Overview
Ananta Street
Harkinder Singh Grewal · Ludhiana
Completion2031-03-16Proposed
Valid to2031-03-16
Approvals21
Sections
| Property title & search report | |
|---|---|
| Approvals | 21 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 3 site details |
| Construction & progress | 2 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 63 documents · 25 source links |
Registration
Registration
| Promoter | Harkinder Singh Grewal | |
|---|---|---|
| District | Ludhiana | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-LDH45-PC0445 | |
| Valid to | 2031-03-16 | |
| Project type | (1) Commercial (Building/Tower Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2031-03-16 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | 2026-06-01 |
| CLU Certificate | |
| CLU Certificate | |
| Environment Clearance certificate/ NOC | 2026-05-05 |
| License to develop colony or society from Competent Authority | |
| Other Document (Affidavit for NOCs) | 2026-03-20 |
| Other Document (Apply for reissuance drainage NOC) | 2026-05-20 |
| Other Document (Apply for reissuance Forest NOC) | 2026-05-20 |
| Other Document (Clarification Regarding Road Access NOC) | 2026-07-13 |
| Other Document (Copy of Re issuance of AAI NOC) | 2026-07-13 |
| Other Document (Drainage NOC) | 2025-07-24 |
| Other Document (Forest NOC) | 2025-07-29 |
| Other Document (Khal Noc) | 2025-10-01 |
| Other Document (PSTCL NOC) | 2025-08-19 |
| Other Document (PWRDA NOC) | 2026-07-06 |
| Other Document (Reissuance of drainage NOC) | 2026-06-05 |
| Other Document (Road access NOC Applied for) | 2026-07-15 |
| Other Document (Road Access NOC) | 2025-07-28 |
| Other Document (sewerage NOC) | 2026-05-14 |
| Other Document (Solid waste NOC Apply For) | 2026-05-11 |
| Pollution Clearance from Punjab Pollution Control Board | 2026-05-27 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹62,20,84,689 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 12,189.28 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 5 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2026-03-16 | |
|---|---|---|
| Proposed completion | 2031-03-16 |
Quarterly progress
| Quarter | Filed on |
|---|---|
| 2026-Q3 | 2026-10-27 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Harkinder Singh Grewal | |
|---|---|---|
| Type | Individual | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12739&inPromoter_ID=3669&inPromoterType=1
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- CA Certificate (Form 3)
- CA Certificate (Form 3)
- CA Certificate (Form 3)
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2026-06-01
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Environment Clearance certificate/ NOC · 2026-05-05
- License to develop colony or society from Competent Authority
- Other Document (Apply for reissuance drainage NOC) · 2026-05-20
- Other Document (Apply for reissuance Forest NOC) · 2026-05-20
- Other Document (Clarification Regarding Road Access NOC) · 2026-07-13
- Other Document (Copy of Re issuance of AAI NOC) · 2026-07-13
- Other Document (Drainage NOC) · 2025-07-24
- Other Document (Forest NOC) · 2025-07-29
- Other Document (Khal Noc) · 2025-10-01
- Other Document (PPCB application form along with payment Receipt) · 2026-07-10 · Sign in to download
- Other Document (pspcl application form along with fee receipt) · 2026-06-27 · Sign in to download
- Other Document (PSTCL NOC) · 2025-08-19
- Other Document (PWRDA NOC) · 2026-07-06
- Other Document (Reissuance of drainage NOC) · 2026-06-05
- Other Document (Road access NOC Applied for) · 2026-07-15
- Other Document (Road Access NOC) · 2025-07-28
- Other Document (sewerage NOC) · 2026-05-14
- Other Document (Solid waste NOC Apply For) · 2026-05-11
- Pollution Clearance from Punjab Pollution Control Board · 2026-05-27
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2026-06-01
- CLU Certificate
- CLU Certificate
- Environment Clearance certificate/ NOC · 2026-05-05
- License to develop colony or society from Competent Authority
- Other Document (Affidavit for NOCs) · 2026-03-20
- Other Document (Apply for reissuance drainage NOC) · 2026-05-20
- Other Document (Apply for reissuance Forest NOC) · 2026-05-20
- Other Document (Clarification Regarding Road Access NOC) · 2026-07-13
- Other Document (Copy of Re issuance of AAI NOC) · 2026-07-13
- Other Document (Drainage NOC) · 2025-07-24
- Other Document (Forest NOC) · 2025-07-29
- Other Document (Khal Noc) · 2025-10-01
- Other Document (PSTCL NOC) · 2025-08-19
- Other Document (PWRDA NOC) · 2026-07-06
- Other Document (Reissuance of drainage NOC) · 2026-06-05
- Other Document (Road access NOC Applied for) · 2026-07-15
- Other Document (Road Access NOC) · 2025-07-28
- Other Document (sewerage NOC) · 2026-05-14
- Other Document (Solid waste NOC Apply For) · 2026-05-11
- Pollution Clearance from Punjab Pollution Control Board · 2026-05-27
- 2026-Q3 · 2026-10-27