Overview
Ananta Homes
Ananta Empires Private Limited · Jalandhar
Units163
Completion2026-03-31Proposed
Valid to2026-03-31
Approvals17
Sections
| Property title & search report | |
|---|---|
| Approvals | 17 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 32 unit types |
| Construction & progress | 2 progress details · 14 quarters |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 42 documents · 34 source links |
Registration
Registration
| Promoter | Ananta Empires Private Limited | |
|---|---|---|
| District | Jalandhar | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-JAL33-PR0853 | |
| Valid to | 2026-03-31 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2026-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2025-03-31 |
| CLU Certificate | |
| CLU Certificate | |
| Electric Substation NOC | 2023-03-29 |
| Electric Substation NOC | 2024-06-21 |
| Electric Substation NOC | 2025-10-10 |
| Environment Clearance certificate/ NOC | 2025-03-31 |
| License to develop colony or society from Competent Authority | |
| License to develop colony or society from Competent Authority | |
| License to develop colony or society from Competent Authority | |
| License to develop colony or society from Competent Authority | |
| NOC from NHAI/ PWD | 2022-09-07 |
| Other Document (Drainage NOC) | 2024-06-19 |
| Other Document (Forest NOC) | 2023-03-29 |
| Other Document (Forest NOC) | 2023-03-22 |
| Other Document (Forest NOC) | 2024-06-20 |
| Pollution Clearance from Punjab Pollution Control Board | 2023-03-20 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹8,31,66,645 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 35,223.9698 | |
|---|---|---|
| Units | 163 |
Unit types
| Shop no 1 -8 | 74.03 | 8 | COMMERCIAL |
| Shop No. 9-10 | 62.71 | 2 | COMMERCIAL |
| Shop No. 11-12 | 56.91 | 2 | COMMERCIAL |
| Plot no 1-13 | 122.63 | 13 | RESIDENTIAL |
| plot no 14-18 | 119.86 | 5 | RESIDENTIAL |
| Plot No 19-26 | 125.419 | 8 | RESIDENTIAL |
| plot no 27-38 | 122.63 | 12 | RESIDENTIAL |
| plot no 39-46 | 125.42 | 8 | RESIDENTIAL |
| Plot no. 47 | 100.34 | 1 | RESIDENTIAL |
| Plot no 48 | 117.9 | 1 | RESIDENTIAL |
| Plot no 49 | 107.726 | 1 | RESIDENTIAL |
| Plot no 50 | 101.45 | 1 | RESIDENTIAL |
| Plot no 51 | 103.194 | 1 | RESIDENTIAL |
| Plot no 52 | 105.276 | 1 | RESIDENTIAL |
| Plot no 53 | 107.68 | 1 | RESIDENTIAL |
| Plot no 54 | 109.95 | 1 | RESIDENTIAL |
| Plot no 55 | 112.42 | 1 | RESIDENTIAL |
| Plot no 56 | 114.92 | 1 | RESIDENTIAL |
| Plot no. 57 | 117.07 | 1 | RESIDENTIAL |
| Plot no 58 | 119.591 | 1 | RESIDENTIAL |
| Plot no 59 | 121.99 | 1 | RESIDENTIAL |
| Plot no 60 | 123.87 | 1 | RESIDENTIAL |
| Plot no 61-62 | 124.78 | 2 | RESIDENTIAL |
| Plot no 68-78 | 120.77 | 11 | RESIDENTIAL |
| Plot no 79-100 | 125.42 | 22 | RESIDENTIAL |
| Plot No. 101-107 | 110.37 | 7 | RESIDENTIAL |
| Plot No. 108 | 114.86 | 1 | RESIDENTIAL |
| Plot No. 109-111 | 124.98 | 3 | RESIDENTIAL |
| Plot No. 112-122 | 120.66 | 11 | RESIDENTIAL |
| Plot No. 123-142 | 125.42 | 20 | RESIDENTIAL |
| Plot No. 143-151 | 120.32 | 9 | RESIDENTIAL |
| Plot no 63-67 | 114.96 | 5 | RESIDENTIAL |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-12-16 | |
|---|---|---|
| Proposed completion | 2026-03-31 |
Quarterly progress
| 2023-Q2 | 2023-07-13 |
| 2023-Q3 | 2023-10-14 |
| 2023-Q4 | 2024-01-23 |
| 2024-Q1 | 2024-05-02 |
| 2024-Q2 | 2024-07-19 |
| 2024-Q3 | 2024-12-12 |
| 2024-Q4 | 2025-09-18 |
| 2025-Q1 | 2025-09-18 |
| 2025-Q2 | 2026-01-19 |
| 2025-Q3 | 2026-01-19 |
| 2025-Q4 | 2026-01-19 |
| 2026-Q1 | 2026-05-30 |
| 2026-Q2 | 2026-07-23 |
| 2026-Q3 | 2026-10-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Ananta Empires Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank Limited | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | RAJINDERA ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11667&inPromoter_ID=2553&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-03-31
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2023-03-29
- Electric Substation NOC · 2024-06-21
- Electric Substation NOC · 2025-10-10
- Environment Clearance certificate/ NOC · 2025-03-31
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2022-09-07
- Other Document (covering revised letter) · 2023-02-24 · Sign in to download
- Other Document (Drainage and water ) · 2022-09-06 · Sign in to download
- Other Document (Drainage NOC) · 2024-06-19
- Other Document (Forest NOC) · 2023-03-29
- Other Document (Forest NOC) · 2023-03-22
- Other Document (Forest NOC) · 2024-06-20
- Other Document (PPCB) · 2025-04-21 · Sign in to download
- Pollution Clearance from Punjab Pollution Control Board · 2023-03-20
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-03-31
- CLU Certificate
- CLU Certificate
- Electric Substation NOC · 2023-03-29
- Electric Substation NOC · 2024-06-21
- Electric Substation NOC · 2025-10-10
- Environment Clearance certificate/ NOC · 2025-03-31
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from NHAI/ PWD · 2022-09-07
- Other Document (Drainage NOC) · 2024-06-19
- Other Document (Forest NOC) · 2023-03-29
- Other Document (Forest NOC) · 2023-03-22
- Other Document (Forest NOC) · 2024-06-20
- Pollution Clearance from Punjab Pollution Control Board · 2023-03-20
- 2023-Q2 · 2023-07-13
- 2023-Q3 · 2023-10-14
- 2023-Q4 · 2024-01-23
- 2024-Q1 · 2024-05-02
- 2024-Q2 · 2024-07-19
- 2024-Q3 · 2024-12-12
- 2024-Q4 · 2025-09-18
- 2025-Q1 · 2025-09-18
- 2025-Q2 · 2026-01-19
- 2025-Q3 · 2026-01-19
- 2025-Q4 · 2026-01-19
- 2026-Q1 · 2026-05-30
- 2026-Q2 · 2026-07-23
- 2026-Q3 · 2026-10-14