DOSLDelhi NCR Workspace

Overview

ARETE, PHASE I

INTERNATIONAL LAND DEVELOPERS PVT. LTD. · Gurugram
Completion2023-03-31Revised · Proposed 2023-03-31
Registered on2019-02-08
Valid to2022-07-02
Approvals15

Sections

Property title & search report
Approvals15 approvals
Disputes & cases2 registration details
Contract & costs3 cost heads
Technical report
Site & area1 site detail · 11 unit types
Construction & progress2 progress details
Developer & finance
Developer4 developer details
The evidence
Sources28 documents · 3 source links

Registration

Registration

PromoterINTERNATIONAL LAND DEVELOPERS PVT. LTD.
DistrictGurugram
RegulatorHRERA Gurugram
Registration numberGGM/312/44/2019/06 DATED 08.02.2019
Registered on2019-02-08
Valid to2022-07-02
Status (as filed)Lapsed Project
Proposed completion2023-03-31
Revised completion2023-03-31