Overview
ASSET SUNNY DAYS
ASSET HOMES PRIVATE LIMITED · PEROORKADA
Units56
Booked56 of 56
Construction progress100%As of 2023-04-08
Completion2024-01-30Revised · Proposed 2024-01-30
Registered on2021-07-12
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 5 site details · 6 unit types |
| Construction & progress | 5 progress details · 8 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 9 documents · 6 source links |
Registration
Registration
| Promoter | ASSET HOMES PRIVATE LIMITED | |
|---|---|---|
| District | Thiruvananthapuram | |
| Locality | PEROORKADA | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/041/2020 | |
| Registered on | 2021-07-12 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Completed | |
| Proposed completion | 2024-01-30 | |
| Revised completion | 2024-01-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | 213/17-18 | 2018-03-31 | 2021-03-28 | THIRUVANANTHAPURAM CORPORATION |
| Development Permit | 213/17-18 | 2018-03-31 | 2021-03-28 | THIRUVANANTHAPURAM CORPORATION |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,300 | |
|---|---|---|
| Built-up (m²) | 8,621.05 | |
| Towers | 0 | |
| Units | 56 | |
| Booked | 56 |
Unit types
| 2BHK | 26 | 26 | ASSET SUNNY DAYS |
| 2BHK | 2 | 2 | ASSET SUNNY DAYS |
| 2BHK | 1 | 1 | ASSET SUNNY DAYS |
| 3BHK | 13 | 13 | ASSET SUNNY DAYS |
| 3BHK | 13 | 13 | ASSET SUNNY DAYS |
| 3BHK | 1 | 1 | ASSET SUNNY DAYS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2023-04-08 | |
| Start | 1900-01-01 | |
| Proposed completion | 2024-01-30 | |
| Revised completion | 2024-01-30 |
Quarterly progress
| Quarter |
|---|
| 2024-2025 Q1 |
| 2022-2023 Q1 |
| 2022-2023 Q2 |
| 2022-2023 Q3 |
| 2021-2022 Q1 |
| 2021-2022 Q2 |
| 2021-2022 Q4 |
| 2020-2021 Q4 |
Extensions
| Valid to |
|---|
| 2024-01-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ASSET HOMES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | FEDERAL BANK | |
| Other projects in this city pack | 57 |
Professional firms
| Role | Firm |
|---|---|
| Architect | AURA ARCHITECTS ENGINEERS AND PLANNERS |
Sources
Sources
Source URLs & documents
- https://nominatim.openstreetmap.org/search?q=peroorkada%2C+Thiruvananthapuram%2C+Kerala%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- https://rera.kerala.gov.in/projects/241
- https://rera.kerala.gov.in/projects?district=601&page=4
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=wrqD%2BJNEH958LaISZF9pRwy15LU5ox%2BpLKPr4u8EglQvLJ%2FUpB7%2BJJfZXzpqgFVDlSUqzzqIiNvt3xNQ9lDRVkJc6vagUXWaZjzCK7IubFYCzJvjuTgNYaTM4HAE7azsYkcDn6x3V2wS5LsgN9LvVr1%2FhFZuhKvbpW1yStnAl8w%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=241&Division=1&UserID=30222&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Extension Certificate · Sign in to download
- Signed project certificate · 2021-07-12
- Extension certificate · 2021-12-01 · Sign in to download
- Consent to establish (Clearance from Pollution Control Board) · 2023-04-04 · Sign in to download
- Declaration by the Promoter - Form No. 6 · 2023-04-04 · Sign in to download
- Final Fire NOC · 2023-04-04
- Occupancy Certificate · 2023-04-04