Overview
Ashiana Nitara Phase 3
Ashiana Housing Limited · Jaipur
Units168
Booked0 of 168As of 2026-09-30
Completion2029-07-31Revised · Proposed 2025-10-01
Registered on2025-03-01
Valid to2029-07-31
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 12 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details · 4 professional firms |
| The evidence | |
| Sources | 54 documents · 7 source links |
Registration
Registration
| Promoter | Ashiana Housing Limited | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2025/3557 | |
| Registered on | 2025-03-01 | |
| Valid to | 2029-07-31 | |
| Project type | Group Housing | |
| Status (as filed) | INPROGRESS | |
| Proposed completion | 2025-10-01 | |
| Revised completion | 2029-07-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Date | Authority |
|---|---|---|
| Revised Building Plan | 2025-07-02 | Jaipur Development Authority |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹20,42,14,697 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹75,44,17,155 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2026-Q3 | ₹0 | ₹12,94,601.12 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 7,105.92 | |
|---|---|---|
| Built-up (m²) | 21,475.54 | |
| Towers | 168 | |
| Units | 168 | |
| Booked | 0 | |
| Booked as of | 2026-09-30 |
Unit types
| 2BHK + 2T | 73.19 | 24 | 24 | Tower/Block 1 |
| 2BHK + 2T | 73.19 | 4 | 4 | Tower/Block 1 |
| 3BHK + 2T | 93.96 | 23 | 17 | Tower/Block 1 |
| 3BHK + 2T | 93.96 | 4 | 2 | Tower/Block 1 |
| 3BHK + 2T (first Floor) | 93.96 | 1 | 1 | Tower/Block 1 |
| 2BHK + 2T | 73.19 | 48 | 0 | Tower/Block 2 |
| 2BHK + 2T | 73.19 | 8 | 8 | Tower/Block 2 |
| 2BHK + 2T | 73.19 | 24 | 0 | Tower/Block 3 |
| 2BHK + 2T | 73.19 | 4 | 4 | Tower/Block 3 |
| 3BHK + 2T | 93.96 | 23 | 23 | Tower/Block 3 |
| 3BHK + 2T | 93.96 | 4 | 4 | Tower/Block 3 |
| 3BHK + 2T (First Floor) | 93.96 | 1 | 0 | Tower/Block 3 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-10-01 | |
|---|---|---|
| Proposed completion | 2025-10-01 | |
| Revised completion | 2029-07-31 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2026-Q3 | 2026-10-28 | 0 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Ashiana Housing Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI Bank Ltd | |
| Other projects in this city pack | 23 |
Professional firms
| Architect | Ricky Mathur and Associates |
| Contractor | ESCEM WATER ENGINEERS |
| CA | Mundhra Rathi and Associates |
| Agent | Ashiana Maintenance Services |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=6kr91dbe5Y8T8zOAuSXp2Q
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/6kr91dbe5Y8T8zOAuSXp2Q
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=6kr91dbe5Y8T8zOAuSXp2Q%3D%3D&QuarterIdEnc=%2BKD7QcnAdOtELCm57RAuQA%3D%3D&PT=1&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=wYJPcz4%2FZ68%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- NOC for environment
- NOC from Airport Authority of India
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Other than Plotted)
- PROJECTCERTIFICATE
- APPROVALDOCREVISEDBUILPLAN · 2025-07-02
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Fire Fighting Provision
- Bankaffidavit · Sign in to download
- RCertificate
- MCAdata · Sign in to download
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- unitsPlanPath
- unitsPlanPath
- unitsPlanPath
- R1_filepath · Sign in to download
- R2_filepath · Sign in to download
- R3_filepath · Sign in to download
- RERABankStatementUpload · Sign in to download
- NoLienCertificateUpload
- Revised Building Plan · 2025-07-02