Overview
AISHWARYAM VILLE
M/S VINAYAK HOMES · RAIPUR
Units163
Booked131 of 163As of 2026-06-30
Construction progress100%As of 2026-06-30
Completion2026-12-05Revised · Proposed 2023-03-31
Registered on2019-06-13
Approvals2
Cases9
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Disputes & cases | 9 cases |
| Contract & costs | 2 cost heads · 29 quarters |
| Technical report | |
| Site & area | 3 site details · 163 unit types |
| Construction & progress | 4 progress details · 29 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 188 documents · 17 source links |
Registration
Registration
| Promoter | M/S VINAYAK HOMES | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA130619000987 | |
| Registered on | 2019-06-13 | |
| Project type | Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2023-03-31 | |
| Revised completion | 2026-12-05 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| SM-EXP-2025-03101 | CG RERA | Complaint | Disposed | 2026-01-12 |
| M-PRO-2025-02714 | CG RERA | Complaint | Disposed | 2025-04-23 |
| M-PRO-2024-02604 | CG RERA | Complaint | Disposed | 2025-03-28 |
| M-PRO-2024-02603 | CG RERA | Complaint | Disposed | 2025-01-17 |
| M-PRO-2024-02628 | CG RERA | Complaint | Disposed | 2025-01-10 |
| M-PRO-2024-02629 | CG RERA | Complaint | Disposed | 2025-01-10 |
| M-PRO-2024-02627 | CG RERA | Complaint | Disposed | 2025-01-10 |
| M-PRO-2024-02625 | CG RERA | Complaint | Disposed | 2024-12-30 |
| M-PRO-2024-02596 | CG RERA | Complaint | Disposed | 2024-12-16 |
Complaints & cases
| Cases | 9 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹10,01,58,000 | |
|---|---|---|
| Construction | ₹6,49,86,000 |
Quarterly money flows
| 2019-Q2 | ₹4,82,210 |
| 2019-Q3 | ₹5,982 |
| 2019-Q4 | ₹10,864 |
| 2020-Q1 | ₹10,628 |
| 2020-Q2 | ₹10,628 |
| 2020-Q3 | ₹10,628 |
| 2020-Q4 | ₹10,302 |
| 2021-Q1 | ₹5,620 |
| 2021-Q2 | ₹5,620 |
| 2021-Q3 | ₹5,324 |
| 2021-Q4 | ₹5,029 |
| 2022-Q1 | ₹4,881 |
| 2022-Q2 | ₹4,39,339 |
| 2022-Q3 | ₹4,07,139 |
| 2022-Q4 | ₹137 |
| 2023-Q1 | ₹105 |
| 2023-Q2 | ₹105 |
| 2023-Q3 | ₹67,594 |
| 2023-Q4 | ₹67,593 |
| 2024-Q1 | ₹1,151 |
| 2024-Q2 | ₹2,321 |
| 2024-Q3 | ₹991 |
| 2024-Q4 | ₹9,509 |
| 2025-Q1 | ₹8,017 |
| 2025-Q2 | ₹1,58,579 |
| 2025-Q3 | ₹7,720 |
| 2025-Q4 | ₹7,720 |
| 2026-Q1 | ₹7,572 |
| 2026-Q2 | ₹7,423 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 163 | |
|---|---|---|
| Booked | 131 | |
| Booked as of | 2026-06-30 |
Unit types
| Plot-1 | 1 | 1 |
| Plot-2 | 1 | 1 |
| Plot-3 | 1 | 1 |
| Plot-4 | 1 | 1 |
