ATAL VIHAR YOJNA PUSSOURE RAIGARH

CHHATTISGARH HOUSING BOARD DIVISION-RAIGARH · RAIGARH
Units9
Booked9 of 9As of 2026-06-30
Construction progress44%As of 2026-06-30
Completion2028-10-29Revised · Proposed 2028-06-29
Registered on2025-07-07
Approvals5

Sections

Property title & search report
Approvals5 approvals
Contract & costs2 cost heads · 4 quarters
Technical report
Site & area3 site details · 9 unit types
Construction & progress4 progress details · 4 quarters
Developer & finance
Developer3 developer details
The evidence
Sources39 documents · 8 source links

Registration

Registration

PromoterCHHATTISGARH HOUSING BOARD DIVISION-RAIGARH
DistrictRAIGARH
RegulatorCG RERA
Registration numberPCGRERA070725001944
Registered on2025-07-07
Project typeGroup Housing
Status (as filed)New
Proposed completion2028-06-29