Overview
ANAND ENCLAVE
ANANDSRI CONSTRUCTION PRIVATE LIMITED · Patna
Booked8As of 2025-12-31
Construction progress95%As of 2025-12-31
Completion2026-03-09Proposed
Registered on2024-04-29
Valid to2026-03-09
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 6 site details |
| Construction & progress | 4 progress details · 7 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 21 documents · 11 source links |
Registration
Registration
| Promoter | ANANDSRI CONSTRUCTION PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP55140-002/129/R-1683/2024 | |
| Registered on | 2024-04-29 | |
| Valid to | 2026-03-09 | |
| Project type | Residential | |
| Status (as filed) | RERA Registered Projects | |
| Proposed completion | 2026-03-09 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Environment Clearance | 2026-03-31 | |
| Fire NOC | 2026-03-31 | |
| Airport NOC | 2026-03-31 | |
| Water Supply Permission | 2026-03-31 | |
| Other approval | 2027-10-19 | DANAPUR NAGAR PARISHAD |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹15,00,00,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 938.5 | |
|---|---|---|
| Built-up (m²) | 1,870.1 | |
| FAR | 1.99 | |
| Towers | 1 | |
| Booked | 8 | |
| Booked as of | 2025-12-31 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 95% | |
|---|---|---|
| As of | 2025-12-31 | |
| Start | 2023-03-10 | |
| Proposed completion | 2026-03-09 |
Quarterly progress
| 2025-Q4 | 2026-01-23 | 95% | 8 |
| 2025-Q3 | 2025-11-17 | ||
| 2025-Q2 | 2025-08-07 | ||
| 2025-Q1 | 2025-04-13 | ||
| 2024-Q3 | 2024-10-30 | ||
| 2024-Q2 | 2024-08-22 | ||
| 2023-Q4 | 2025-01-18 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ANANDSRI CONSTRUCTION PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP02132023155140_002
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP02132023155140&ld=pan&pj=RERAP02132023155140_002&f=2025-2026&q=3
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP02132023155140_002
- https://rera.bihar.gov.in/RCpage.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- CA certificate · Sign in to download
- Upload Sanctioned Layout Plan
- Sanction Certificate for Bank Construction Finance · Sign in to download
- Sanctioned Building Plan
- Audited Profit and Loss account · Sign in to download
- Audited Profit and Loss account · Sign in to download
- Audited Profit and Loss account · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-23
- Q2 (Jul - Sep) / 2025-2026 · 2025-11-17
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-07
- Q4-Jan to Mar / 2024-2025 · 2025-04-13
- Q2-Jun to Sep / 2024-2025 · 2024-10-30
- Q1-Apr to Jun / 2024-2025 · 2024-08-22
- Q3-Oct to Dec / 2023-2024 · 2025-01-18
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- 2025-Q3 · 2025-11-17
- 2025-Q2 · 2025-08-07
- 2025-Q1 · 2025-04-13
- 2024-Q3 · 2024-10-30
- 2024-Q2 · 2024-08-22
- 2023-Q4 · 2025-01-18