Overview
Anand Enclave Block-E
Anand Enclave Developers Pvt. Ltd. · Ludhiana
Units190
Completion2029-03-31Proposed
Valid to2029-03-31
Approvals13
Sections
| Property title & search report | |
|---|---|
| Approvals | 13 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 42 unit types |
| Construction & progress | 2 progress details · 10 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 26 documents · 26 source links |
Registration
Registration
| Promoter | Anand Enclave Developers Pvt. Ltd. | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH44-PR0973 | |
| Valid to | 2029-03-31 | |
| Project type | (1) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | |
| License to develop colony or society from Competent Authority | |
| NOC from Fire Department/ Chief Fire Officer | 2024-02-02 |
| NOC from NHAI/ PWD | 2024-02-07 |
| NOC from NHAI/ PWD | 2024-01-31 |
| Other Document (BDPO NOC) | 2024-02-09 |
| Other Document (Forest NOC) | 2024-02-02 |
| Other Document (PSPCL NOC ) | 2024-01-31 |
| Other Document (Tehsildar NOC) | 2024-02-02 |
| Pollution Clearance from Punjab Pollution Control Board | 2024-01-31 |
| Consent details of actual owner of Land | |
| Consent details of actual owner of Land | |
| Consent details of actual owner of Land |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹28,60,52,259 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 78,534.307 | |
|---|---|---|
| Units | 190 |
Unit types
| Plot No 1-4 | 121.355 | 4 | RESIDENTIAL PLOTS |
| Plot No 5 | 123.562 | 1 | RESIDENTIAL PLOTS |
| Plot No 6-9 | 141.907 | 4 | RESIDENTIAL PLOTS |
| Plot No 10 | 144.089 | 1 | RESIDENTIAL PLOTS |
| Plot No 11 | 142.559 | 1 | RESIDENTIAL PLOTS |
| Plot No 12-15 | 140.402 | 4 | RESIDENTIAL PLOTS |
| Plot No 16 | 111.857 | 1 | RESIDENTIAL PLOTS |
| Plot No 17-24 | 109.85 | 8 | RESIDENTIAL PLOTS |
| Plot No 25 | 111.857 | 1 | RESIDENTIAL PLOTS |
| Plot No 26-29 | 140.402 | 4 | RESIDENTIAL PLOTS |
| Plot No 30 | 142.559 | 1 | RESIDENTIAL PLOTS |
| Plot No 31 | 355.387 | 1 | RESIDENTIAL PLOTS |
| Plot No 32-38 | 278.129 | 7 | RESIDENTIAL PLOTS |
| Plot no 39 | 359.25 | 1 | RESIDENTIAL PLOTS |
| Plot No 40 | 182.05 | 1 | RESIDENTIAL PLOTS |
| Plot No 41-43 | 167.225 | 3 | RESIDENTIAL PLOTS |
| Plot No 44-45 | 182.05 | 2 | RESIDENTIAL PLOTS |
| Plot No 46-48 | 167.225 | 3 | RESIDENTIAL PLOTS |
| Plot NO 49 | 182.05 | 1 | RESIDENTIAL PLOTS |
| Plot NO 50 | 249.441 | 1 | RESIDENTIAL PLOTS |
| Plot No 51-58 | 167.225 | 8 | RESIDENTIAL PLOTS |
| Plot No 59-60 | 199.725 | 2 | RESIDENTIAL PLOTS |
| Plot No 61-68 | 199.725 | 8 | RESIDENTIAL PLOTS |
| Plot No 69 | 251.732 | 1 | RESIDENTIAL PLOTS |
| Plot No 70-92 | 209.032 | 23 | RESIDENTIAL PLOTS |
| Plot NO 93 | 197.518 | 1 | RESIDENTIAL PLOTS |
| Plot NO 94-102 | 209.032 | 9 | RESIDENTIAL PLOTS |
| Plot No 103-104 | 250.838 | 2 | RESIDENTIAL PLOTS |
| Plot No 105-114 | 256.649 | 10 | RESIDENTIAL PLOTS |
| Plot No 115-116 | 252.067 | 2 | RESIDENTIAL PLOTS |
| Plot No 117-126 | 258.622 | 10 | RESIDENTIAL PLOTS |
| Plot No 127-126 | 252.067 | 2 | RESIDENTIAL PLOTS |
| Plot NO 129-138 | 258.622 | 10 | RESIDENTIAL PLOTS |
| Plot No 139-147 | 193.237 | 9 | RESIDENTIAL PLOTS |
| Plot No 148-158 | 268.488 | 11 | RESIDENTIAL PLOTS |
| Plot No 159-168 | 251.674 | 10 | RESIDENTIAL PLOTS |
| Plot NO 169 | 253.622 | 1 | RESIDENTIAL PLOTS |
| Plot NO 170-180 | 181.824 | 11 | RESIDENTIAL PLOTS |
| Plot No 181-183 | 212.209 | 3 | RESIDENTIAL PLOTS |
| Plot NO 184-188 | 179.633 | 5 | RESIDENTIAL PLOTS |
| 1 | 3,999.347 | 1 | EWS SITE |
| School | 2,287.82 | 1 | SCHOOL SITE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-03-31 | |
|---|---|---|
| Proposed completion | 2029-03-31 |
Quarterly progress
| 2024-Q2 | 2025-07-30 |
| 2024-Q3 | 2025-07-30 |
| 2024-Q4 | 2025-07-30 |
| 2025-Q1 | 2025-07-30 |
| 2025-Q2 | 2025-07-30 |
| 2025-Q3 | 2026-07-18 |
| 2025-Q4 | 2026-07-18 |
| 2026-Q1 | 2026-07-18 |
| 2026-Q2 | 2026-07-18 |
| 2026-Q3 | 2026-10-13 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Anand Enclave Developers Pvt. Ltd. | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11956&inPromoter_ID=2842&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-02-02
- NOC from NHAI/ PWD · 2024-02-07
- NOC from NHAI/ PWD · 2024-01-31
- Other Document (BDPO NOC) · 2024-02-09
- Other Document (Forest NOC) · 2024-02-02
- Other Document (PSPCL NOC ) · 2024-01-31
- Other Document (PSTCL NO requirement from PSPCL) · 2024-02-01 · Sign in to download
- Other Document (Tehsildar NOC) · 2024-02-02
- Other Document (water and drainage) · 2024-02-09 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2024-01-31
- Consent details of actual owner of Land
- Consent details of actual owner of Land
- Consent details of actual owner of Land
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-02-02
- NOC from NHAI/ PWD · 2024-02-07
- NOC from NHAI/ PWD · 2024-01-31
- Other Document (BDPO NOC) · 2024-02-09
- Other Document (Forest NOC) · 2024-02-02
- Other Document (PSPCL NOC ) · 2024-01-31
- Other Document (Tehsildar NOC) · 2024-02-02
- Pollution Clearance from Punjab Pollution Control Board · 2024-01-31
- Consent details of actual owner of Land
- Consent details of actual owner of Land
- Consent details of actual owner of Land
- 2024-Q2 · 2025-07-30
- 2024-Q3 · 2025-07-30
- 2024-Q4 · 2025-07-30
- 2025-Q1 · 2025-07-30
- 2025-Q2 · 2025-07-30
- 2025-Q3 · 2026-07-18
- 2025-Q4 · 2026-07-18
- 2026-Q1 · 2026-07-18
- 2026-Q2 · 2026-07-18
- 2026-Q3 · 2026-10-13