Overview
ATH THE PALLADIUM
M/s. ASSET TREE HOMES · CHENNAI
Units10
Completion2027-09-01Proposed
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Technical report | |
| Site & area | 2 site details · 2 unit types |
| Construction & progress | 1 progress detail · 2 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 15 documents · 7 source links |
Registration
Registration
| Promoter | M/s. ASSET TREE HOMES | |
|---|---|---|
| District | Chennai | |
| Locality | CHENNAI | |
| Regulator | TNRERA | |
| Registration number | TN/29/Building/0060/2025 | |
| Project type | Building | |
| Status (as filed) | Progress of Work as on December 2025 | |
| Proposed completion | 2027-09-01 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Planning permission | OL-PP/NHRB/0518/2024 | 2024-09-02 | 2032-09-01 | The Member Secretary - CMDA |
| Building permit | CEBA/WDCN12/00474/2024 | 2024-09-26 | Greater Chennai Corporation |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 550 | |
|---|---|---|
| Units | 10 |
Unit types
| Type | Units | Tower | Floor |
|---|---|---|---|
| Floor Area < 60 Sq.M | 0 | 0 | 0 |
| Floor Area > 60 Sq.M: | 10 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2027-09-01 |
|---|
Quarterly progress
| Quarter |
|---|
| 2025-Q4 |
| 2026-Q3 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M/s. ASSET TREE HOMES | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | IDBI Bank | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.tn.gov.in/project-details/76ae14d0-c77a-11ef-84e1-498eadae7587
- https://rera.tn.gov.in/public-view1/building/pfirm/76aaf4a0-c77a-11ef-894c-d7067e959a70
- https://rera.tn.gov.in/public-view2/building/pfirm/42523a70-c856-11ef-9a69-250bc3527ee5
- https://rera.tn.gov.in/registered-building/tn
- Document
- Progress of Work as on December 2025
- Planning Permission Approval / Renewal Letter
- Approved Plan with Local Body Seal(Upload in Readable Format)
- Building Permit Letter
- View GLV Document · Sign in to download
- Encumbrance Certificate from the date of approval of planning permission to RERA submission date
- Carpet Area Statement
- Carpet Area Statement (Duly signed by registered architect / promoter with seal)
- Structural Stability Certificate along with Structural Design Calculation (Indicating Site Address & No. of Floors as per Approved Plan)
- Design & Drawing for Structural Stability
- Declaration (Form B) · Sign in to download
- Stage of Construction & Site Photographs with date · Sign in to download
- Bank statement for the last one year duly signed by the Bank to be enclosed
- Furnish the details Flat-wise
- Planning permission · 2024-09-02
- Building permit · 2024-09-26
- 2025-Q4