Overview
ATAL AWAS AT KANHARPURI PHASE -II
CHHATTISGARH HOUSING BOARD DIVISION-DHAMTARI · DHAMTARI
Units118
Booked93 of 118As of 2018-09-30
Construction progress100%As of 2018-09-30
Completion2018-12-31Proposed
Registered on2018-08-02
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 2 cost heads |
| Technical report | |
| Site & area | 3 site details · 1 unit type |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 25 documents · 8 source links |
Registration
Registration
| Promoter | CHHATTISGARH HOUSING BOARD DIVISION-DHAMTARI | |
|---|---|---|
| District | DHAMTARI | |
| Regulator | CG RERA | |
| Registration number | PCGRERA020818000648 | |
| Registered on | 2018-08-02 | |
| Project type | Group Housing | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2018-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Nazul clearance in case of Nazul Area |
| Enviornment Clearance |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 | |
|---|---|---|
| Construction | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 118 | |
|---|---|---|
| Booked | 93 | |
| Booked as of | 2018-09-30 |
Unit types
| Type | Carpet (m²) | Units | Booked |
|---|---|---|---|
| 1BHK | 280 | 118 | 3 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2018-09-30 | |
| Proposed completion | 2018-12-31 |
Quarterly progress
| Quarter | Progress |
|---|---|
| 2018-Q3 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | CHHATTISGARH HOUSING BOARD DIVISION-DHAMTARI | |
|---|---|---|
| Type | Authority | |
| Other projects in this city pack | 9 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=NzQw
- Document
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Modified Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Apartment Details · Sign in to download
- Garage Details · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Stilt Basement Parking · Sign in to download
- Open Parking · Sign in to download
- Common Area Facilities · Sign in to download
- Agent Details · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Nazul clearance in case of Nazul Area
- Enviornment Clearance
- Development Permission from competent authorities