Overview
Aparna Mansion
Aparna Architect Pvt. Ltd. · Patna
Units70
Completion2018-06-30Proposed
Registered on2018-05-18
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 2 unit types |
| Construction & progress | 2 progress details · 10 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 26 documents · 14 source links |
Registration
Registration
| Promoter | Aparna Architect Pvt. Ltd. | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00108-1/57/R-25/2018 | |
| Registered on | 2018-05-18 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Completed | |
| Proposed completion | 2018-06-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,69,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,746 | |
|---|---|---|
| Built-up (m²) | 7,144 | |
| FAR | 1.9 | |
| Towers | 3 | |
| Units | 70 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 2 BHK | 16 | Aparna Mansion |
| 3 BHK | 54 | Aparna Mansion |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2015-06-10 | |
|---|---|---|
| Proposed completion | 2018-06-30 |
Quarterly progress
| 2021-Q1 | 2023-01-02 |
| 2020-Q4 | 2022-12-27 |
| 2020-Q3 | 2023-01-02 |
| 2020-Q2 | 2022-12-27 |
| 2020-Q1 | 2023-01-02 |
| 2019-Q4 | 2023-01-02 |
| 2019-Q3 | 2022-12-27 |
| 2019-Q2 | 2022-12-27 |
| 2019-Q1 | 2022-12-27 |
| 2018-Q3 | 2022-12-27 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Aparna Architect Pvt. Ltd. | |
|---|---|---|
| Type | Company | |
| Escrow bank | BANK OF INDIA | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP111201800108-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP111201800108-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q4-Jan to Mar / 2020-2021 · 2023-01-02
- Q3-Oct to Dec / 2020-2021 · 2022-12-27
- Q2-Jul to Sep / 2020-2021 · 2023-01-02
- Q1-Apr to Jun / 2020-2021 · 2022-12-27
- Q4-Jan to Mar / 2019-2020 · 2023-01-02
- Q3-Oct to Dec / 2019-2020 · 2023-01-02
- Q2-Jul to Sep / 2019-2020 · 2022-12-27
- Q1-Apr to Jun / 2019-2020 · 2022-12-27
- Q4-Jan to Mar / 2018-2019 · 2022-12-27
- Q2-Jul to Sep / 2018-2019 · 2022-12-27
- 2021-Q1 · 2023-01-02
- 2020-Q4 · 2022-12-27
- 2020-Q3 · 2023-01-02
- 2020-Q2 · 2022-12-27
- 2020-Q1 · 2023-01-02
- 2019-Q4 · 2023-01-02
- 2019-Q3 · 2022-12-27
- 2019-Q2 · 2022-12-27
- 2019-Q1 · 2022-12-27
- 2018-Q3 · 2022-12-27