Overview
ARANYA CITY OF WOODLAND CHATOUD
ARANYA REAL ESTATES PVT. LTD · RAIPUR
Units209
Booked132 of 209As of 2026-06-30
Construction progress95%As of 2026-06-30
Completion2027-05-16Revised · Proposed 2023-10-16
Registered on2020-12-21
Approvals6
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 23 quarters |
| Technical report | |
| Site & area | 3 site details · 209 unit types |
| Construction & progress | 4 progress details · 23 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 161 documents · 13 source links |
Registration
Registration
| Promoter | ARANYA REAL ESTATES PVT. LTD | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA211220001170 | |
| Registered on | 2020-12-21 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2023-10-16 | |
| Revised completion | 2027-05-16 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Nazul clearance in case of Nazul Area |
| Enviornment Clearance |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXA-2026-03508 | CG RERA | Complaint | Disposed | 2026-05-14 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,11,38,000 | |
|---|---|---|
| Construction | ₹8,96,73,000 |
Quarterly money flows
| 2020-Q4 | ₹0 |
| 2021-Q1 | ₹0 |
| 2021-Q2 | ₹0 |
| 2021-Q3 | ₹13,300 |
| 2021-Q4 | ₹14,300 |
| 2022-Q1 | ₹7,300 |
| 2022-Q2 | ₹100 |
| 2022-Q3 | ₹52,902 |
| 2022-Q4 | ₹7,362 |
| 2023-Q1 | ₹7,321 |
| 2023-Q2 | ₹1,21,821 |
| 2023-Q3 | ₹7,361 |
| 2023-Q4 | ₹7,061 |
| 2024-Q1 | ₹7,841 |
| 2024-Q2 | ₹1,16,341 |
| 2024-Q3 | ₹63,61,176 |
| 2024-Q4 | ₹17,11,684 |
| 2025-Q1 | ₹5,24,085 |
| 2025-Q2 | ₹52,00,433 |
| 2025-Q3 | ₹74,16,516 |
| 2025-Q4 | ₹69,69,228 |
| 2026-Q1 | ₹61,92,382 |
| 2026-Q2 | ₹1,80,671 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 209 | |
|---|---|---|
| Booked | 132 | |
| Booked as of | 2026-06-30 |
Unit types
| F-1-1 | 1 | 0 |
| F-2-2 | 1 | 1 |
| F-3-3 | 1 | 1 |
| F-4-4 | 1 | 1 |
| F-5-5 | 1 | 0 |
| F-6-6 | 1 | 1 |
| F-7-7 | 1 | 1 |
| F-8-8 | 1 | 0 |
| F-9-9 | 1 | 1 |
| F-10-10 | 1 | 1 |
| F-11-11 | 1 | 1 |
| F-12-12 | 1 | 0 |
| F-13-13 | 1 | 1 |
| F-14-14 | 1 | 1 |
| F-15-15 | 1 | 1 |
| F-16-16 | 1 | 1 |
| F-17-17 | 1 | 1 |
| F-18-18 | 1 | 1 |
| F-19-19 | 1 | 0 |
| F-20-20 | 1 | 1 |
| F-21-21 | 1 | 1 |
| F-22-22 | 1 | 1 |
| F-23-23 | 1 | 1 |
| F-24-24 | 1 | 1 |
| G-1-1 | 1 | 1 |
| G-2-2 | 1 | 1 |
| G-3-3 | 1 | 1 |
| G-4-4 | 1 | 0 |
| G-5-5 | 1 | 1 |
| G-6-6 | 1 | 1 |
| G-7-7 | 1 | 1 |
| G-8-8 | 1 | 1 |
| G-9-9 | 1 | 0 |
| G-10-10 | 1 | 0 |
| G-11-11 | 1 | 1 |
| G-12-12 | 1 | 1 |
