Overview
ANIKA CLASSIC
ELLY REALCON PRIVATE LIMITED · Ghaziabad
Units189
Completion2024-06-30Revised · Proposed 2023-12-31
Registered on2019-06-06
Valid to2024-06-30
Approvals1
Complaints5As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 5 project complaints · 5 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 9 unit types |
| Construction & progress | 3 progress details · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 2 professional firms |
| The evidence | |
| Sources | 10 documents · 7 source links |
Registration
Registration
| Promoter | ELLY REALCON PRIVATE LIMITED | |
|---|---|---|
| District | Ghaziabad | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ115895 | |
| Registered on | 2019-06-06 | |
| Valid to | 2024-06-30 | |
| Project type | Commercial | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2023-12-31 | |
| Revised completion | 2024-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | 745/HOTEL/GMP/ZONE-1/16-17 | 2019-04-03 | 2024-04-02 | Ghaziabad Development Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 5 | |
|---|---|---|
| Promoter | 5 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹36,29,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,339 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 6 | |
| Units | 189 |
Unit types
| SHOP | 375.65 | 40 | A | BSMNT |
| SHOP | 375.65 | 32 | A | GF |
| SHOP | 170.76 | 16 | A | 1 |
| STUDIO | 316.6 | 12 | A | 1 |
| STUDIO | 701.6 | 21 | A | 2 |
| STUDIO | 434.6 | 13 | A | 3 |
| STUDIO | 614.6 | 21 | A | 4 |
| STUDIO | 614.6 | 21 | A | 5 |
| STUDIO | 224.6 | 13 | A | 6 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-04-15 | |
|---|---|---|
| Proposed completion | 2023-12-31 | |
| Revised completion | 2024-06-30 |
Extensions
| Valid to | Reason |
|---|---|
| 2024-06-30 | Six months extension in view of force majeure caused by covid-19 pandemic |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ELLY REALCON PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | IDBI BANK | |
| Other projects in this city pack | 0 |
Professional firms
| Role | Firm |
|---|---|
| Architect | DHAMA ASSOCIATES |
| Contractor | SAWARIA SETH INFRATECH PRIVATE LIMITED |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=XUbUzFsLuoc=&hfFlag=q5Tk0QUeJB8oatkp/Oqbxw==&NPJ6RAme=ZnVaf0RmDNpAA4VSAdUaaA==&PaURJEMAN4=ZL9MNERkNdZuqozvo6nWfg==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=GHAZIABAD
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=XUbUzFsLuoc=
- Details of Encumbrances · 2019-05-16 · Sign in to download
- Commencement Certificate · 2019-05-16
- Other Plan(If Any) · 2019-05-16
- Proforma of Application Form · 2019-04-30 · Sign in to download
- Proforma of Allotment Letter · 2019-04-30 · Sign in to download
- Waste Disposal Plan · 2019-06-01
- Water Supply Plan · 2019-06-01
- Electricity Supply Plan · 2019-06-01
- Development Work Plan · 2019-06-01
- Affidavit (Form-B) · 2019-05-23 · Sign in to download