Overview
AMBIENCE BUSINESS PARK
SHRI RAM INFRA RESOURCES · BILASPUR
Booked24As of 2022-03-31
Construction progress100%As of 2022-03-31
Completion2023-08-30Revised · Proposed 2022-11-30
Registered on2019-09-07
Approvals5
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 11 quarters |
| Technical report | |
| Site & area | 2 site details · 29 unit types |
| Construction & progress | 4 progress details · 11 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 92 documents · 11 source links |
Registration
Registration
| Promoter | SHRI RAM INFRA RESOURCES | |
|---|---|---|
| District | BILASPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA070919001035 | |
| Registered on | 2019-09-07 | |
| Project type | Commercial | |
| Status (as filed) | New | |
| Proposed completion | 2022-11-30 | |
| Revised completion | 2023-08-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Nazul clearance in case of Nazul Area |
| Enviornment Clearance |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXP-2024-02177 | CG RERA | Complaint | Disposed | 2024-03-15 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,39,72,500 | |
|---|---|---|
| Construction | ₹1,90,69,540 |
Quarterly money flows
| 2019-Q3 | ₹0 |
| 2019-Q4 | ₹0 |
| 2020-Q1 | ₹0 |
| 2020-Q2 | ₹0 |
| 2020-Q3 | ₹0 |
| 2020-Q4 | ₹5,00,000 |
| 2021-Q1 | ₹0 |
| 2021-Q2 | ₹0 |
| 2021-Q3 | ₹0 |
| 2021-Q4 | ₹0 |
| 2022-Q1 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Booked | 24 | |
|---|---|---|
| Booked as of | 2022-03-31 |
Unit types
| Commercial | 27 | 18 | |
| COMMERCIAL | 61.6 | 1 | 1 |
| COMMERCIAL | 31.8 | 1 | 1 |
| COMMERCIAL | 31.8 | 1 | 1 |
| COMMERCIAL | 20.2 | 1 | 1 |
| COMMERCIAL | 54 | 1 | 1 |
| COMMERCIAL | 45.65 | 1 | 1 |
| COMMERCIAL | 61.35 | 1 | 1 |
| COMMERCIAL | 55 | 1 | 1 |
| COMMERCIAL | 55.6 | 1 | 1 |
| COMMERCIAL | 46.6 | 1 | 0 |
| COMMERCIAL | 24.1 | 1 | 1 |
| COMMERCIAL | 24.1 | 1 | 1 |
| COMMERCIAL | 15.2 | 1 | 1 |
| COMMERCIAL | 40.7 | 1 | 1 |
| COMMERCIAL | 34.55 | 1 | 0 |
| COMMERCIAL | 46.35 | 1 | 1 |
| COMMERCIAL | 55 | 1 | 1 |
| COMMERCIAL | 55.6 | 1 | 0 |
| COMMERCIAL | 46.6 | 1 | 1 |
| COMMERCIAL | 24.1 | 1 | 1 |
| COMMERCIAL | 24.1 | 1 | 1 |
| COMMERCIAL | 15.2 | 1 | 1 |
| COMMERCIAL | 40.7 | 1 | 1 |
| COMMERCIAL | 34.55 | 1 | 1 |
| COMMERCIAL | 46.35 | 1 | 1 |
| COMMERCIAL | 55 | 1 | 1 |
| COMMERCIAL | 55.6 | 1 | 1 |
| Commercial | 1,026.6 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2022-03-31 | |
| Proposed completion | 2022-11-30 | |
| Revised completion | 2023-08-30 |
Quarterly progress
| 2019-Q3 | 47% |
| 2019-Q4 | 55% |
| 2020-Q1 | 76% |
| 2020-Q2 | 80% |
| 2020-Q3 | 91% |
| 2020-Q4 | 95% |
| 2021-Q1 | 98% |
| 2021-Q2 | 99% |
| 2021-Q3 | 99% |
| 2021-Q4 | 100% |
| 2022-Q1 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHRI RAM INFRA RESOURCES | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | HDFC Bank | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTI4Ng==
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Enviornment Clearance
- Modified Layout Plan
- Development Permission from competent authorities
- Agent Details · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2024-03-15 · Sign in to download
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Enviornment Clearance
- Development Permission from competent authorities
- SM-EXP-2024-02177 · Sign in to download