| G-13-13 | 1 | 1 |
| G-14-14 | 1 | 0 |
| G-15-15 | 1 | 1 |
| G-16-16 | 1 | 1 |
| G-17-17 | 1 | 1 |
| G-18-18 | 1 | 0 |
| G-19-19 | 1 | 1 |
| G-20-20 | 1 | 1 |
| G-21-21 | 1 | 1 |
| G-22-22 | 1 | 1 |
| G-23-23 | 1 | 1 |
| G-24-24 | 1 | 1 |
| G-25-25 | 1 | 1 |
| G-26-26 | 1 | 1 |
| G-27-27 | 1 | 0 |
| G-28-28 | 1 | 1 |
| G-29-29 | 1 | 1 |
| G-30-30 | 1 | 1 |
| G-31-31 | 1 | 1 |
| G-32-32 | 1 | 1 |
| G-33-33 | 1 | 1 |
| G-34-34 | 1 | 1 |
| G-35-35 | 1 | 1 |
| G-36-36 | 1 | 1 |
| G-37-37 | 1 | 1 |
| G-38-38 | 1 | 0 |
| G-39-39 | 1 | 1 |
| G-40-40 | 1 | 1 |
| G-41-41 | 1 | 1 |
| G-42-42 | 1 | 1 |
| G-43-43 | 1 | 1 |
| G-44-44 | 1 | 1 |
| G-45-45 | 1 | 1 |
| G-46-46 | 1 | 1 |
| G-47-47 | 1 | 1 |
| G-48-48 | 1 | 1 |
| G-49-49 | 1 | 0 |
| G-50-50 | 1 | 0 |
| G-51-51 | 1 | 0 |
| G-52-52 | 1 | 0 |
| G-53-53 | 1 | 1 |
| G-54-54 | 1 | 1 |
| G-55-55 | 1 | 1 |
| G-56-56 | 1 | 1 |
| G-57-57 | 1 | 1 |
| G-58-58 | 1 | 1 |
| G-59-59 | 1 | 1 |
| G-60-60 | 1 | 1 |
| G-61-61 | 1 | 1 |
| G-62-62 | 1 | 1 |
| G-63-63 | 1 | 1 |
| G-64-64 | 1 | 1 |
| G-65-65 | 1 | 1 |
| G-66-66 | 1 | 0 |
| G-67-67 | 1 | 0 |
| G-68-68 | 1 | 0 |
| G-69-69 | 1 | 0 |
| G-70-70 | 1 | 0 |
| G-71-71 | 1 | 1 |
| G-72-72 | 1 | 1 |
| G-73-73 | 1 | 1 |
| G-74-74 | 1 | 1 |
| G-75-75 | 1 | 1 |
| G-76-76 | 1 | 1 |
| G-77-77 | 1 | 1 |
| G-78-78 | 1 | 1 |
| G-79-79 | 1 | 1 |
| G-80-80 | 1 | 1 |
| G-81-81 | 1 | 1 |
| G-82-82 | 1 | 1 |
| G-83-83 | 1 | 1 |
| G-84-84 | 1 | 1 |
| G-85-85 | 1 | 1 |
| G-86-86 | 1 | 1 |
| G-87-87 | 1 | 1 |
| G-88-88 | 1 | 1 |
| G-89-89 | 1 | 1 |
| G-90-90 | 1 | 1 |
| G-91-91 | 1 | 1 |
| G-92-92 | 1 | 1 |
| G-93-93 | 1 | 1 |
| G-94-94 | 1 | 1 |
| G-95-95 | 1 | 1 |
| G-96-96 | 1 | 1 |
| G-97-97 | 1 | 0 |
| G-98-98 | 1 | 0 |
| G-99-99 | 1 | 1 |
| G-100-100 | 1 | 1 |
| G-101-101 | 1 | 1 |
| G-102-102 | 1 | 1 |
| G-103-103 | 1 | 1 |
| G-104-104 | 1 | 1 |
| G-105-105 | 1 | 1 |
| G-106-106 | 1 | 1 |
| G-107-107 | 1 | 1 |
| G-108-108 | 1 | 1 |
| G-109-109 | 1 | 1 |
| G-110-110 | 1 | 1 |
| G-111-111 | 1 | 0 |
| G-112-112 | 1 | 1 |
| G-113-113 | 1 | 1 |
| G-114-114 | 1 | 1 |
| G-115-115 | 1 | 1 |
| G-116-116 | 1 | 0 |
| G-117-117 | 1 | 1 |
| G-118-118 | 1 | 1 |
| G-119-119 | 1 | 1 |
| G-120-120 | 1 | 1 |
| G-121-121 | 1 | 1 |
| G-122-122 | 1 | 1 |
| G-123-123 | 1 | 1 |
| G-124-124 | 1 | 1 |
| G-125-125 | 1 | 1 |
| G-126-126 | 1 | 1 |
| G-127-127 | 1 | 1 |
| G-128-128 | 1 | 1 |
| G-129-129 | 1 | 1 |
| G-130-130 | 1 | 1 |
| G-131-131 | 1 | 1 |
| G-132-132 | 1 | 1 |
| G-133-133 | 1 | 0 |
| G-134-134 | 1 | 1 |
