Overview
ANANDA VIHARA
MUNIPALLE KRISHNA MOHAN · Chittoor
Completion2032-01-22Proposed
Registered on2026-03-30
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 1 site detail · 122 unit types |
| Construction & progress | 2 progress details · 2 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 21 documents · 9 source links |
Registration
Registration
| Promoter | MUNIPALLE KRISHNA MOHAN | |
|---|---|---|
| District | Chittoor | |
| Regulator | AP RERA | |
| Registration number | P10120276492 | |
| Registered on | 2026-03-30 | |
| Project type | Layouts for Plots & Buildings | |
| Status (as filed) | New Project | |
| Proposed completion | 2032-01-22 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Authority |
|---|---|---|---|
| Building / layout plan | 1166/0122/B/RUMNDL/THLM/2025 | 2026-01-22 | Vice Chairman,UDA |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,80,00,000 | |
|---|---|---|
| Construction | ₹21,80,00,000 | |
| Total | ₹24,60,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Towers | 16 |
|---|
Unit types
| 2BHK | 36.64 | 1 | ANANDA VIHARA -1 | FIRST FLOOR |
| 2BHK | 38.41 | 1 | ANANDA VIHARA -1 | FIRST FLOOR |
| 2BHK | 36.64 | 1 | ANANDA VIHARA -1 | GROUND FLOOR |
| 2BHK | 38.41 | 1 | ANANDA VIHARA -1 | GROUND FLOOR |
| 2BHK | 36.64 | 1 | ANANDA VIHARA -1 | SECOND FLOOR |
| 2BHK | 38.41 | 1 | ANANDA VIHARA -1 | SECOND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -10 | FIRST FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -10 | FIRST FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -10 | GROUND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -10 | GROUND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -10 | SECOND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -10 | SECOND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -11 | FIRST FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -11 | FIRST FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -11 | GROUND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -11 | GROUND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -11 | SECOND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -11 | SECOND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -12 | FIRST FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -12 | FIRST FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -12 | GROUND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -12 | GROUND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -12 | SECOND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -12 | SECOND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -13 | FIRST FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -13 | FIRST FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -13 | GROUND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -13 | GROUND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -13 | SECOND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -13 | SECOND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -14 | FIRST FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -14 | FIRST FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -14 | GROUND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -14 | GROUND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -14 | SECOND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -14 | SECOND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -15 | FIRST FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -15 | FIRST FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -15 | GROUND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -15 | GROUND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -15 | SECOND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -15 | SECOND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -16 | FIRST FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -16 | FIRST FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -16 | GROUND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -16 | GROUND FLOOR |
| 2BHK | 36.63 | 1 | ANANDA VIHARA -16 | SECOND FLOOR |
| 2BHK | 38.42 | 1 | ANANDA VIHARA -16 | SECOND FLOOR |
| 2BHK | 36.64 | 1 | ANANDA VIHARA -2 | FIRST FLOOR |
| 2BHK | 38.41 | 1 | ANANDA VIHARA -2 | FIRST FLOOR |
| 2BHK | 36.64 | 1 | ANANDA VIHARA -2 | GROUND FLOOR |
| 2BHK | 38.41 | 1 | ANANDA VIHARA -2 | GROUND FLOOR |
| 2BHK | 36.64 | 1 | ANANDA VIHARA -2 | SECOND FLOOR |
| 2BHK | 38.41 | 1 | ANANDA VIHARA -2 | SECOND FLOOR |
| 2BHK | 35.61 | 1 | ANANDA VIHARA -3 | FIRST FLOOR |
| 2BHK | 37.39 | 1 | ANANDA VIHARA -3 | FIRST FLOOR |
| 2BHK | 35.61 | 1 | ANANDA VIHARA -3 | GROUND FLOOR |
| 2BHK | 37.39 | 1 | ANANDA VIHARA -3 | GROUND FLOOR |
| 2BHK | 35.61 | 1 | ANANDA VIHARA -3 | SECOND FLOOR |
| 2BHK | 37.39 | 1 | ANANDA VIHARA -3 | SECOND FLOOR |
| 2BHK | 40.37 | 1 | ANANDA VIHARA -4 | FIRST FLOOR |
| 2BHK | 41 | 1 | ANANDA VIHARA -4 | FIRST FLOOR |
| 2BHK | 40.37 | 1 | ANANDA VIHARA -4 | GROUND FLOOR |
| 2BHK | 41 | 1 | ANANDA VIHARA -4 | GROUND FLOOR |
| 2BHK | 40.37 | 1 | ANANDA VIHARA -4 | SECOND FLOOR |
