AMBIENCE CREACIONS
AMBIENCE PROJECTS AND INFRASTRUCTURE PVT. LTD. · Gurugram
Completion2022-03-31Revised · Proposed 2021-09-30
Registered on2017-10-17
Valid to2023-09-29
Approvals19
Sections
| Property title & search report | |
|---|---|
| Approvals | 19 approvals |
| Disputes & cases | 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 8 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 14 documents · 3 source links |
Registration
Registration
| Promoter | AMBIENCE PROJECTS AND INFRASTRUCTURE PVT. LTD. | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 318 OF 2017 DATED 17.10.2017 | |
| Registered on | 2017-10-17 | |
| Valid to | 2023-09-29 | |
| Status (as filed) | Lapsed Project | |
| Proposed completion | 2021-09-30 | |
| Revised completion | 2022-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 48 of 2012(11-05-2018) | Town & Country Planning Department | |
| Layout Plan | |||
| Building Plan | |||
| I. LICENSE | 2012-05-16 | ||
| II. ELECTRICAL LOAD AVAILABILITY | |||
| III. ENVIRONMENTAL CLEARANCE | |||
| IV. CONSENT TO ESTABLISH | |||
| V. MINING PERMISSION | |||
| VI. FIRE SCHEME APPROVAL | |||
| VII. SERVICES ESTIMATES AND PLANS | |||
| VIII. FOREST NOC | 2013-10-24 | ||
| IX. AIRPORT HEIGHT CLEARANCE | |||
| X. HUDA CONSTRUCTION WATER NOC | |||
| XI. RENEWAL LICENSE | |||
| XII. GMDA/ HUDA/ MCG SERVICES CONNECTION PERMISSION | |||
| XIII. ELECTRICAL LOAD CONNECTION/ ENERGIZATION | |||
| XIV. HSD STORAGE NOC | |||
| XV. CONSENT TO OPERATE NOC | |||
| XVI. OCCUPATION PERMISSION INCLUDING FIRE NOC, HSVP INTERNAL AND EXTERNAL SERVICES NOC, LIFT NOC, CHIEF ELECTRICAL ENGINEER NOC AND ANY OTHER REQUIRED APPROVAL |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2023-09-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,31,51,00,000 | |
|---|---|---|
| Construction | ₹10,58,07,00,000 | |
| Total | ₹24,68,29,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 14.819 | |
|---|---|---|
| FAR | 1.75 |
Unit types
| 1 | |
| 2 | |
| 3 | 92 |
| 4 | |
| 5 | |
| 6 | |
| 7 | |
| 8 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2021-09-30 | |
|---|---|---|
| Revised completion | 2022-03-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | AMBIENCE PROJECTS AND INFRASTRUCTURE PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/1005
- https://nominatim.openstreetmap.org/search?q=sector+22%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2017-10-17
- DEMARCATION PLAN · 2020-01-19
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2020-01-19 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2020-01-19
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2020-01-19 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2020-01-19
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2020-01-19 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2020-01-19 · Sign in to download
- DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD · 2020-01-19 · Sign in to download
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2020-01-19
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2020-01-19
- ZONING PLAN · 2020-01-19
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2020-01-19
- EXTENSION NO. 02 OF 2023 DATED 23.02.2023 · 2023-06-15 · Sign in to download