Overview
ANTAS
RAJA DEVELOPERS INDIA PRIVATE LIMITED · Lucknow
Units177
Completion2021-06-30Revised · Proposed 2020-12-31
Registered on2017-10-28
Valid to2021-06-30
Approvals1
Complaints0As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 0 project complaints · 0 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 8 unit types |
| Construction & progress | 3 progress details · 2 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 13 documents · 9 source links |
Registration
Registration
| Promoter | RAJA DEVELOPERS INDIA PRIVATE LIMITED | |
|---|---|---|
| District | Lucknow | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ11910 | |
| Registered on | 2017-10-28 | |
| Valid to | 2021-06-30 | |
| Project type | Commercial | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2020-12-31 | |
| Revised completion | 2021-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | 37587 | 2015-01-12 | 2020-01-11 | Lucknow Development Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| Promoter | 0 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹50,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 4,680 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 6 | |
| Units | 177 |
Unit types
| SHOP | 1,643 | 28 | 1 | GF |
| SHOP | 1,622 | 31 | 1 | 1 |
| SHOP | 1,246.29 | 29 | 1 | 2 |
| SHOP | 1,246.29 | 29 | 1 | 3 |
| OTHER | 462.88 | 2 | 1 | 4 |
| SHOP | 784 | 20 | 1 | 5 |
| SHOP | 783.41 | 18 | 1 | 6 |
| SHOP | 784 | 20 | 1 | 4 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2014-05-15 | |
|---|---|---|
| Proposed completion | 2020-12-31 | |
| Revised completion | 2021-06-30 |
Quarterly progress
| Quarter |
|---|
| 2020-Q2 |
| 2021-Q1 |
Extensions
| Valid to | Reason |
|---|---|
| 2021-06-30 | Six months extension in view of force majeure caused by covid-19 pandemic |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RAJA DEVELOPERS INDIA PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | YES BANK | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=fPJH4BlvkN4=&hfFlag=GL34ZTSSjlw=&NPJ6RAme=SrCOMIK2HNk=&PaURJEMAN4=ZL9MNERkNdaEN0bXF/Uj9w==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=LUCKNOW
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=fPJH4BlvkN4=
- Commencement Certificate · 2018-07-06
- Waste Disposal Plan · 2018-07-06
- Water Supply Plan · 2018-07-06
- Electricity Supply Plan · 2018-07-06
- Development Work Plan · 2018-07-06
- CA CERTIFICATE · 2018-07-06 · Sign in to download
- ARCHITECT CERTIFICATE · 2018-07-06 · Sign in to download
- Commencement Certificate · 2017-08-17
- 2020-Q2 CA certificate
- 2020-Q2 Architect certificate
- 2020-Q2 Engineer certificate
- 2021-Q1 CA certificate
- 2021-Q1 Architect certificate
- 2020-Q2
- 2021-Q1