Overview
ATLANTIS
M. AHUJA PROJECT INDIA PVT. LTD. · RAIPUR
Units60
Booked60 of 60As of 2024-06-30
Construction progress99%As of 2024-06-30
Completion2019-05-31Proposed
Registered on2018-06-27
Approvals1
Cases2
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 2 cases |
| Contract & costs | 2 cost heads · 24 quarters |
| Technical report | |
| Site & area | 3 site details · 60 unit types |
| Construction & progress | 3 progress details · 24 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 92 documents · 8 source links |
Registration
Registration
| Promoter | M. AHUJA PROJECT INDIA PVT. LTD. | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA270618000354 | |
| Registered on | 2018-06-27 | |
| Project type | Commercial | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2019-05-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXP-2024-02249 | CG RERA | Complaint | Disposed | 2024-08-05 |
| M-COM-2019-00415 | CG RERA | Complaint | Disposed | 2021-10-26 |
Complaints & cases
| Cases | 2 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,42,30,000 | |
|---|---|---|
| Construction | ₹8,29,64,000 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹0 |
| 2019-Q1 | ₹0 |
| 2019-Q2 | ₹0 |
| 2019-Q3 | ₹0 |
| 2019-Q4 | ₹0 |
| 2020-Q1 | ₹0 |
| 2020-Q2 | ₹0 |
| 2020-Q3 | ₹0 |
| 2020-Q4 | ₹0 |
| 2021-Q1 | ₹0 |
| 2021-Q2 | ₹0 |
| 2021-Q3 | ₹0 |
| 2021-Q4 | ₹0 |
| 2022-Q1 | ₹0 |
| 2022-Q2 | ₹0 |
| 2022-Q3 | ₹0 |
| 2022-Q4 | ₹0 |
| 2023-Q1 | ₹0 |
| 2023-Q2 | ₹0 |
| 2023-Q3 | ₹0 |
| 2023-Q4 | ₹0 |
| 2024-Q1 | ₹0 |
| 2024-Q2 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 60 | |
|---|---|---|
| Booked | 60 | |
| Booked as of | 2024-06-30 |
Unit types
| COMMERCIAL | 110.28 | 1 | 1 |
| COMMERCIAL | 47.19 | 1 | 1 |
| COMMERCIAL | 47.19 | 1 | 1 |
| COMMERCIAL | 47.19 | 1 | 1 |
| COMMERCIAL | 47.19 | 1 | 1 |
| COMMERCIAL | 44.97 | 1 | 1 |
| COMMERCIAL | 47.1 | 1 | 1 |
| COMMERCIAL | 47.1 | 1 | 1 |
| COMMERCIAL | 58.34 | 1 | 1 |
| COMMERCIAL | 51.84 | 1 | 1 |
| COMMERCIAL | 114.83 | 1 | 1 |
| COMMERCIAL | 48.96 | 1 | 1 |
| COMMERCIAL | 48.96 | 1 | 1 |
| COMMERCIAL | 48.96 | 1 | 1 |
| COMMERCIAL | 48.96 | 1 | 1 |
| COMMERCIAL | 46.73 | 1 | 1 |
| COMMERCIAL | 48.77 | 1 | 1 |
| COMMERCIAL | 48.96 | 1 | 1 |
| COMMERCIAL | 60.57 | 1 | 1 |
| COMMERCIAL | 53.7 | 1 | 1 |
| COMMERCIAL | 119.19 | 1 | 1 |
| COMMERCIAL | 50.82 | 1 | 1 |
| COMMERCIAL | 50.82 | 1 | 1 |
| COMMERCIAL | 50.82 | 1 | 1 |
| COMMERCIAL | 50.82 | 1 | 1 |
| COMMERCIAL | 48.4 | 1 | 1 |
| COMMERCIAL | 50.54 | 1 | 1 |
| COMMERCIAL | 50.73 | 1 | 1 |
| COMMERCIAL | 63.17 | 1 | 1 |
| COMMERCIAL | 56.21 | 1 | 1 |
| COMMERCIAL | 125.61 | 1 | 1 |
| COMMERCIAL | 53.42 | 1 | 1 |
| COMMERCIAL | 53.42 | 1 | 1 |
| COMMERCIAL | 53.42 | 1 | 1 |
| COMMERCIAL | 53.42 | 1 | 1 |
| COMMERCIAL | 50.73 | 1 | 1 |
| COMMERCIAL | 53.14 | 1 | 1 |
| COMMERCIAL | 53.42 | 1 | 1 |
| COMMERCIAL | 67.08 | 1 | 1 |
| COMMERCIAL | 59.83 | 1 | 1 |
| COMMERCIAL | 127.93 | 1 | 1 |
| COMMERCIAL | 54.44 | 1 | 1 |
| COMMERCIAL | 54.44 | 1 | 1 |
| COMMERCIAL | 54.44 | 1 | 1 |
| COMMERCIAL | 54.44 | 1 | 1 |
| COMMERCIAL | 51.75 | 1 | 1 |
| COMMERCIAL | 54.16 | 1 | 1 |
| COMMERCIAL | 54.44 | 1 | 1 |
| COMMERCIAL | 68.47 | 1 | 1 |
| COMMERCIAL | 61.32 | 1 | 1 |
| COMMERCIAL | 132.29 | 1 | 1 |
| COMMERCIAL | 56.3 | 1 | 1 |
| COMMERCIAL | 56.3 | 1 | 1 |
| COMMERCIAL | 56.3 | 1 | 1 |
| COMMERCIAL | 56.3 | 1 | 1 |
| COMMERCIAL | 53.51 | 1 | 1 |
| COMMERCIAL | 55.93 | 1 | 1 |
| COMMERCIAL | 56.3 | 1 | 1 |
| COMMERCIAL | 71.16 | 1 | 1 |
| COMMERCIAL | 73.21 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 99% | |
|---|---|---|
| As of | 2024-06-30 | |
| Proposed completion | 2019-05-31 |
Quarterly progress
| 2018-Q3 | 100% |
| 2018-Q4 | 95% |
| 2019-Q1 | 95% |
| 2019-Q2 | 95% |
| 2019-Q3 | 95% |
| 2019-Q4 | 95% |
| 2020-Q1 | 95% |
| 2020-Q2 | 95% |
| 2020-Q3 | 99% |
| 2020-Q4 | 99% |
| 2021-Q1 | 95% |
| 2021-Q2 | 95% |
| 2021-Q3 | 99% |
| 2021-Q4 | 99% |
| 2022-Q1 | 99% |
| 2022-Q2 | 99% |
| 2022-Q3 | 99% |
| 2022-Q4 | 99% |
| 2023-Q1 | 99% |
| 2023-Q2 | 99% |
| 2023-Q3 | 99% |
| 2023-Q4 | 99% |
| 2024-Q1 | 99% |
| 2024-Q2 | 99% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | M. AHUJA PROJECT INDIA PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Escrow bank | UCO Bank | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=NDQx
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2024-08-05 · Sign in to download
- Final order · 2021-10-26 · Sign in to download
- Approval Letter of Town And Country Planning
- SM-EXP-2024-02249 · Sign in to download
- M-COM-2019-00415 · Sign in to download