Overview
ANTA - KINGS PLACE
ANTA BUILDERS & DEVELOPERS PVT LTD · Ernakulam
Units67
Booked8 of 67
Construction progress42%
Completion2026-05-30Revised · Proposed 2023-05-30
Registered on2021-09-02
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 1 registration detail |
| Technical report | |
| Site & area | 5 site details · 12 unit types |
| Construction & progress | 4 progress details · 9 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 3 professional firms |
| The evidence | |
| Sources | 2 documents · 7 source links |
Registration
Registration
| Promoter | ANTA BUILDERS & DEVELOPERS PVT LTD | |
|---|---|---|
| District | Ernakulam | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/043/2020 | |
| Registered on | 2021-09-02 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Registration Expired Project (official expired filter) | |
| Proposed completion | 2023-05-30 | |
| Revised completion | 2026-05-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | PW2-BA(83641)/2018 | 2018-05-02 | 2021-05-01 | Tripunithura Municipality |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Registration status
| Status | Registration Expired Project (official expired filter) |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,032 | |
|---|---|---|
| Built-up (m²) | 8,809.88 | |
| Towers | 0 | |
| Units | 67 | |
| Booked | 8 |
Unit types
| 2BHK | 1 | 0 | KINGS PLACE |
| 2BHK | 1 | 0 | KINGS PLACE |
| 2BHK | 10 | 0 | KINGS PLACE |
| 2BHK | 10 | 2 | KINGS PLACE |
| 3BHK | 1 | 0 | KINGS PLACE |
| 3BHK | 1 | 0 | KINGS PLACE |
| 3BHK | 9 | 0 | KINGS PLACE |
| 3BHK | 10 | 2 | KINGS PLACE |
| 3BHK | 10 | 2 | KINGS PLACE |
| 3BHK | 10 | 2 | KINGS PLACE |
| 4BHK | 2 | 0 | KINGS PLACE |
| 4BHK | 2 | 0 | KINGS PLACE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 42% | |
|---|---|---|
| Start | 1900-01-01 | |
| Proposed completion | 2023-05-30 | |
| Revised completion | 2026-05-30 |
Quarterly progress
| Quarter |
|---|
| 2024-2025 Q1 |
| 2024-2025 Q2 |
| 2024-2025 Q3 |
| 2023-2024 Q4 |
| 2021-2022 Q1 |
| 2021-2022 Q2 |
| 2023-2024 Q2 |
| 2023-2024 Q3 |
| 2022-2023 Q2 |
Extensions
| Valid to |
|---|
| 2026-05-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ANTA BUILDERS & DEVELOPERS PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | State Bank of India | |
| Other projects in this city pack | 9 |
Professional firms
| Role | Firm |
|---|---|
| Architect | Ajith Sunny Architects |
| Engineer | Vellapally Engineers and Consultancy |
| CA | Paulson and Company |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/explore-projects?status=expired&page=7
- https://rera.kerala.gov.in/projects/131
- https://rera.kerala.gov.in/projects?district=595&page=2
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=T7wu4hdAyOlKcOWag30TJI06UD8%2FjPuXlKTO1X1vn%2BBUc95LzZgc8S%2BBTDAGZfW1EO9TskEFbOhztnh3sgxN5miSxhztSX7Y3XWp77X3DZm6gM8uu80qpKZDrd1eFFdZpP8sM1d%2F8FEH2tQclRBD7StjyF%2BTAUgky9qwRa%2F3ZJo%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=131&Division=1&UserID=30187&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Signed project certificate · 2021-09-02
- Extension certificate · 2022-06-20 · Sign in to download
- Extension order · Sign in to download