| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | 1 | Clear |
| Disputes & cases | – | – | – | – |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
Disputes & cases
Builder: AKSHADHAA ASSISTED LIVING ESTABLISHMENT LLP
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Not checked. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Not checked. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None found. | ||||||
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| Not checked. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
Source: K-RERA project page and the documents filed there, as read by us.
| – |
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | 2 | Clear |
|---|
| Loan & collateral | – | – | – | – |
|---|
| Survey numbers | 333/1, 333/3, 333/4, Survey Number | |
|---|---|---|
| Area on the KGIS map | Not verified yet | |
| Land area of this registration | 19,627 sq m | |
| Building plan (Local Planning Authority) | Sanctioned 3 Aug 2023 · No. 39 | |
|---|---|---|
| Power NOC (BESCOM) | Not verified yet | |
| Fire NOC | Not verified yet | |
| Environmental clearance | Not verified yet | |
| Airport height NOC | Not verified yet | |
| Pollution board (CFE) | Not verified yet | |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 0 | |
| RERA completion date | 14 Feb 2029 |
2BHK 30.8%Studio 30.3%2BHK · avg 71 m² 15.4%Studio · avg 37 m² 15.1%2 other types 8.4%
| 1BHK | 10 | 6,082 |
| 1BHK | 20 | Not filed |
| 2BHK | 55 | 42,291 |
| 2BHK | 110 | Not filed |
| Studio | 54 | 21,754 |
| Studio | 108 | Not filed |
| Sold, Q2 2026-27 | 97 / 119 | |
|---|---|---|
| Unsold, Q2 2026-27 | 22 | |
| Months to sell, derived from filed bookings | 40 months |
| Amenities declared | Earth work and other leveling preparation work · Foundation footing work · Upto Plinth Level · Sub-structure flooring (Parking Floor, more than one floor below general ground level) · Retaining wall (All types) · RCC or MS Framed structure · Masonry Construction · Plastering inside , outside & Ceiling · Joinery: Doors, Windows, Ventilators etc · Basic work of Water supply, Sanitary and Electrification · Dadoing, Skirting, Flooring, Tiles work (All types) · Railing and Grill fixing · Electrification, Water supply and Sanitary Finishing · Painting · Weather Proof work(tile,concrete) · Elevation work · Internal and External work including landscapes as per sanctioned drawings · Water Supply · Sewage and Drainage System · Water conservation/rain water harvesting/recharge of ground water · Energy management · Fire protection and fire safety requirements · Solid waste management and disposal · Emergency Evacuation services · Water Supply · Internal Roads & Footpaths · Sewage and Drainage System · Electricity supply transformer and substation · Solid waste management and disposal · Emergency Evacuation services · Storm water drains · Use of renewable energy · Water conservation/rain water harvesting/recharge of ground water · Fire protection and fire safety requirements · Sewage Treatment Plant (STP) · Parks & Tree planting · Street Lighting · Electricity · CCTV Surveillance · Community Hall · Gym · Parks · Power Backup · Piped Gas · Water and Sanitation · SNI Learning Center Facility · Staircases · Lifts · Corridor/Lobbies · Fire escapes · Common entrance and exit for the building/common portico/foyer/verandah · Terrace · Open parking areas · Provision for lodging of management staff and security staff · Water conservation and renewable energy · Earth work and other leveling preparation work · Foundation footing work · Upto Plinth Level · Sub-structure flooring (Parking Floor, more than one floor below general ground level) · Retaining wall (All types) · RCC or MS Framed structure · Masonry Construction · Plastering inside , outside & Ceiling · Joinery: Doors, Windows, Ventilators etc · Basic work of Water supply, Sanitary and Electrification · Dadoing, Skirting, Flooring, Tiles work (All types) · Railing and Grill fixing · Electrification, Water supply and Sanitary Finishing · Painting · Weather Proof work(tile,concrete) · Elevation work · Internal and External work including landscapes as per sanctioned drawings · Water Supply · Sewage and Drainage System · Water conservation/rain water harvesting/recharge of ground water · Energy management · Fire protection and fire safety requirements · Solid waste management and disposal · Emergency Evacuation services · Water Supply · Internal Roads & Footpaths · Sewage and Drainage System · Electricity supply transformer and substation · Solid waste management and disposal · Emergency Evacuation services · Storm water drains · Use of renewable energy · Water conservation/rain water harvesting/recharge of ground water · Fire protection and fire safety requirements · Sewage Treatment Plant (STP) · Parks & Tree planting · Street Lighting · Electricity · CCTV Surveillance · Community Hall · Gym · Parks · Power Backup · Piped Gas · Water and Sanitation · SNI Learning Center Facility · Staircases · Lifts · Corridor/Lobbies · Fire escapes · Common entrance and exit for the building/common portico/foyer/verandah · Terrace · Open parking areas · Provision for lodging of management staff and security staff · Water conservation and renewable energy | |
|---|---|---|
| Kitchen handover | Not verified yet | |
| Sewage plant | Not verified yet | |
| Power backup | Declared by the promoter | |
As the promoter reported it
| Main structure | Not verified yet | |
|---|---|---|
| Electrical and plumbing finishing | Not verified yet | |
| Internal roads | Not started | |
| Club house | Not verified yet | |
| Completion | 55% | |
| Completion, accountant | Not verified yet | |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | Not verified yet | |
| RERA completion date | 14 Feb 2029 | |
| Work began, as filed | 14 Feb 2024 | |
The promoter filed this with the registration.
| Windows | Not verified yet | |
|---|---|---|
| Flooring | Not verified yet | |
| Toilet tiles, spec vs brochure | Not verified yet | |
| Wiring | Not verified yet | |
| Sanctioned load per flat | Not verified yet | |
| Power backup | Provided | |
| Sewage plant | Not verified yet | |
The promoter filed this with the registration.
| Estimated cost | ₹40.00 Cr | |
|---|---|---|
| Cost incurred | Not verified yet | |
| Cost left | Not verified yet | |
| Collected from buyers | Not verified yet | |
| Receivable, sold flats | Not verified yet | |
| Land cost revision | Not verified yet | |
Sold (97) 81.5%Unsold (22) 18.5%
| Sold, Q3 2025-26 | 92 / 119 · 27 available | |
|---|---|---|
| Sold, Q4 2025-26 | 97 / 119 · 22 available | |
| Sold, Q1 2026-27 | 97 / 119 · 22 available | |
| Sold, Q2 2026-27 | 97 / 119 · 22 available | |
| Unsold, Q2 2026-27 | 22 | |
| Sold in Q4 2025-26 | 5 | |
| Sold in Q1 2026-27 | 0 | |
| Sold in Q2 2026-27 | 0 |
| Escrow bank | Axis Bank | |
|---|---|---|
| Designated account, collected | Not verified yet | |
| Designated account, withdrawn | Not verified yet | |
| Withdrawn from the escrow account to date | ₹0 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 0 | |
| Developer's project loan | Not verified yet | |
|---|---|---|
| Records searched to | Not verified yet | |
| Building plan | Sanctioned 3 Aug 2023 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| Sale deed in favour of | Not verified yet | |
| Escrow bank | Axis Bank | |