ARANYA CITY OF WOODLAND PACHEDA

ARANYA REAL ESTATES PVT. LTD · RAIPUR
Units499
Booked261 of 499As of 2026-06-30
Construction progress98%As of 2026-06-30
Completion2027-09-27Revised · Proposed 2022-08-31
Registered on2018-06-23
Approvals2
Cases1

Sections

Property title & search report
Approvals2 approvals
Disputes & cases1 case
Contract & costs2 cost heads · 32 quarters
Technical report
Site & area3 site details · 499 unit types
Construction & progress4 progress details · 32 quarters
Developer & finance
Developer3 developer details
The evidence
Sources205 documents · 8 source links

Registration

Registration

PromoterARANYA REAL ESTATES PVT. LTD
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA230618000300
Registered on2018-06-23
Project typePlotted Development
Status (as filed)Ongoing
Proposed completion2022-08-31
Revised completion2027-09-27