| 2BHK | 41 | 1 | ANANDA VIHARA -4 | SECOND FLOOR |
| 2BHK | 40.37 | 1 | ANANDA VIHARA -5 | FIRST FLOOR |
| 2BHK | 41 | 1 | ANANDA VIHARA -5 | FIRST FLOOR |
| 2BHK | 40.37 | 1 | ANANDA VIHARA -5 | GROUND FLOOR |
| 2BHK | 41 | 1 | ANANDA VIHARA -5 | GROUND FLOOR |
| 2BHK | 40.37 | 1 | ANANDA VIHARA -5 | SECOND FLOOR |
| 2BHK | 41 | 1 | ANANDA VIHARA -5 | SECOND FLOOR |
| 2BHK | 36.09 | 1 | ANANDA VIHARA -6 | FIRST FLOOR |
| 2BHK | 36.08 | 1 | ANANDA VIHARA -6 | FIRST FLOOR |
| 2BHK | 36.09 | 1 | ANANDA VIHARA -6 | GROUND FLOOR |
| 2BHK | 36.08 | 1 | ANANDA VIHARA -6 | GROUND FLOOR |
| 2BHK | 36.09 | 1 | ANANDA VIHARA -6 | SECOND FLOOR |
| 2BHK | 36.08 | 1 | ANANDA VIHARA -6 | SECOND FLOOR |
| 2BHK | 36.04 | 1 | ANANDA VIHARA -7 | FIRST FLOOR |
| 2BHK | 36.01 | 1 | ANANDA VIHARA -7 | FIRST FLOOR |
| 2BHK | 36.04 | 1 | ANANDA VIHARA -7 | GROUND FLOOR |
| 2BHK | 36.01 | 1 | ANANDA VIHARA -7 | GROUND FLOOR |
| 2BHK | 36.04 | 1 | ANANDA VIHARA -7 | SECOND FLOOR |
| 2BHK | 36.01 | 1 | ANANDA VIHARA -7 | SECOND FLOOR |
| 2BHK | 36.04 | 1 | ANANDA VIHARA -8 | FIRST FLOOR |
| 2BHK | 36.01 | 1 | ANANDA VIHARA -8 | FIRST FLOOR |
| 2BHK | 36.04 | 1 | ANANDA VIHARA -8 | GROUND FLOOR |
| 2BHK | 36.01 | 1 | ANANDA VIHARA -8 | GROUND FLOOR |
| 2BHK | 36.04 | 1 | ANANDA VIHARA -8 | SECOND FLOOR |
| 2BHK | 36.01 | 1 | ANANDA VIHARA -8 | SECOND FLOOR |
| 2BHK | 35.85 | 1 | ANANDA VIHARA -9 | FIRST FLOOR |
| 2BHK | 35.84 | 1 | ANANDA VIHARA -9 | FIRST FLOOR |
| 2BHK | 35.9 | 1 | ANANDA VIHARA -9 | FIRST FLOOR |
| 2BHK | 35.9 | 1 | ANANDA VIHARA -9 | FIRST FLOOR |
| 2BHK | 35.85 | 1 | ANANDA VIHARA -9 | GROUND FLOOR |
| 2BHK | 35.84 | 1 | ANANDA VIHARA -9 | GROUND FLOOR |
| 2BHK | 35.9 | 1 | ANANDA VIHARA -9 | GROUND FLOOR |
| 2BHK | 35.9 | 1 | ANANDA VIHARA -9 | GROUND FLOOR |
| 2BHK | 35.85 | 1 | ANANDA VIHARA -9 | SECOND FLOOR |
| 2BHK | 35.84 | 1 | ANANDA VIHARA -9 | SECOND FLOOR |
| 2BHK | 35.9 | 1 | ANANDA VIHARA -9 | SECOND FLOOR |
| 2BHK | 35.9 | 1 | ANANDA VIHARA -9 | SECOND FLOOR |
| 2BHK | 35.85 | 1 | ANANDA VIHARA -9 | THIRD FLLOR |
| 2BHK | 35.84 | 1 | ANANDA VIHARA -9 | THIRD FLLOR |
| 2BHK | 35.9 | 1 | ANANDA VIHARA -9 | THIRD FLLOR |
| 2BHK | 35.9 | 1 | ANANDA VIHARA -9 | THIRD FLLOR |
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 | |||
| Plot | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2026-01-22 | |
|---|---|---|
| Proposed completion | 2032-01-22 |
Quarterly progress
| Quarter | Filed on |
|---|---|
| 2026-Q2 | 2026-07-21 |
| 2026-Q3 | 2026-10-20 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MUNIPALLE KRISHNA MOHAN | |
|---|---|---|
| Type | Individual | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.ap.gov.in/RERA/Views/GeoMap.aspx
- https://rera.ap.gov.in/RERA/Views/Project.aspx??enc=mUX5JvffTObOCE+6xFBEFUCuid8RacXkacmDmJ9CiV7/tia4hLgH0NjfYHYiT3vf4cisxdoBkQDHJdQZeDuGzb0oAARt8IIELvY9Q4GXgdM/Pbm3lWYpXB/FEW1HX2h8
- https://rera.ap.gov.in/RERA/Views/Reports/ApprovedProjects.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/DwellingUnitsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/ProjExpectedDateofCompletion.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QprProjectsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QuarterlyReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/SoldInformation.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/TotalBuildupArea.aspx
- Litigation details
- Modified plan
- Architect certificate
- 1.Income Tax Return Acknowledgement of Preceding Year 1
- 2. Income Tax Return Acknowledgement of Preceding Year 2
- 3.Income Tax Return Acknowledgement of Preceding Year 3
- 4.Balance Sheet
- 10. Detailed site plan showing the measurements as on ground including diagonals, Latitude and Longitude at end points of the project site
- 15. Details of the cases pending before the Authorities or in Courts of Law and their current status along with the copies of the orders issued
- 16. Copy of the plan and proceedings issued by the competent Authority for approval of plans
- 17. Approved plan / list of amenities proposed in the site
- 18. NOC's issued by Authority
- 19. Detailed technical specifications of the construction if the buildings and facilities proposed in the project including brand specifications details of fixtures and fittings
- 20. Full address of the proposed development project along with the land mark nearby and a location plan/ Topo plan drawn to a scale
- 21. Licenses/Enrolment form of Civil Contractors, or turnkey contractor, or EPC Contractors.
- 25.Licenses/Enrolment form of Chartered Accountant or firm or company
- 26.Detailed estimate of the expenditure for construction of the building
- 27. Statement of source of funds for construction of project
- 29.Proforma of the Allotment Letter proposed to be signed with the Allottee
- 32.Structural Stability Certificate duly issued by Certified Structural Consultant/Engineer along with the details of parameters followed for verification of structural stability *
- APRERA CERTIFICATE