Overview
ALORA
VARDHAMAN ENTERPRISES · Gulab Badi Bhavan Nirman Sahkar Smiti, Vardhaman Nagar-B
Units36
Booked24 of 36As of 2026-09-30
Completion2028-05-31Revised · Proposed 2023-07-01
Registered on2024-02-20
Valid to2028-05-31
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 7 site details · 12 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 31 documents · 6 source links |
Registration
Registration
| Promoter | VARDHAMAN ENTERPRISES | |
|---|---|---|
| District | Jaipur | |
| Locality | Gulab Badi Bhavan Nirman Sahkar Smiti, Vardhaman Nagar-B | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2024/3016 | |
| Registered on | 2024-02-20 | |
| Valid to | 2028-05-31 | |
| Project type | Group Housing | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2023-07-01 | |
| Revised completion | 2028-05-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,26,23,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹10,26,23,000 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2026-Q3 | ₹10,68,27,970 | ₹51,62,291.67 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,091.25 | |
|---|---|---|
| Built-up (m²) | 5,676.53 | |
| Towers | 36 | |
| Maximum floors | 6 | |
| Units | 36 | |
| Booked | 24 | |
| Booked as of | 2026-09-30 |
Unit types
| 3 BHK 601 with private terrace | 89.47 | 1 | 1 | ALORA |
| 3 BHK 602 with private terrace | 89.24 | 1 | 1 | ALORA |
| 3 BHK 603 with private terrace | 86.69 | 1 | 0 | ALORA |
| 3 BHK 604 with private terrace | 89.65 | 1 | 1 | ALORA |
| 3 BHK 605 with private terrace | 87.61 | 1 | 1 | ALORA |
| 3 BHK 606 with private terrace | 87.12 | 1 | 1 | ALORA |
| 3 BHK TYPE 1 (101 TO 501) | 89.47 | 5 | 5 | ALORA |
| 3 BHK TYPE 2 (102 TO 502) | 89.24 | 5 | 5 | ALORA |
| 3 BHK TYPE 3 (103 TO 503) | 86.69 | 5 | 1 | ALORA |
| 3 BHK TYPE 4 (104 TO 504) | 89.65 | 5 | 3 | ALORA |
| 3 BHK TYPE 5 (105 TO 505) | 87.61 | 5 | 0 | ALORA |
| 3 BHK TYPE 6 (106 TO 506) | 87.12 | 5 | 5 | ALORA |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2023-07-01 | |
|---|---|---|
| Proposed completion | 2023-07-01 | |
| Revised completion | 2028-05-31 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2026-Q3 | 2026-08-13 | 24 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | VARDHAMAN ENTERPRISES | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | FINGROWTH CO-OPERATIVE BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=jxfY4B1mzteUUUmC_10rSA
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/jxfY4B1mzteUUUmC_10rSA
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=jxfY4B1mzteUUUmC%2F10rSA%3D%3D&QuarterIdEnc=%2BKD7QcnAdOtELCm57RAuQA%3D%3D&PT=1&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=AkLoCNhvjpU%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Other than Plotted)
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Fire Fighting Provision
- Others
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- unitsPlanPath
- R1_filepath · Sign in to download
- R2_filepath · Sign in to download
- R3_filepath · Sign in to download
- RERABankStatementUpload · Sign in to download
- NoLienCertificateUpload