 · 2026-04-10
- 2026-Q2 · 2026-07-14
- 2026-Q3 · 2026-10-09