Ashiana Ekansh Phase I

Ashiana Housing Limited · Jaipur
Units168
Booked167 of 168As of 2025-12-31
Completion2027-02-28Revised · Proposed 2023-03-01
Registered on2022-12-10
Valid to2027-02-28
Approvals1

Sections

Property title & search report
Approvals1 approval · 1 occupancy certificate
Contract & costs3 cost heads · 1 quarter
Technical report
Site & area7 site details · 4 unit types
Construction & progress3 progress details · 1 quarter
Developer & finance
Developer4 developer details · 5 professional firms
The evidence
Sources51 documents · 7 source links

Registration

Registration

PromoterAshiana Housing Limited
DistrictJaipur
RegulatorRajasthan RERA
Registration numberRAJ/P/2022/2276
Registered on2022-12-10
Valid to2027-02-28
Project typeGroup Housing
Status (as filed)COMPLETED & OC ISSUED
Proposed completion2023-03-01
Revised completion2027-02-28