Overview
ATHENA
BRAHMA DEVELOPERS PVT. LTD. · Gurugram
Registered on2017-09-20
Valid to2022-12-31
Cases5
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 5 cases · 2 registration details |
| Contract & costs | 1 quarter |
| Technical report | |
| Construction & progress | 1 quarter |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 6 documents · 5 source links |
Registration
Registration
| Promoter | BRAHMA DEVELOPERS PVT. LTD. | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 239 OF 2017 DATED 20.09.2017 | |
| Registered on | 2017-09-20 | |
| Valid to | 2022-12-31 | |
| Status (as filed) | Lapsed Project |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| RERA-GRG-5394-2019 | HRERA Gurugram | Pending |
| RERA-GRG-2896-2022 | HRERA Gurugram | |
| RERA-GRG-2561-2022 | HRERA Gurugram | Pending |
| RERA-GRG-3353-2022 | HRERA Gurugram | Pending |
| RERA-GRG-5183-2022 | HRERA Gurugram | Pending |
Complaints & cases
| Cases | 5 |
|---|
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2022-12-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2026-Q3 | ₹0 | ₹1,83,71,800 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Quarterly progress
| Quarter | Filed on | Sold |
|---|---|---|
| 2026-Q3 | 2026-10-12 | 0 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BRAHMA DEVELOPERS PVT. LTD. | |
|---|---|---|
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/assistancecontrol/print_quarterly_schedules/Mg==/NDU3/MjAxOQ==
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/MjM5IG9mIDIwMTcgREFURUQgMjAuMDkuMjAxNw==
- https://haryanarera.gov.in/view_project/quaterly_schedule_preview_open
- https://nominatim.openstreetmap.org/search?q=sector+16%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2017-09-20
- SELF CERTIFICATE OF THE PROMOTER TO SHOW THE NUMBER OF PLOTS/APARTMENTS SOLD UPTO THE DATE OF REGISTRATION AND THE PLOTS/APARTMENTS SOLD IN EACH QUARTER THERE-AFTER. · 2026-10-12
- CERTIFICATE OF THE REGISTERED ARCHITECT OF THE PROJECT CERTIFYING THE PERCENTAGE OF THE CONSTRUCTION WORK UPTO DATE; THE PERCENTAGE OF CONSTRUCTION WORK UNDERTAKEN DURING THE PREVIOUS QUARTER; AND THE PERCENTAGE OF WORK REMAINING. · 2026-10-12
- CERTIFICATE OF CHARTERED ACCOUNTANT OF THE PROJECT TO SHOW TOTAL AMOUNT OF MONEY RECEIVED FROM ALLOTTEES AND OTHER SOURCES; MONEY DEPOSITED IN THE ESCROW ACCOUNT; THE MONEY WITHDRAWN FROM THE ESCROW ACCOUNT; AMOUNT OF FUNDS INVESTED ON THE CONSTRUCTION WORK OF THE PROJECT INCLUDING PURCHASE OF MATERIALS. THE CERTIFICATE SHALL ALSO CONTAIN INFORMATION RELATING TO THE QUANTUM OF MONEY WITHDRAWN BY THE PROMOTERS FOR THE PURPOSES OTHER THAN FOR THE PROJECT · 2026-10-12
- A CERTIFICATE OF THE REGISTERED ENGINEER CERTIFYING PERCENTAGE OF INFRASTRUCTURE WORK CARRIED OUT. THE INFRASTRUCTURE WORK INCLUDES ROADS, SEWERAGE SYSTEM, STORM WATER DRAINAGE SYSTEM, WATER SUPPLY, AND ELECTRICITY SUPPLY. · 2026-10-12
- A SEPARATE CERTIFICATE BY A CHARTERED ACCOUNTANT CERTIFYING THE TOTAL CUMULATIVE COST INCURRED ON CONSTRUCTION OF THE PROJECT UPTO END OF LAST QUARTER; THE PERCENTAGE OF REMAINING WORK IN TERMS OF COST, AND THE ESTIMATED BALANCE COST TO BE INCURRED FOR COMPLETION OF THE PROJECT. · 2026-10-12