| G-135-135 | 1 | 0 |
| G-136-136 | 1 | 0 |
| LIG-1-1 | 1 | 0 |
| LIG-2-2 | 1 | 0 |
| LIG-3-3 | 1 | 0 |
| LIG-4-4 | 1 | 0 |
| LIG-5-5 | 1 | 0 |
| LIG-6-6 | 1 | 0 |
| LIG-7-7 | 1 | 0 |
| LIG-8-8 | 1 | 0 |
| LIG-9-9 | 1 | 0 |
| LIG-10-10 | 1 | 0 |
| LIG-11-11 | 1 | 0 |
| LIG-12-12 | 1 | 0 |
| LIG-13-13 | 1 | 0 |
| LIG-14-14 | 1 | 0 |
| LIG-15-15 | 1 | 0 |
| LIG-16-16 | 1 | 0 |
| LIG-17-17 | 1 | 0 |
| LIG-18-18 | 1 | 0 |
| LIG-19-19 | 1 | 0 |
| LIG-20-20 | 1 | 0 |
| LIG-21-21 | 1 | 0 |
| LIG-22-22 | 1 | 0 |
| LIG-23-23 | 1 | 0 |
| LIG-24-24 | 1 | 0 |
| LIG-25-25 | 1 | 0 |
| LIG-26-26 | 1 | 0 |
| LIG-27-27 | 1 | 0 |
| LIG-28-28 | 1 | 0 |
| LIG-29-29 | 1 | 0 |
| LIG-30-30 | 1 | 0 |
| LIG-31-31 | 1 | 0 |
| LIG-32-32 | 1 | 0 |
| LIG-33-33 | 1 | 0 |
| LIG-34-34 | 1 | 0 |
| LIG-35-35 | 1 | 0 |
| LIG-36-36 | 1 | 0 |
| LIG-37-37 | 1 | 0 |
| LIG-38-38 | 1 | 0 |
| LIG-39-39 | 1 | 0 |
| LIG-40-40 | 1 | 0 |
| LIG-41-41 | 1 | 0 |
| LIG-42-42 | 1 | 0 |
| LIG-43-43 | 1 | 0 |
| LIG-44-44 | 1 | 0 |
| LIG-45-45 | 1 | 0 |
| LIG-46-46 | 1 | 0 |
| LIG-47-47 | 1 | 0 |
| LIG-48-48 | 1 | 0 |
| LIG-49-49 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 95% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2023-10-16 | |
| Revised completion | 2027-05-16 |
Quarterly progress
| 2020-Q4 | 0% |
| 2021-Q1 | 0% |
| 2021-Q2 | 0% |
| 2021-Q3 | 0% |
| 2021-Q4 | 0% |
| 2022-Q1 | 0% |
| 2022-Q2 | 0% |
| 2022-Q3 | 0% |
| 2022-Q4 | 0% |
| 2023-Q1 | 0% |
| 2023-Q2 | 0% |
| 2023-Q3 | 0% |
| 2023-Q4 | 0% |
| 2024-Q1 | 0% |
| 2024-Q2 | 0% |
| 2024-Q3 | 8% |
| 2024-Q4 | 15% |
| 2025-Q1 | 45% |
| 2025-Q2 | 65% |
| 2025-Q3 | 80% |
| 2025-Q4 | 80% |
| 2026-Q1 | 95% |
| 2026-Q2 | 95% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ARANYA REAL ESTATES PVT. LTD | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTQ1Ng==
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Enviornment Clearance
- Modified Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Apartment Details · Sign in to download
- Garage Details · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Stilt Basement Parking · Sign in to download
- Open Parking · Sign in to download
- Common Area Facilities · Sign in to download
- Agent Details · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-05-14 · Sign in to download
- Interim order · 2026-02-26 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Enviornment Clearance
- Development Permission from competent authorities
- SM-EXA-2026-03508 · Sign in to download