Overview
Antheia D4
Overview
Antheia D4
Overview
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | 1 | – | – | Red flag |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | ||
Title & ownership
We haven't verified this for this project yet.
Sign in first, then it is one click.
Approvals
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 30 Jun 2018 |
| Registration number | P52100000416 | |
|---|---|---|
| Registered | 15 Jul 2017 |
Disputes & cases
Builder: Mahindra Lifespace Developers limited
The filing names no land owners, so there is no name to search.
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None listed. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Search pending. | |||||||
| Other status 2 | ||||||
|---|---|---|---|---|---|---|
| – | 926 | Court of Civil Judge Senior Division Pune | Pimpri Chinchawad (M Corp.) | – | Filed case | –, Medium: The record does not say whether it is decided. |
| – | 24692 | High Court Mumbai | Pimpri Chinchawad (M Corp.) | – | Filed case | –, Medium: The record does not say whether it is decided. |
61 other registrations under this promoter's exact name in Maharashtra; a complaint on one is listed when MahaRERA lists it.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Projects within 4 km, counted | 96 (96 with an approximate location) | |
|---|---|---|
| Flats in them | 15,203 | |
Location & risks
Construction & progress
Developer
Land · ₹11.68 Cr 18.6%Development · ₹51.07 Cr 81.4%
Loan & collateral
Data room
Source: MahaRERA project page and the documents filed there, as read by us. 9 documents filed with MahaRERA, identity papers and photographs, are left out of this list.
| – |
| – |
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
All projects in Pune → (12 of 4,369 shown here)
Everything here is as filed by the promoter with MahaRERA, and can be stale or wrong at source. Verify against certified records before you transact.
| Sold or booked |
|---|
| 11,848 of 15,203 (78%) |
| Unsold | 3,355 |
|---|
Well within 3 km of filed pin; not a site reading.
| Groundwater | monitoring well, 2026-01-10: 3 m below ground |
|---|
| RERA completion date | 30 Jun 2018 | |
|---|---|---|
| Registered | 15 Jul 2017 |
| Estimated cost, at registration | ₹62.75 Cr |
|---|
| Other phases under this promoter name | 46 | |
|---|---|---|
| With a filed extension or completion | 21 (0 completed, 21 extended) | |
| Average schedule slip | 8 months |