Overview
ASSET LIMELIGHT
ASSET HOMES PRIVATE LIMITED · EDAPALLY
Units47
Booked42 of 47
Construction progress100%As of 2023-04-08
Completion2023-10-30Revised · Proposed 2023-10-30
Registered on2021-05-26
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 21 unit types |
| Construction & progress | 5 progress details · 7 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 2 documents · 7 source links |
Registration
Registration
| Promoter | ASSET HOMES PRIVATE LIMITED | |
|---|---|---|
| District | Ernakulam | |
| Locality | EDAPALLY | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/042/2020 | |
| Registered on | 2021-05-26 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Completed | |
| Proposed completion | 2023-10-30 | |
| Revised completion | 2023-10-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | EYP3/329/COC/116/15 | 2016-10-26 | 2022-10-24 | KOCHI MUNICIPAL CORPORATION |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,755 | |
|---|---|---|
| Built-up (m²) | 10,189.51 | |
| Towers | 0 | |
| Units | 47 | |
| Booked | 42 |
Unit types
| 2BHK | 8 | 8 | ASSET LIMELIGHT |
| 2BHK | 1 | 1 | ASSET LIMELIGHT |
| 2BHK | 1 | 1 | ASSET LIMELIGHT |
| 2BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 8 | 7 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 7 | 6 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 7 | 5 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 1 | 0 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
| 3BHK | 1 | 1 | ASSET LIMELIGHT |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2023-04-08 | |
| Start | 1900-01-01 | |
| Proposed completion | 2023-10-30 | |
| Revised completion | 2023-10-30 |
Quarterly progress
| Quarter |
|---|
| 2022-2023 Q1 |
| 2022-2023 Q2 |
| 2022-2023 Q3 |
| 2021-2022 Q1 |
| 2021-2022 Q2 |
| 2021-2022 Q4 |
| 2020-2021 Q4 |
Extensions
| Valid to |
|---|
| 2023-10-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ASSET HOMES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | FEDERAL BANK | |
| Other projects in this city pack | 57 |
Professional firms
| Role | Firm |
|---|---|
| Architect | LIFE BY DESIGN ARCHITECTURE STUDIO |
Sources
Sources
Source URLs & documents
- https://nominatim.openstreetmap.org/search?q=edapally%2C+Ernakulam%2C+Kerala%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- https://rera.kerala.gov.in/projects/242
- https://rera.kerala.gov.in/projects?district=595&page=3
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=F5bjgZiBcJs2KvGCjYLlPO3wQp2F1yrydkdrMAfN%2BaAXQlORaeX7%2BAQYieMZSOl5k2Hc8kv8GYtp3qRiTXR%2B41m6l%2FdCD5WCZGE23dU%2FFdsXKE2zl4bxxrgnVr5OL24Wfzi4dDDUOSBlI%2BSMjdiYmoyrdJpWHnLwdLbvr0BIPDc%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=242&Division=1&UserID=30222&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Signed project certificate · 2021-05-26
- Extension certificate · 2021-12-02 · Sign in to download
- Extension order · Sign in to download