| Plot-5 | 1 | 1 |
| Plot-6 | 1 | 1 |
| Plot-7 | 1 | 1 |
| Plot-8 | 1 | 1 |
| Plot-9 | 1 | 1 |
| Plot-10 | 1 | 1 |
| Plot-11 | 1 | 1 |
| Plot-12 | 1 | 1 |
| Plot-13 | 1 | 1 |
| Plot-14 | 1 | 1 |
| Plot-15 | 1 | 1 |
| Plot-16 | 1 | 1 |
| Plot-17 | 1 | 1 |
| Plot-18 | 1 | 1 |
| Plot-19 | 1 | 1 |
| Plot-20 | 1 | 1 |
| Plot-21 | 1 | 1 |
| Plot-22 | 1 | 1 |
| Plot-23 | 1 | 1 |
| Plot-24 | 1 | 1 |
| Plot-25 | 1 | 1 |
| Plot-26 | 1 | 1 |
| Plot-27 | 1 | 1 |
| Plot-28 | 1 | 1 |
| Plot-29 | 1 | 0 |
| Plot-30 | 1 | 0 |
| Plot-31 | 1 | 0 |
| Plot-32 | 1 | 0 |
| Plot-33 | 1 | 1 |
| Plot-34 | 1 | 1 |
| Plot-35 | 1 | 1 |
| Plot-36 | 1 | 1 |
| Plot-37 | 1 | 0 |
| Plot-38 | 1 | 0 |
| Plot-39 | 1 | 1 |
| Plot-40 | 1 | 1 |
| Plot-41 | 1 | 1 |
| Plot-42 | 1 | 1 |
| Plot-43 | 1 | 1 |
| Plot-44 | 1 | 1 |
| Plot-45 | 1 | 1 |
| Plot-46 | 1 | 0 |
| Plot-47 | 1 | 0 |
| Plot-48 | 1 | 0 |
| Plot-49 | 1 | 1 |
| Plot-50 | 1 | 1 |
| Plot-51 | 1 | 1 |
| Plot-52 | 1 | 1 |
| Plot-53 | 1 | 1 |
| Plot-54 | 1 | 0 |
| Plot-55 | 1 | 1 |
| Plot-56 | 1 | 1 |
| Plot-57 | 1 | 1 |
| Plot-58 | 1 | 1 |
| Plot-59 | 1 | 1 |
| Plot-60 | 1 | 1 |
| Plot-61 | 1 | 1 |
| Plot-62 | 1 | 0 |
| Plot-63 | 1 | 0 |
| Plot-64 | 1 | 0 |
| Plot-65 | 1 | 0 |
| Plot-66 | 1 | 1 |
| Plot-67 | 1 | 1 |
| Plot-68 | 1 | 1 |
| Plot-69 | 1 | 1 |
| Plot-70 | 1 | 1 |
| Plot-71 | 1 | 0 |
| Plot-72 | 1 | 1 |
| Plot-73 | 1 | 1 |
| Plot-74 | 1 | 1 |
| Plot-75 | 1 | 1 |
| Plot-76 | 1 | 1 |
| Plot-77 | 1 | 1 |
| Plot-78 | 1 | 0 |
| Plot-79 | 1 | 0 |
| Plot-80 | 1 | 0 |
| Plot-81 | 1 | 0 |
| Plot-82 | 1 | 1 |
| Plot-83 | 1 | 1 |
| Plot-84 | 1 | 1 |
| Plot-85 | 1 | 1 |
| Plot-86 | 1 | 1 |
| Plot-87 | 1 | 1 |
| Plot-88 | 1 | 1 |
| Plot-89 | 1 | 1 |
| Plot-90 | 1 | 0 |
| Plot-91 | 1 | 1 |
| Plot-92 | 1 | 1 |
| Plot-93 | 1 | 1 |
| Plot-94 | 1 | 1 |
| Plot-95 | 1 | 1 |
| Plot-96 | 1 | 1 |
| Plot-97 | 1 | 0 |
| Plot-98 | 1 | 0 |
| Plot-99 | 1 | 0 |
| Plot-100 | 1 | 0 |
| Plot-101 | 1 | 1 |
| Plot-102 | 1 | 1 |
| Plot-103 | 1 | 1 |
| Plot-104 | 1 | 1 |
| Plot-105 | 1 | 1 |
| Plot-106 | 1 | 1 |
| Plot-107 | 1 | 1 |
| Plot-108 | 1 | 1 |
| Plot-109 | 1 | 1 |
| Plot-110 | 1 | 1 |
| Plot-111 | 1 | 1 |
| Plot-112 | 1 | 1 |
| Plot-113 | 1 | 1 |
| Plot-114 | 1 | 1 |
| Plot-115 | 1 | 1 |
| Plot-116 | 1 | 1 |
| Plot-117 | 1 | 1 |
| Plot-118 | 1 | 1 |
| Plot-119 | 1 | 1 |
| Plot-120 | 1 | 1 |
| Plot-121 | 1 | 1 |
| Plot-122 | 1 | 0 |
| Plot-123 | 1 | 0 |
| Plot-124 | 1 | 0 |
| Plot-125 | 1 | 0 |
| Plot-126 | 1 | 0 |
| Plot-127 | 1 | 1 |
| Plot-LIG-128 | 1 | 1 |
