Overview
ANANTAVILASA
MNB BUILD FAB PRIVATE LIMITED · Gurugram
Units74
Completion2030-12-31Proposed
Registered on2025-01-13
Valid to2030-12-31
Approvals18
Sections
| Property title & search report | |
|---|---|
| Approvals | 18 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 7 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 54 documents · 3 source links |
Registration
Registration
| Promoter | MNB BUILD FAB PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/899/631/2025/02 DATED 13.01.2025 | |
| Registered on | 2025-01-13 | |
| Valid to | 2030-12-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2030-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | Town & Country Planning Department | |
| Layout Plan | 2024-10-10 | |
| Building Plan | 2024-10-10 | |
| I. ASSURANCE FOR SEWERAGE CONNECTION FOR DISCHARGE OF 50 KLD SURPLUS DOMESTIC TREATED EFFLUENT. | 2024-07-22 | |
| II. ASSURANCE FOR STORM WATER CONNECTION OF PROPOSED GROUP HOUSING PROJECT. | 2024-07-22 | |
| III. NO OBJECTION CERTIFICATE FOR HIGHT CLEARANCE | 2024-08-20 | |
| IV. NO OBJECTION CERTIFICATE FOR FIRE | 2024-02-24 | |
| V. ENVIRONMENT CLEARANCE | 2024-10-29 | |
| VI. MINING PERMISSION | 2024-11-05 | |
| VII. TREE CUTTING PERMISSION | 2023-12-19 | |
| VIII. GREEN RATING FOR INTEGRATED HABITAT ASSESSMENT | 2024-08-05 | |
| IX. BUILDING PLAN | 2024-10-10 | |
| X. ASSURANCE FOR WATER SUPPLY 5 KLD FOR DOMESTIC PURPOSE. | 2024-07-23 | |
| XI. ASSURANCE FOR SUPPLY OF 30 KLD STP TREATED WATER FOR CONSTRUCTION OF GROUP HOUSING PROJECT. | 2024-07-22 | |
| XII. SITE PLAN | 2024-10-10 | |
| XIII. POSSESSION CERTIFICATE | 2023-11-08 | |
| XIV. NON ENCUMBRANCE CERTIFICATE | 2024-09-10 | |
| XV. LETTER OF INTENT | 2023-11-08 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹67,99,17,400 | |
|---|---|---|
| Construction | ₹1,27,93,00,000 | |
| Total | ₹2,63,44,17,300 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,438.75 | |
|---|---|---|
| FAR | 4.12 | |
| Units | 74 |
Unit types
| Apartment/Shops/Other Buildings | 162.56 | 14 |
| Apartment/Shops/Other Buildings | 163.57 | 15 |
| Apartment/Shops/Other Buildings | 162.56 | 15 |
| Apartment/Shops/Other Buildings | 163.06 | 14 |
| Apartment/Shops/Other Buildings | 158.05 | 14 |
| Apartment/Shops/Other Buildings | 162.56 | 1 |
| Apartment/Shops/Other Buildings | 163.06 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-01-01 | |
|---|---|---|
| Proposed completion | 2030-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MNB BUILD FAB PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI BANK | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/3057
- https://nominatim.openstreetmap.org/search?q=sector+56%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2025-01-13
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2024-09-01
- PERMISSION FOR FELLING OF TREES. · 2024-09-01 · Sign in to download
- AIRPORTS AUTHORITY OF INDIA - HEIGHT CLEARANCE. · 2024-09-01
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2024-10-22
- DEMARCATION PLAN · 2024-10-21
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2024-10-22
- ZONING PLAN · 2024-10-21
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2024-10-21
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2024-10-22
- COI, DISSOLUTION AND CONVERSION CERTIFICATE. · 2024-10-22 · Sign in to download
- ENVIRMENT CLEARENCE · 2024-11-01 · Sign in to download
- LETTER OF INTENT BY HSVP · 2025-01-15 · Sign in to download
- ALLOTTEE- AGREEMENT FOR SALE · 2025-01-15 · Sign in to download
- BASEMENT 3 -PLAN · 2025-01-15
- ALLOTEE -PAYMENT RECEIPT · 2025-01-15 · Sign in to download
- NET WORTH CERTIFICATE · 2025-01-15 · Sign in to download
- PERT CHART · 2025-01-15 · Sign in to download
- 4TH FLOOR TO 14TH FLOOR · 2025-01-15 · Sign in to download
- BASEMENT 1 -PLAN · 2025-01-15
- ALLOTTEE- ALLOTMENT LETTER · 2025-01-15 · Sign in to download
- POSSESSION CERTIFICATE BY HSVP · 2025-01-15 · Sign in to download
- 2ND FLOOR · 2025-01-15 · Sign in to download
- ELEVATION PLAN 'C' AND 'D' · 2025-01-15
- AFFIDAVIT 4(2)(L)(D) · 2025-01-15 · Sign in to download
- HSVP PERMISSION FOR THIRD PARTY RIGHTS CREATION · 2025-01-15 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2025-01-15 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2025-01-15 · Sign in to download
- ALLOTTEE- CONVEYANCE DEED · 2025-01-15 · Sign in to download
- NEC - TEHSILDAR · 2025-01-15 · Sign in to download
- 1ST FLOOR · 2025-01-15 · Sign in to download
- PROJECT COST CERTIFICATE · 2025-01-15 · Sign in to download
- CLEARIFICATION · 2025-01-15 · Sign in to download
- BANK UNDERTAKING · 2025-01-15 · Sign in to download
- BR FOR BANK AUTHORISED · 2025-01-15 · Sign in to download
- AFFIDAVIT CUM DECLARATION FOR PAID EDC IDC · 2025-01-15 · Sign in to download
- ELEVATION PLAN 'A' AND 'B' · 2025-01-15
- ALLOTMENT LETTER BY HSVP · 2025-01-15 · Sign in to download
- CERTIFICATE OF INCORPORATION - MNB BUILD FAB · 2025-01-15 · Sign in to download
- GRIHA GREEN RATING 4 STAR · 2025-01-15 · Sign in to download
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2025-01-15 · Sign in to download
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2025-01-15 · Sign in to download
- GROUND FLOOR PLAN · 2025-01-15
- GH-26A CONVEYANCE DEED · 2025-01-15 · Sign in to download
- STATEMENT OF QUARTERLY ESTIMATED EXPEND · 2025-01-15 · Sign in to download
- STATEMENT OF QUARTERLY SOURCES OF FUND · 2025-01-15 · Sign in to download
- TITLE SEARCH REPORT - LATEST · 2025-01-15 · Sign in to download
- VARIOUS APPROVALS FROM HSVP · 2025-01-15
- 3RD FLOOR · 2025-01-15 · Sign in to download
- 15TH FLOOR · 2025-01-15 · Sign in to download
- BASEMENT 2 -PLAN · 2025-01-15
- SECTION PLAN · 2025-01-15
- STAIR CASE AREA · 2025-01-15 · Sign in to download
- ALLOTTEE- APPLICATION FORM · 2025-01-15 · Sign in to download