DOSLJaipur, Rajasthan Workspace

Overview

Akshat Kanota Estate-Phase 2

AKSHAT APARTMENTS PRIVATE LIMITED · Nayla Road
Units66
Booked0 of 66As of 2019-12-31
Completion2020-12-31Revised · Proposed 2016-04-15
Registered on2017-10-12
Valid to2020-12-31

Sections

Property title & search report
Approvals1 occupancy certificate
Contract & costs3 cost heads · 1 quarter
Technical report
Site & area7 site details · 66 unit types
Construction & progress2 progress details · 1 quarter
Developer & finance
Developer4 developer details · 1 professional firm
The evidence
Sources75 documents · 6 source links

Registration

Registration

PromoterAKSHAT APARTMENTS PRIVATE LIMITED
DistrictJaipur
LocalityNayla Road
RegulatorRajasthan RERA
Registration numberRAJ/P/2017/334
Registered on2017-10-12
Valid to2020-12-31
Project typeGroup Housing
Status (as filed)COMPLETED & OC ISSUED
Proposed completion2016-04-15
Revised completion2020-12-31