| Plot-LIG-129 | 1 | 1 |
| Plot-LIG-130 | 1 | 0 |
| Plot-131 | 1 | 1 |
| Plot-132 | 1 | 1 |
| Plot-133 | 1 | 1 |
| Plot-134 | 1 | 1 |
| Plot-135 | 1 | 1 |
| Plot-136 | 1 | 1 |
| Plot-137 | 1 | 1 |
| Plot-138 | 1 | 1 |
| Plot-139 | 1 | 1 |
| Plot-140 | 1 | 1 |
| Plot-141 | 1 | 1 |
| Plot-142 | 1 | 1 |
| Plot-143 | 1 | 1 |
| Plot-144 | 1 | 1 |
| Plot-145 | 1 | 1 |
| Plot-LIG-146 | 1 | 1 |
| Plot-LIG-147 | 1 | 1 |
| Plot-LIG-148 | 1 | 1 |
| Plot-LIG-149 | 1 | 1 |
| Plot-LIG-150 | 1 | 1 |
| Plot-LIG-151 | 1 | 1 |
| Plot-LIG-152 | 1 | 1 |
| Plot-LIG-153 | 1 | 1 |
| Plot-LIG-154 | 1 | 1 |
| Plot-LIG-155 | 1 | 1 |
| Plot-LIG-156 | 1 | 1 |
| Plot-LIG-157 | 1 | 1 |
| Plot-LIG-158 | 1 | 0 |
| Plot-LIG-159 | 1 | 1 |
| Plot-160 | 1 | 1 |
| Plot-161 | 1 | 1 |
| Commercial-1 | 1 | 1 |
| Commercial-2 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2023-03-31 | |
| Revised completion | 2026-12-05 |
Quarterly progress
| 2019-Q2 | 0% |
| 2019-Q3 | 4% |
| 2019-Q4 | 8% |
| 2020-Q1 | 11% |
| 2020-Q2 | 11% |
| 2020-Q3 | 11% |
| 2020-Q4 | 19% |
| 2021-Q1 | 24% |
| 2021-Q2 | 61% |
| 2021-Q3 | 61% |
| 2021-Q4 | 61% |
| 2022-Q1 | 61% |
| 2022-Q2 | 61% |
| 2022-Q3 | 61% |
| 2022-Q4 | 61% |
| 2023-Q1 | 64% |
| 2023-Q2 | 77% |
| 2023-Q3 | 78% |
| 2023-Q4 | 82% |
| 2024-Q1 | 83% |
| 2024-Q2 | 84% |
| 2024-Q3 | 86% |
| 2024-Q4 | 86% |
| 2025-Q1 | 87% |
| 2025-Q2 | 88% |
| 2025-Q3 | 100% |
| 2025-Q4 | 100% |
| 2026-Q1 | 100% |
| 2026-Q2 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/S VINAYAK HOMES | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTIzOA==
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-01-12 · Sign in to download
- Final order · 2025-04-23 · Sign in to download
- Final order · 2025-03-28 · Sign in to download
- Final order · 2025-01-17 · Sign in to download
- Final order · 2025-01-10 · Sign in to download
- Final order · 2025-01-10 · Sign in to download
- Final order · 2025-01-10 · Sign in to download
- Final order · 2024-12-30 · Sign in to download
- Final order · 2024-12-16 · Sign in to download
- Interim order · 2025-10-17 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- SM-EXP-2025-03101 · Sign in to download
- M-PRO-2025-02714 · Sign in to download
- M-PRO-2024-02604 · Sign in to download
- M-PRO-2024-02603 · Sign in to download
- M-PRO-2024-02628 · Sign in to download
- M-PRO-2024-02629 · Sign in to download
- M-PRO-2024-02627 · Sign in to download
- M-PRO-2024-02625 · Sign in to download
- M-PRO-2024-02596 · Sign in to download