Overview
ASHIANA MAJESTIC
ASHIANA ESTATES PRIVATE LIMITED · Patna
Units20
Completion2019-07-31Proposed
Registered on2022-02-01
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 2 unit types |
| Construction & progress | 2 progress details · 8 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 25 documents · 11 source links |
Registration
Registration
| Promoter | ASHIANA ESTATES PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00519-2/635/R-624/2019 | |
| Registered on | 2022-02-01 | |
| Project type | Mixed Development(residential and commercial) | |
| Status (as filed) | Completed | |
| Proposed completion | 2019-07-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,86,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 755.76 | |
|---|---|---|
| Built-up (m²) | 1,495.44 | |
| FAR | 2.24 | |
| Towers | 1 | |
| Units | 20 |
Unit types
| Type | Units | Tower |
|---|---|---|
| Shop | 16 | ASHIANA MAJESTIC |
| 3 BHK | 4 | ASHIANA MAJESTIC |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2012-06-16 | |
|---|---|---|
| Proposed completion | 2019-07-31 |
Quarterly progress
| 2023-Q1 | 2023-04-10 |
| 2022-Q4 | 2023-01-09 |
| 2022-Q3 | 2022-11-24 |
| 2022-Q2 | 2022-11-24 |
| 2022-Q1 | 2022-11-24 |
| 2021-Q4 | 2022-03-10 |
| 2021-Q3 | 2022-03-10 |
| 2021-Q2 | 2022-03-10 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ASHIANA ESTATES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP226201800519-2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP226201800519-2
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- Project Registration Certificate
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q4-Jan to Mar / 2022-2023 · 2023-04-10
- Q3-Oct to Dec / 2022-2023 · 2023-01-09
- Q2-Jul to Sep / 2022-2023 · 2022-11-24
- Q1-Apr to Jun / 2022-2023 · 2022-11-24
- Q4-Jan to Mar / 2021-2022 · 2022-11-24
- Q3-Oct to Dec / 2021-2022 · 2022-03-10
- Q2-Jul to Sep / 2021-2022 · 2022-03-10
- Q1-Apr to Jun / 2021-2022 · 2022-03-10
- 2023-Q1 · 2023-04-10
- 2022-Q4 · 2023-01-09
- 2022-Q3 · 2022-11-24
- 2022-Q1 · 2022-11-24
- 2021-Q4 · 2022-03-10
- 2021-Q3 · 2022-03-10
- 2021-Q2 · 2022-03-10